Revamped

Permit To Work
What is a Permit to Work?
 A Work Permit is a formal written document used to control certain
types of work (which may have potential of accidents).
 It is also a means of communication between Management, Plant
Supervisors, Operators and those who carry out the work.

2
Features of Work Permit System
 Clear identification of who may authorize particular jobs (and any
limits to their authority)
 Who is responsible for specifying the necessary precautions and
permission of work.
 Instructions in the issue and use of Permits

 Monitoring & Auditing to ensure that the system works as intended.

3
Advantages of using Work Permits
Ensures appropriate people are authorized to carry out
designated work.
Makes it clear to people carrying out the work the exact
identity, nature and extent of the job and the hazards
involved.
Specifies the precautions which need to be taken.
Ensures that the person in charge of the area is aware of all
the work being done under the work permit system.
Provides a formal handover procedure for use when the
permit is issued for a period longer than one shift.

4
VALIDATION PERIOD

PTW validation period has been revised; revamped


procedure has following validation period
 Maximum time for validation is 03 normal Operations shift. (Normal: 8

hrs shift 02 extensions of 8 hrs & 01 extensions for 12 hrs shifts)


 Overall timing shouldn’t exceed 24hours in any case.

 Revalidation to be done at work place & within 2 hrs of next shift

start by USE, Operator & technician at work place.


 Permits should be closed within 02 hrs. after completion of Job.

 Applicable on all permits; irrespective of their types.

FATIMAFERT LIMITED REVAMPED PTW


5 SYSTEM
Permit to Work Authority Matrix

PTW can only be issued and accepted by all authorized individuals.


There are certain permits which requires elevated level for issuer /
acceptor or authorization considering the associated hazards / risk for
specific job. Below matrix is developed ensuring appropriate skill;
experience and authorization level of issuance and acceptance of permits
to be ensured and complied for safer handover and execution of job.

Note:- In Major outages/Turnarounds when area is declassified, all authorized


acceptors can accept all type of PTWs including mentioned above except clause “7.b, 7.d;
9.b; 9.c; & 9.d”

FATIMAFERT LIMITED REVAMPED PTW


6 SYSTEM
Sr. # PTW Type Issuer Acceptor
1 Cold PTW (without JSA) All Authorized Issuer All Authorized Acceptor
2 Critical jobs involved JSA (any PTW) USE, Authorized by SEIC. Area Engr / Sub Eng.
3 LOPE USE Area Engr / Sub Eng.
All authorized issuer Motor Pool Authorized
4 Vehicle Entry
acceptor
Radiography Inspection Engr. Inspection Personal
Cosign by USE,
5 Authorized by SEIC.

6 Excavation and Civil Work All Authorized Issuer All Authorized Acceptor
7 HOT WORK PERMITS
Minor Jobs like Chipping; drilling; power
brushing; grinding / welding on structure /
7.a supports Photography etc. All Authorized Issuer All Authorized Acceptor

HWP (Tie Ins or live circuits i.e. Pressure >


7.b USE Area Engr / Sub Eng.
10 Kg/CM2 or Temp > 150 0C.)

7.c HWP (except 7.a & 7.b & without JSA) USE Authorized acceptors till Sup
USE
7.d Hot Tap Authorization By SEIC Area Engr / Sub Eng.

