PKM Section I

23rd April, 2018

Site Observation.
By: QA/QC Dept: Multan
Headquarter
PKM Sukkur to Multan Sec-01

FINDINGS
APRIL, 23 2018
PKM Sukkur to Multan Sec-01

• Cement mortar detachment between adjacent curb block


• Curing of NJB slip form construction
• Cracks in NJB
• Bearing Pads Deformation
• Compaction of earthen shoulder
• ITS
• Record Keeping
• Approval of method statements
• Approval of JMF
• Bitumen Testing
• Safety
PKM Sukkur to Multan Sec-01
23rd April 2018

The soil has been used for the B zone is contaminated & have lumps @ Km 380+100
PKM Sukkur to Multan Sec-01
23rd April 2018

B Zone above sand fill the material appeared to be the plastic nature with lumps
PKM Sukkur to Multan Sec-01
23rd April 2018

• A remarkable detachment of cement mortar between two adjacent chute blocks


PKM Sukkur to Multan Sec-01
23rd April 2018

• Damaged prime coat


PKM Sukkur to Multan Sec-01
23rd April 2018

Crack progression
PKM Sukkur to Multan Sec-01
23rd April 2018

Matching of NJB profile


PKM Sukkur to Multan Sec-01
23rd April 2018

Curb block
• Fill behind curb block for earthen shoulder is required 32.0 cm must be filled in two
layers of 15 cm thickness prior to the construction of shoulders
• Damaged curb block
PKM Sukkur to Multan Sec-01
23rd April 2018

The installation of pillars for Guard Rail without compacted layers of shoulder
PKM Sukkur to Multan Sec-01
23rd April 2018

Honey combing at retaining wall


PKM Sukkur to Multan Sec-01
23rd April 2018

• Air voids or air bubble at retaining wall


PKM Sukkur to Multan Sec-01
23rd April 2018

• Placement of steel with out any protection under sky


PKM Sukkur to Multan Sec-01
23rd April 2018

The inferior class of repair of girder damaged during transportation


PKM Sukkur to Multan Sec-01
23rd April 2018

Rain or water cut & the material behavior shows that it is NP


PKM Sukkur to Multan Sec-01
23rd April 2018

Debris or rubbish stacked along the side of NJB


PKM Sukkur to Multan Sec-01
23rd April 2018

Segregated & loose aggregate base material at abutment of Bridge


THANK YOU