Professional Documents
Culture Documents
Alshamrani
Alshamrani
303SBC
.. -
:
ICC
/ / / / / / /
/ )( ./ / ./ / / ./
SCIENTIFIC BASES COMPACT NOT VOLUMINOUS RELEVANT TO LOCAL ISSUES SIMPLIFIED WITHOUT UNWARRANTED COMPLEXTIES MINIMUM SHORTCOMINGS AND DEFICIENCIES
:
Saudi Building Code Structural Com ittee workshop m Towards rational and applicable code (s)
Divisions Loading and forces Steel Alum inum Reinforced Concrete M asonry wood Testing and inspection Criteria for developing an applicable code Output
Scientific bases Com pact not volum inous M inim shortcom um ings and deficiencies Sim plified without unwarranted com plexity Relevant to national/ local issues
of IBC
GENERAL (0.25) FOUNDATION AND SOILS (1.5) EXCAVATION, GRADING AND FILL (1) ALLOWABLE LOAD-BEARING VALUES OF SOILS (0.75) FOOTINGS AND FOUNDATIONS (8) RETAINING WALLS (0) DAMPPROOFING AND WATERPROOFING (1.5) PIER AND PILE FOUNDATIONS (12.5) DRIVEN PILE FOUNDATIONS CAST-IN-PLACE CONCRETE PILE FOUNDATIONS COMPOSITE PILES PIER FOUNDATIONS
Out of the 8 pages for shallow footings, footings are covered in one page, Foundation walls in about 5 pages
The one page for footings covers concrete, masonry, and timber footings
Site investigations need more guidelines Coverage of shallow foundations devoted largely to foundation walls No provisions for collapsible soils The section of
retaining walls is merely one statement
Extensive emphasis is put on pile foundations Insufficient coverage of shallow foundations Most provisions for seismic loading pertains to Categories D, E, and F Some irrelevant materials are scattered throughout the Chapter
1802.5 Soil boring and sampling. The soil boring and sampling procedure and apparatus shall be in accordance with generally accepted engineering practice. The registered design professional shall have a fully qualified representative on the site during boring and sampling operations.
RELEVANCY (Foundation Material& Environment)(Cont.) 1805.4.5 Timber footings. Timber footings are
permitted for buildings of Type V construction 1805.4.6 Wood foundations. Wood foundation systems shall be designed and installed in accordance with AFPA Technical Report No. 7. . 1809.1 Timber piles. Timber piles shall be designed in accordance with the AFPA NDS.
1805.2.1
otherwise protected from frost, foundation walls, piers and.. Shall be protected from frost by one of the following .
OMISSION (Structure)
the standard 60 pounds per square foot swell test is performed on any soil with a
When swell greater than 4 percent, it shall be considered expansive.
DEFICIENCY (Loads) 1805.4.1.2 Vibratory loads. Where machinery operations or other vibrations are transmitted through the foundation, consideration shall be given in the footing design to prevent detrimental disturbances of the soil. 1805.4.2.2 Footing seismic ties. Where a structure is assigned to Seismic Design Category D, E, or F in accordance with Section 1616, individual spread footings founded on soil defined in Section 1615.1.1 as Site Class E or F shall be
interconnected by ties.
WHAT ABOUT THE ARAB CODE? WHAT ABOUT THE ARAB CODE?
TEN PARTS (1470 pages) IN GENERAL TAKES THE FORM OF A MANUAL COVERS IRRELEVANT AREAS OF GEOTECH. ENGINEERING NO REFERRAL TO OTHER STANDARDS OR SPECIFICATIONS OVERLAPPING BETWEEN SOME CHAPTERS CONSIDERS INSTRUMENTATIONS AND REMEDIES DEEP FOUNDATIONS IS THOROUGHLY COVERED
NEW TOPICS
SPECIAL SHALLOW FOOTINGS DESIGN FOR COLLAPSIBLE AND SABKHA SOILS RETAINING WALLS DESIGN FOR IMPACT AND VIBRATORY LOADS
CONTEMPLATED ISSUES
ONE OR SEVERAL CODES THOROUGHNESS REFERRALS TO OTHER STANDARDS OMISSIONS AND ABBREVIATIONS CONCERNED PROFESSIONALS AND AGENCIES STANDARDS AND SPECIFICATIONS FOR PROPOSED NEW LOCAL PRACTICE AND TECHNOLOGICAL COMPETENCY LENIENCY VS STRINGENCY SECTIONS
. IBC . . . .
ENVSIONED CONTENTS FOR THE SAUDI BUILDING CODE REQUIREMENTS FOR SOILS AND FOUNDATIONS
Title
Definitions
1 2 3 4 5 6 7 8 9
Site Investigation, Grading & Backfilling Shallow Foundations Deep Foundations Characterization & Building on Expansive Soils Characterization & Building on Collapsible Soils Excavation & Retaining Walls Foundations for Vibratory Loads Dampprofing & Waterprofing
MAIN SOURCES FOR THE SAUDI BUILDING CODE REQUIREMENTS FOR SOILS AND FOUNDATIONS
IBC
MASONRY WORKGROUP
. : . .
. . .
. . . . . . . . . . . .. . . .
GENERAL
1.3 DEFINITIONS. The following words and terms New shall, for the purposes of this code, have the meanings shown herein. Borehole. Borehole is a hole made by boring into the ground
to study stratification, to obtain natural resources, or to release underground pressures.
Active
zone. The upper few meters of the soil deposit, Index. Expansion index is the percent volume
Expansion
change determined in accordance with ASTM-D4829 multiplied by fraction passing No. 4 sieve of the soil multiplied by 100.