8 CONFINED SPACE PERMITS


8.a All permits except open pits USE Area Engr / Sub Eng.
8.b Pits; excavated areas etc. USE All Authorized Acceptor
7 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
9 ELECTRICAL PTW (DETAILS SECTION # 6.3
USE
Cosigned by All Authorized All Authorized Electrical
9.a On De-energized circuits
Electrical Tech; Acceptors
Authorized by SEIC
Energized control/instrumentation USE
loops/circuit from 25~220 Volts outside Cosigned by Electrical Engr / Sub
sub-station. Eng. Electrical Engr / Sub Eng.
9.b Authorized by SEIC. Off Hours;
Off Hours; Cosign By: All Electrical Tech
Shift Sub Eng (Shift Foreman)
Energized Circuits ≤ 440 Volts inside
Substations USE, Cosigned by Electrical Tech.;
Authorized by Electrical Engr / Sub Electrical Engr / Sub Eng.
9.c Eng. Off Hours;
Off Hours; Authorized By: All Electrical Tech
Shift Sub Eng (Shift Foreman)
Energized Circuits above 440 Volts inside
Substations. USE,
Electrical Engr / Sub Eng.
Cosigned by Electrical Engr / Sub
9.d Presence of Electrical UM /
Eng.;
SH Mandatory on the Job.
Authorized by Electrical UM / SH
10 INSTRUMENT PTW (DETAILS SECTION # 6.4; PAGE # 21)
USE
10.a All Non SCD All Authorized Acceptor
USE, Cosigned by Instrument
Engr / Sub Eng. Instrument Engr / Sub Eng.
10.b All SCD Authorized by SEIC. Off Hours;
Off Hours; Cosign By: All Instrument Tech
Shift Sub Engr (Shift Foreman)
All authorized issuer
10.c Energized circuit below ≤ 24 Volts All Authorized Acceptor
8 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
Permit to Work Types
Revamped procedure has 9 following types;
1. Cold Work Permit (Green)
2. Hot Work Permit (Red)

3. Electrical Work Permit (Purple)

4. Instrument Work Permit (Pink) for DCS, PLC, Rack Panel Jobs.

5. Radiography Permit (Yellow)

6. Confined Space Entry Permit (Blue)

7. Vehicle Entry Permit (Grey)

8. Excavation and Civil Work Permit (White)


9 FATIMAFERT LIMITED REVAMPED PTW SYST
9. Lifting
EM Over Process Equipment Permit (Orange)
Cold PTW (Green)
A Cold Permit to Work is issued for work, not including the use of naked
flames or equipment which could produce a spark or any other source of
ignition, on prescribed plant or equipment.
Validation Period : 24hr Max (2 revalidation for 8 hr or 01 for 12 hrs)
 USE will initiate and Acceptor will be Technician for Non-critical

job.
 Acceptor will be Area Engr / Sub Engr for critical job.

 Cold PTW for JSA related jobs will be accepted / issued not lower

than Sub Engr level.


10 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
HOT PTW (RED)
A Hot Work Permit is required for any job where the heat
generated is of sufficient magnitude and intensity to cause
ignition of any flammable liquids, gases or any other
material.
Validation Period; 24hr Max (2 revalidation for 8 hr or 01 for
12 )

• Preparations of HWP will be under CWP.

• If Hot work related jobs required JSA will be accepted /

issued not lower than Sub Engr level.


• HWP checklist checks has made part of PTW and should
11 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
Hot Work Permit Exemption
During turnaround / Shutdown, if there is no fire or explosion
hazard in area then on the recommendation of UEIC, the
Production Manager of the relevant site can declare area as
declassified and may obtain HSE waiver for following;
• Photography can be done under cold PTW.
•No PTW required for Photography with classified camera in
operating areas or in control rooms building however, prior verbal
approval has to be taken from USE /SEIC.

