Four Laning of Teleibani-Sambalpur Section (Part-2) of NH-6
Four Laning of Teleibani-Sambalpur Section (Part-2) of NH-6
Salient Features:
NHDP Phase
Mode of Implementation
Concessionaire
Date of agreement
Length of Project
Traffic
Estimate cost
Appointed date
Schedule completion date
Likely date of completion
Authority Engineer
Safety consultant
4-lane completed
Physical Progress
:
:
:
:
:
:
:
:
:
:
:
:
:
:
IV
EPC
Yet to be awarded
23.628 Km (Km 521.528-545.156)
11879-20644 PCU (2010)
Rs.300/- Approximately
Widening to 4-lane
23.351 km.
Service road
Minor bridge
(2-lane)
Way side amenities
Completed
length / numbers
Work to be
awarded
:
:
:
:
:
:
:
:
:
:
:
:
: