30 MARCH 2015
COAL STORAGE
Excavato
r
Compact
or
Project Summarize :
1. 2 unit Bulldozer push the soil from
the insitu area (as figure no.1) to
the bunker area (as the green
line).
2. 1 excavator in the morning make
the good slope around bunker
area. Then after lunch the
excavator load the soil from
innsitu area to 1 unit OHT and
dumping in bunker area. Then at
03.40 p.m the excavator back to
bunker area to make the bunker
because the TSS operator have
meeting in office.
3. 1 compactor make good berm
around bunker area.
Heavy machine use :
Bulldozer
2 unit
OHT
1 unit
Excavator
1 unit
Compactor
1 unit
Problem:
Counter measure :
Plan next day
Continue move the little bit of soil
from insitu area (as figure no.1) to
bunker area use the bulldozer,
excavator and OHT, then make good
bunker.