12 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
CONFINED SPACE ENTRY WORK
PERMIT
A Confined Space Entry permit is to be obtained before any person enters a location defined
as Confined Space Entry.
Validity:- 24 Hr max.
Authorization:- USE can issue CSEP followed by approval by the SEIC. Only relevant
section Engr / Sub Engr will be acceptor for other then open pit, skirts etc.
Confined Space Entry Standard
Examples of confined spaces include tanks, vessels, certain pits, ditches, sewers/septic tanks,
excavations; exhaust stacks and vessel support skirts and all excavations greater than 3.5
feet in depth. Entry will be allowed only after compliance with the specific guidelines of
this standard.
 It is mandatory to provide proper and safe means of entry and egress for all confined
spaces. This Rule is applicable for all confined spaces, whether these are permit required
or non-permit required.
 Special Considerations, Prior to confined space entry, all interfaces involved in
confined space entry must discuss / agree on the safety precautions to be taken for
safe execution of the job.
13 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
CONFINED SPACE ENTRY
PERMIT
Isolating Confined Spaces:- Physically disconnect or blind all process material lines,
including nitrogen purging lines. Put blind as close to the vessel as possible.
For shared stack / duct; the duct or stack to be disconnected or blinded.
Lock-out
All power driven equipment as associated with the permit must be LOTOTO
Agitated / rotating equipment must be disconnected & tagged from power source.
General Requirements;
 A safety harness and rope for every individual who will enter the confined space.
 Authorized individuals are allowed to enter only. (list will be available with Standby
man)
Secure Rotating Equipment
 The drive coupling must be disconnected or.
 The leads at the motor must be disconnected.
 Shafts for fan blades or agitators must be secured to prevent their movement before
anyone enters the tank if a draft or other force can produce free wheeling.
14 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
Electrical Work Permit (Purple Card)
Required for any work electrical system inside Sub Stations including grounding of
system.
Note:- This excludes visual inspection of motors; electrical isolation of Motors or
miscellaneous electrical field related work, which will require a cold Work Permit.
Validity : 24 Hrs Max ( 2 validation for 8 hr shifts or 1 revalidation of 12 hrs shift)
 Electrical team will take care of job themselves however job will be informed to O&U
operations & SEIC
 Power source to be disconnected strictly in accordance LOTOTO.

 Issuer himself or via an Tech to personally verify that correct power source turned off /
disconnected and has been locked and properly tagged

Electrical Permit Exemption;


Following electrical jobs are exempted form electrical permit;
 Electrical work carried out in Electrical Shop other than on live electrical circuits, no
Work Permit is required.
15 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
Electrical PTW ISSUANCE
Permit de-energized circuits; initiated by USE authorized by SEIC co-signed by All
Authorized Electrical Tech confirming regarding electrical isolations.

Work on the following live circuits


 Testing of electrical potential ; Local checking of current with clamp-on ampere meter
 Testing operation and adjustment of electrical control circuit.
 Bagging machines; Man-lift servicing / repair.
Energized equipment inside sub stations with voltage below 440 V, initiated by USE co-

signed by Electrical Tech. Authorized by Electrical Engr / Sub Eng. SEIC info only
High voltage circuits i.e. 440V or above; initiated by USE Cosigned by Electrical Engr /

Sub Eng. Authorized by Electrical UM / SH

16 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
Electrical PTW Exemption
Following electrical jobs are exempted from electrical
permit;
1.Electrical work carried out in Electrical Shop
other than on live electrical circuits, no PTW is
required.
2.Routine readings from panels in Substation
I.e. Current measurement etc.
General services jobs in side Substation like tube lights
replacement, air conditioner repairing (Relevant PTW to
be obtained e.g. CWP)

17 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
Instrument Work Permit
This permit must be obtained while carrying out jobs on the following:
 DCS , ESD Systems ,PLCs and Energized Field Instrumentation
 Work inside marshaling cabinet; Annunciator panels
 Other instruments & control systems e.g. Anemometer, Recorders, Vibration Monitors etc.
 Safety Critical devices; USE will initiate; Instt Engr / Sub-Engr shall fill and co-sign the E&I
related part. Approved / authorized by the SEIC keeping UM in loop.
 Non-Safety Critical devices : USE can authorize; while Inst Engr / Sub Engr or Authorized tech to
cosign the Work Permit after filling the E&I related part.
 Work on energized devices; less than & equal 24V, USE to initiate & accepted by respective
instrument acceptor.
 energized circuit 24 ~ 220V; initiated by USE & authorized by SEIC and co-signed by area
Instrument Engr / Sub Engineer / Supervisor.
Note:
a) A cold work permit shall be used for work on field instruments (Local PG; TG; Cable laying
etc.). All jobs associated with ESD, DCS or even field electronic instrumentation should be
covered under Instrument permit.
b) Permit for changing the set point or the logic of Safety Critical devices will be issued only if
the approved “Safety Critical Device Set Point/ Logic Change Form” is available.
c) Note: - Work on TE (thermocouple) will be considered de-energized.