SITE INVESTIGATIONS
Exception: The building official need not require a foundation or soils investigation where satisfactory data from adjacent areas is available that demonstrates an investigation is not necessary for any of the conditions in Sections 1802.2.1 through 1802.2.7.
New
No site investigation report is needed if the building meet the following combined criteria: 1) The net applied load on the foundation is less than 50kPa 2) There are no dynamic or vibratory loads on the building 3) The footprint area of the building is less than 4x4 m2 4) Questionable soil is not suspected underneath the building 5) Cavities are not suspected under the footing of the building
SITE INVESTIGATIONS
2.2.3 Ground-water table..
Exception. A subsurface soil investigation shall not be required where waterproofing is provided in accordance with Section 1807. Subsection 1802.2.3 is amended by deleting its exception without replacement.
New
2.2.4.1 Rock cavities. In areas likely to have rock cavities, the building official shall require site investigation to determine the sizes and locations of such cavities.
SBC 303
SITE INVESTIGATIONS
2.3.3 Collapsible soils. Soils meeting all four of the New following provisions shall be considered collapsible. Compliance with Items 1, 2 and 3 shall not be required if the test prescribed in Item 4 is conducted: 2.4.2 Number of boreholes. The minimum number of boreholes in a given site shall be taken in accordance Table 2.1 and its provisions. The values included in Table 2.1 shall be considered as minimum guideline. 2.4.3 Depth of boreholes. The depth of boreholes shall cover all strata likely to be affected by the loads from the building and adjacent buildings. The minimum depth of boreholes shall be taken from Table 2.1.
SITE INVESTIGATIONS
2.6 REPORTS
Introduction that shows the site location map, any other adjacent
buildings, and utility lines.
Elevation
of the water table, if encountered and recommended procedures for dewatering, if necessary.
Suitability of onsite soils for use as fill material . Address, if applicable, the possible impacts on adjoining properties
and mitigating measures to be undertaken.
SITE INVESTIGATIONS
record of the soil profile. With the SPT values at the corresponding depths if soil is encountered. RQD and TCR values of rock core samples should be included in case rock is encountered.
Recommendations
for foundation type and design criteria, including but not limited to: . provisions to mitigate the effects of problematic soils (expansive, collapsible, sabkha, etc.); mitigation of ... The recommendations for foundation
design must be based on the facts stated in the report, i.e. on the borehole records and test data. They must not be based on conjecture.
3.2 Commencement. Excavation, grading and fill shall not be New commenced without first having obtained a permit from the building
official.
engineers.
3. .
ALLOWABLE LOAD-BEARING
4.2 Presumptive load-bearing values. The maximum allowable foundation pressure for supporting soils shall not exceed the values specified in Table 1804.2 unless data to substantiate the use of a higher value are submitted and approved by the building official. 4.4 Computed load-bearing values. It shall be permitted to obtain the ultimate bearing capacity from appropriate laboratory and/or field tests including, but need not be limited to, standard penetration test conforming to ASTM 1586 and plate load test conforming to ASTM 1194. ..
New
New
5.2 Depth of footings. The minimum depth of footing SBC below the natural ground level shall not be less than 1200 303 mm for cohesionless soils, 1500 mm for silty and clay soils and 600 mm to 1200 mm for rocks depending on strength and integrity of the rock formations.
minimized.
1808.2.12 Settlement analysis. The settlement of piers, individual piles or groups of piles shall be estimated based on approved methods of analysis.
SPREAD FOOTINGS
5.4.1.5 Design settlements. Settlements shall be estimated by a SBC registered design professional based on methods of analysis 303 approved by the building official. The least value found from Tables 5.1 and 5.2 shall be taken as the allowable differential settlement.
TABLE 5.1 MAXIMUM ALLOWABLE TOTAL SETTLEMENT
FOOTING TYPE
60 80
New
5.4.1.6 Factor of safety. Factor of safety shall not be less than 3 for permanent structures and 2 for temporary structures. Consideration shall be given to all possible circumstances including, but not limited to, flooding of foundation soil, removal of existing overburden by scour or excavation, and change in groundwater table level.
RETAINING WALLS
1806.1 General. Retaining walls shall be IBC
designed to ensure stability against overturning, sliding, excessive foundation pressure and water uplift.Retaining walls shall be designed for a safety factor of 1.5 against lateral sliding and overturning.
New
New
New
New
New
New
10.1.1 Approval of special systems of design or construction. Sponsors of any system of design or construction within the scope of Chapter 10, the adequacy of which has been shown by successful use or by analysis or test, but which does not conform to or is not covered by Chapter 10, shall have the right to present that data on which their design is based to the building official or to a board of examiners appointed by the building official.
New
10.1.1 Approval of special systems of design or construction. This board shall be composed of competent geotechnical and structural engineers and shall have authority to investigate the data so submitted, to require tests, and to formulate rules governing design and construction of such systems to meet the intent of Chapter 10. These rules when approved by the building official and promulgated shall be of the same force as the provisions of Chapter 10.
New
9.3.2.1 Shallow foundations. Continuous or spread footings shall not be used on expansive soils unless the soil deposit has a low expansion potential, as determined in accordance with Table 9.1 or the superstructure is designed to account for the potential foundation movement. ..
New
303 SBC
. . . . . . . .
CONCLUDING REMARKS
The Draft of SBC 303 was developed based on Chapter 18 of the (IBC) 2003 edition and by inclusions of excerpts from a number of national and international documents. The committee included professionals from academia, governmental and semi-governmental agencies, and consulting firms. Development of the SBC 303 draft followed the methodology approved by the Saudi Building Code National Committee.
The necessity for revision or addition, the reliability of the to-be added materials, and their conformity and consistency with the provisions of the IBC document, all were given due considerations.