Professional Documents
Culture Documents
K.Kannan
Executive Engineer
Mettur TPS
HEAT RATE
Power generation is transitioning from a protected &
unquestioned environment. Now the focus is shifted from “only
Generation” to “economical generation”, “energy efficiency
index” and “Eco friendly generation”.
boiler 210
T
MW 200 MW
120.7 t/h auxpower 10 MW
4000 kcal/kg
Furnace side
Early Ignition
Heavy fuel concentration
Large particle Ash
Slag build-up on tubes
40
Vortex Eliminator
WATERSID
E DEPOSIT
leading to
failure
Even if the make up water quality is excellent, there will be
deposits of Iron oxides & copper
Sources of Deposition
Sources :
water borne materials
treatment chemicals
corrosion products
contaminants
Hardness salts { Ca & Mg salts , silica }
Dosing chemicals { ‘PO4’ , NH3 , N2H4 esw..}
During normal
operation
numerous solid portions of
The in-soluble insoluble materials
constituents materials are expected to
partially be
may enter removed by
deposit on tube
inside surface
boiler with blow down
feed water.
Over a period of time with
continual operation, the
Magnetite layer Grows in
thickness due to slow
corrosion
Effects of Deposits
Deposits reduces the heat
absorption due to:
• slagging may occur due to
increase in tube surface temp
• this affect the further heat
transfer
• it increase the FOT due to less
heat absorption in furnace zone
• it will increase the SH & RH
steam temp.
• more spray water is required to
maintain the required steam
temp.
• it may required frequent soot
Thermal resistance across the wall increases due to blower operation
• larger thickness of deposited layer, • in extreme cases, it may
• lower thermal conductivity of deposits required to reduce the load.
Need for Post Operational Chemical Cleaning
65 – 70ºC
E2 valve
Chemical water
entry to Boiler
E2 valve bonnet was removed and connected with chemical water line
from the Tank for circulation. A wooden dummy has been provided at
feed water side to prevent the chemical water entry towards LLCV /
FLCV
Ring Header hand hole
plate connection
Feeding line to
Boiler
Drain to neutralizing
pit
Drum air vents are connected with Nitrogen filling line
QUANTITY OF DEPOSITS REMOVED FROM THE SYSTEM
Overheating
leading to of water
failure wall tubes
Fireside DEPOSIT
BOILER CLEANING TECHNOLOGIES
1. On load cleaning:
– Wall blowers
– LRSB,s
– Smart wall blowing system
– Adding chemical additives
2. Off-load cleaning:
– Water washing
– Mechanical cleaning
Various methods tried to overcome these
encountered problems, :
Recorded Readings
Sl No Key Parameters Unit
Before After
1. Generation MW 210 210
2. Total steam flow T/hr 684 657
3. Feed water flow T/hr 723 663
4. Coal flow T/hr 137 127
5. Main steam pressure kg/cm2 132 132
6. Burner tilt % Full negative Zero
Radial seals
Damaged By-Pass seal
By-Pass seal
DOUBLE SEAL ED ROTOR
FLUE GAS DUCTS
Atmospheric air ingress into the flue gas duct
Source:
• Eroded & damaged expansion joint,
• worn out ducting
Remedial action:
• Timely replacement of expansion joints or
periodical replacement in the planned shutdown
like AOH.
• Re-engineering of duct flow pattern based on the
CFD
• Providing Wear resistance lining on inner wall
Effect of air ingress into FG Duct
Problem:
a) Increase in unburnt carbon loss & CO loss due to incomplete
combustion.
b) Slagging / clinking tendency in boiler due to reducing
atmosphere.
Problem Identification:
The reasons for above problem have been identified as below: -
1. Heavy ingress of atmospheric air into the flue gas duct.
2. High air in-leakage through APH seals.
3. High system resistance of flue gas duct due to multilayered
patching.
MILLING SYSTEM
The performance of milling system has a direct
impact over the efficiency of boiler.