18 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
Instrument Work Permit General
guidelines
 General guidelines; Following guidelines should be followed while carrying out
an instrument related job;
 Electrical lock out, tag out or own isolation must be fulfilled before issuance of PTW.
 PM on any single security loop will be covered through one work permit. However,
safety critical defeat precaution is to be taken as per procedure.
 For any hot work; separate Hot PTW to be obtained addition to Instrument permit.
 A separate electrical permit must be issued for electrical disconnection of circuit
breaker leads where required. (separate rack out procedure/ card)
 Ensure that the work area is free of any toxic gases and the area condition is
sufficiently open to allow for adequate ventilation.
 Boardman’s signature is MANDATORY for work on controllers / control valves.

19 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
Vehicle Entry Permit
Vehicle entry permit to be obtained before any vehicle enter B/L of operating
plants or PTW areas.
Authorization:- USE will be issuer; accepted by Motor Pool or relevant section
authorized representatives.
Vehicle operator will sign the permit after thorough understanding of the job.
For routine chemical / Oil shifting without lifting as per Operations
requirement should also be covered under PTW.
Single Vehicle Entry Work Permit is sufficient for single vehicle for a single
area.

20 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
Vehicle Entry Permit
Chemicals / Raw Material unloading tankers / trucks; are allowed to
travel on non PTW roads / non process areas provided allowed by respective
Area Owner / USE to enter in non PTW areas / roads.
 In case of entry towards PTW roads / process areas PTW will be required.
SEIC will issue the permit and to be accepted by respective area Owner
/USE
 Note: - a) If a vehicle such as fork lifter or pay loader is used for
transferring material inside the plant battery limit, an additional cold
work permit will not be required.
 Do not drive through a cloud of Ammonia or any other combustible
gas / vapor, even if a road barricade has not been put up.
 No Road barrication is allowed without prior formal information to
SEIC;,ERT and area owner and formal approval from SEIC after
ensuring this information dissipated to all concerned.
21 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
Lifting Over Process Equipment Permit
This permit must be obtained before handling of any load over process equipments by
Crane or other lifting devices (fork lifter, hydra lift, pay loader etc.).
Authorization; Issued by USE ,if there is no potential of PSI. accepted by authorized
acceptor of Maintenance / Project or relevant section.
 In case, a potential for PSI is present permit will be filled by USE and co-signed by
Maint Engr / Sub-Engr (defining load path where boom swing) and then approved
by the SEIC.
 Incase of 4 MT weight or above it will be verified and co-signed by Maint Engr
along with precautions and rigging plan. For lesser weight, the permit will be issued
by USE
 Separate permits of Vehicle entry & LOPE will be issued.
 Permanently mounted hoists, overhead cranes, and lifts covered by an area
procedure are exempted from requiring this permit.
 Lifts made with chain blocks do not require this permit.

