You are on page 1of 10

W41 REVIEW AND PLAN W42

OKTOBER 2022
MAA JOB SITE OBI
PLAN WEEK 42
 Working Hours Plan

 PA, UA, Production Equipment

TAILING
 Equipment Required.
:
 Production Target

14 th PROJECT
Oktober – 20 Oktober 2022
th
 Fuel Consumption Estimation

 Plan Fleet Map


LAND CLEARING REVIEW

Total Clearing Review


PLAN : 105.000 m2
ACTUAL : 87.500 m2
LAND CLEARING TO DATE
Working Hours TAILING

TOTAL PLAN WORKING


Working Time HOURS :
Day Shift 07.00 – 19.00
Night Shift 19.00 – 07.00 50,3%
Long Shift 07.00 – 00.00
84,5 HOURS
Plan Equipment PA & UA 35
Productivity Plan
(Land Clearing & Quarry)

Total Land Clearing Area


Plan Week 42 :
=105,000 m²
=10,5 ha
Plan Quarry :
= 6,760 BCM
W42 Plan
Unit Required & Fuel
Consumption Estimate

TOTAL UNIT TOTAL FUEL


TAILING
52,386 Liter
PLAN MAP

PLAN CLEARING WEEK 42

• Plan Clearing at Area Segment

C-E-F Tailing

• Move from West to East

• Quarry Stocking at Segment B

• Road Maker & Maintenance

Continue
Thank You