Safety Campaign For Working in or Adjacent To The Operating Railway (Contractor's Version) - English Updated
Safety Campaign For Working in or Adjacent To The Operating Railway (Contractor's Version) - English Updated
Working in or adjacent
Growing Communities by Rail
Page 5
Overview of All SCL OI Work Incidents
(Incidents per month in 2013 and 2014)
si ng
a
In cre
Page 6
Overview of SCL OI Works Safety Related Incidents
(Incidents per month in 2013 and 2014)
Page 7
SCL OI Works Safety Related Incident Summary
(Incidents by root cause)
2013
2013
Nature of Root 2013 2014 Incompetency
Cause
No. of % No. of % 21% Careless
incident incidents 43%
s Rule
Violation
Carelessness 6 43% 3 21% 29%
Page 8
Common Mistakes
A number of
passengers were
injured and the
vehicle was
damaged
• WIL E&M Induction Oct 12, Version 2
MTR Corporation
Electric Shock of a Worker
– Cause
Did not implement risk mitigation measures identified
6 workers
Did not follow RSR
Poor safety awareness
could have
– Consequence
been
Worker hospitalized with minor burn on the right arm
Work stopped until further notice
electrocuted
Management Investigation required
– Cause
Poor judgement & reckless act
– Consequence
Management Investigation required
Works stopped till 16 Jun 2015
Improvement actions taken, e.g., a few staff fired,
improve safety / risk management / awareness /
communication etc.
Page 20
Water pipes damaged at HUH
Water pipes damaged at HUH
– Cause
Under‐estimated danger & risk in working so close to
live utilities
– Consequence
Water damage to equipment in SCR & Customs Office
– Cause
New / inexperienced CP(T)
Unfamiliar with RSR & tools / material clearing
procedures
– Consequence
Slight delay to the start of traffic
CP(T) disqualified
Could lead to derailment
– Cause
Inadequate design margin
– Consequence
Train service affected
• Single line bi-directional working for 3 hours
• Temporary Speed Restriction 22kph then 40 kph
Cables
Manhole
Optical fiber cables damaged
Optical fiber cables damaged
Optical fiber cables damaged
– Cause
Workers did not use hand tools to dig within 300mm of
detected cables
– Consequence
Could have affected communication systems of whole
EAL!
Works stopped until 2 new optical fiber cables laid
between SHT & TAW in Dec 2015 (9 months), at the cost
of a few million
Improvement actions taken, e.g., a few staff fired,
enhanced Permit-To-Dig procedures & management etc.
– Cause
Cables near heavy civil machinery not properly
protected
Poor risk identification & safety awareness
– Consequence
The trains between MKK and HUH were tripped
Train Service delay of 14 min & evening peak service
seriously affected
Works stopped for 6 days until improvement actions
completed, e.g., mark & protect all exposed site cables,
daily inspection & risk assessment by site staff etc.
MTR Corporation Page 34
Exposed site cables damaged
Page 36
Live Towngas pipe damaged at HHF
– Cause
Under‐estimated danger & risk in working so close to
gas pipe
Poor site supervision & communication
– Consequence
Works stopped till 13 Sep 2013
Improvement actions taken, e.g., clearly label each item
to be demolished, protect nearby utilities, improve safety
/ risk management / awareness / communication etc.
• Page
• MTR Corporation 38
Reasons Leading to the Accidents
Page 39
Whatever the Reasons, Fail to Manage Work in
Operational Areas May Lead To:
Multiple fatalities or injuries to passengers
Multiple fatalities or injuries to workers
Disruption of train service
Damage to railway facilities
Causing delay to projects
Page 40
Incidents can be prevented
Plan
– Develop EDOC & Method Statement
– Conduct Risk assessment
Do
– Book Possessions / SPA /PA
– Issue Traffic Notice & Work Notice to inform others
– Strictly follow RSR
– Strictly implement identified risk mitigation measures
– Strictly follow the Method Statement
Check
– No short-cut, no last-minute changes without consent
– Ask & escalate
Page 41