An additional Cold Work Permit will not be needed for the


lifting over job.
22 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
Excavation and Civil Work Permit
(White)
 Excavation PTW must be obtained for all excavations greater than SIX inches in depth.
Initiated;- Within the process units’ battery limit by USE and Co-signed by Project
Incharge or designate, Electrical in-charge or his designate, IT In-charg
 Excavation by powered equip is prohibited closer than 4 feet to any underground
cable/pipe.
 Initial digging in proximity to bricks must be done cautiously by hand. An Electrical
Work Permit for excavation at or near electrical equipment is required in addition to the
Civil and Excavation Work Permit.
 Red bricks must not be broken or cut without written approval of the Electrical UM.
Validation:- revalidation after 15 day by all interfaces.
 Shoring:-
 All excavations greater than 3½ feet or closer to a wall than the depth of the excavation
shall either be shored or excavated in ½: 1 side slope to protect the employees from cave-
ins or sliding material.
 In locations where sub soil water is encountered at a depth less than 3½ feet, shoring shall
be done at all depths.
23 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
Radiography Work Permit
This permit is intended prior to conducting any radiography in the
area to ensure protection for people from exposure working in the
surrounding area.
Authorization; Radiography Work Permits will be initiated by the
Inspection Engineer/Sub Engineer and approved by the SEIC after
it has been cosigned by the USE and accepted by Inspection
personnel.
 Normally, a 24 hrs.' notice regarding intended place & time of
radiography work will be given to Prod Dept. by inspection
except in emergency cases.
 The UM / SEIC should ascertain that area is cleared of people
prior to radio grapy via announcement through PA or Available
means.

24 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
Radiography Work Permit
•an adequate number of warning signs shall be conspicuously
displayed on the out-skirt of the cordoned area
•A physical radiation survey around/outside of the cordoned off area
shall be carried out during radiographic operation. This is usually
accomplished by using a radiation intensity meter
•Prior to radiography operation, the radiographers and their
assistants shall ensure that no unauthorized personnel are within the
radioactive sphere
•At all times during the exposure, a competent and qualified
radiographer must be at the site. He must be capable of returning
the isotope to its camera at any time when circumstances so warrant
•On completion of radiography, Area operator will ensure that all
barrication tapes and signs are removed
The annual allowable exposure limit is 5.0 REMS
25 FATIMAFERT LIMITED REVAMPED PTW SYST
EM
Lock Out Tag Out
In revamped SOP; LOCK out; Tag out and try out is being
proposed as per OSHA guidelines. Following is brief update
• Breakers to be locked as per existing practice by all involved discipline.
• Filed isolation will be supplemented by lock & Tag on all valves by operations.
• Group Lock out to be followed (Keys of all locks to placed in a box followed by
lock by operations.)
• Key box will also be locked by all discipline involved in job on equipment.
• Upon job completion & PTW close out discipline will remove their lock.
• Operation will remove their lock in last to remove field isolations.
• Incase of interplant PTW; requesting plant’s lock key will also be put in group
locks box.
FATIMAFERT LIMITED REVAMPED PTW
26 SYSTEM
LOCKOUT, TAG OUT AND TRY
PROCEDURE

Group locks by all sections working on single job.


 Maintenance : Blue
 Electrical : Red
 Instrument : Green
 Productions : White
 Other Interfaces: Black
 Interplant : Orange

27 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
PHYSICAL ISOLATION
Double Block & Bleed Isolation
Physical isolation procedure proves impractical in majority of areas due to
design constraints at all plants. Following guidelines will be followed:
 If the circuit downstream of I/V to be dismantled with only one I/V available
then after dismantling, pressure blind must be applied till reinstallation.
 If the circuit downstream of I/V not to dismantled, job can be handed over on
single isolation (W/O Blind ) after LOTO; provided NO passing of I/V.
 If blind installation is not possible; job can be handed over on single I/V with
LOTO provided there is NO passing of I/V and job verification by SEIC /
UM. Permit for such Jobs to be authorized by SEIC only.
 In case of single isolation with passing problem or in case of block & bleed
with both valves passing then in order to perform the job, JSA must be
carried out by a multi-disciplinary team. SEIC to authorized and accept
respective MaintLIMITED
FATIMAFERT Engr REVAMPED
/ Sub Engr
PTWto accept.
28 SYSTEM
Availability of Blind list at CR or
working Areas
Blind register to be made available in control rooms / areas along
with approved blind list and isolation plan. A copy of blind list /
isolation plan to be attached with PTW and display at job isolation.
FATIMAFERT LIMITED
Blind Tag List
Permit: _______________________________ Date: __________________
Job Description ___________________________________________________________________
Equipment: _______________________________________________________________________

Blind Installed By: Date Blind Removed By: Date


Blind Specific
Sr.No Location Blind Tag #
Name Sign P.No Name Sign P.No

FATIMAFERT LIMITED REVAMPED PTW


29
SYSTEM
Electrical Lock Out, Tag Out & Try Out.
By all interface involved in the job

30 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
Job preparations by installing locks & tags on
field isolations by authorized person (Operator).
After the equipment, process or pipe has been safely shutdown, all hazardous energy has
been dissipated or isolated, flushing, purging and the equipment has been cleared, the Shift
Engr/Sub Engr. or his designated Area Operator install his lock and tag (duly filled) on the
valves. To verify that the right valves have been isolated, the area operator shall ensure by
operating / opening bleeder/drain valve of the isolated loop

FATIMAFERT LIMITED REVAMPED PTW


31 SYSTEM
Group Locking
Once all valves have been isolated and verified in field by
Issuer or his designate, keys of all locks to be placed on
group lock out box. After placing keys of field isolation
locks in the box, Issuer or his designate shall put his
additional individual lock on the multiple locking device
of “Group Lockout” box

FATIMAFERT LIMITED REVAMPED PTW


32 SYSTEM
NTER-PLANT CONNECTING LINES ISOLATION PROCEDURE

INTER PLANT PTW REQUEST FORM


a)Request for Isolation & Tag
Time: - _____________ Hrs Date: _________________________
FROM: - ____________ Plant Initiated by: - _____________________
TO: - __________________________ Plant
PLEASE ENSURE THAT LINE # _______________________ OF ________________________
___________________________________________________________________________
Is physically isolated, depressurized & drained in a way that downstream system could be handed over for work.
-------------------- --------- ---------------- ------------------------
•Verification Tag:
DECLARATION:- I declare that line # ______________of ____________________________
________________________________________________________________has been isolated, depressurized and
drained up to my satisfaction downstream system is isolated from any flow stream entering toward downstream system
from this line.
Lock No: - _______________
Area Operator (Name & Sign): - ________________ USE (Name & Sign): - ______________
Time: ______________ ON _______________________________.
-------------------- -------------------------- ------------------------
•Authorization Tag:
DECLARATION: - I declare that job associated with line #______________ of
_________________________________________________ has been completed and isolation can be removed.
Lock No: ______________
USE / Sub Engr (Name & Sings): _____________________ Date: ________________

Plant: -
Date: - ___________

 Interplant isolation; USE /Sub-Engr of respective area will initiate “REQUEST


33 FOR LOCKOUT / TAGOUT” along with orange lock.
PERMIT FOR NON PROCESS AREAS

All areas at plant site including non process and buildings


will requires PTW for any job (except PTW exempted jobs
as per laid process).
 Relevant Building / area owner will issue permit.

 Operations will also be issuing permit for non routine jobs performed under

their direct supervision.

FATIMAFERT LIMITED REVAMPED PTW


34 SYSTEM
Cancellation of the permit

35 FATIMAFERT LIMITED REVAMPED PTW SYST


EM
Entry Registering Not Requiring Signing
Anyone requiring entry to a unit or area for any reason other than
Work Permit; routine inspection; supervision of on going job or
preprations of job , Log in and out & sign in register placed in
control room after getting permission and approval from
Engr/Sub-Engr or Board man.

Retention of Permits
HARD and SOFT copies of Work Permits to be retained by
Production and Maintenance interfaces for THREE
MONTH respectively.

FATIMAFERT LIMITED REVAMPED PTW


36 SYSTEM
Thank You

Questions ??
37