DAI QUANG MINH ZONE II PROJECT - POLT 5.

5
D N: KHU CAO C VN PHNG THNG
MI DCH V TI L 5-4, 5-5
TEST PILE WORKS CONSTRUCTION METHOD
STATEMENT
BIN PHP THI CNG CC TH
VERSION A

02/2015

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th
BACHY SOLETANCHE VIETNAM
126 Nguyen Thi Minh Khai, District 3, Ho Chi Minh City, Vietnam
Tel. (84.8) 930 5782 Fax: (84.8) 930 5783
*********

DAI QUANG MINH ZONE II PROJECT POLT 5.5


District 2 - Ho Chi Minh City - Vietnam

TEST PILE WORKS CONSTRUCTION


METHOD STATEMENT

DQM

BSV

THE CLIENT (DAI QUANG MINH)


CH U T

TP

MS

THE CONSULTANT
T VN GIM ST

Page 2

001

THE CONTRACTOR (BSV)


NH THU

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Date /
Ngy

Revesion /
Ln sa
i

Content / Ni dung

02-2015

For Construction

Page 3

Prepared
by /
Chun b

Checked
by / Kim
tra

Approved by
/ Ph duyt

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

CONTENTS / MC LC

A. GENERAL / GII THIU CHUNG.................................................................................................. 6


I. BUILDING CHARACTERISTICS / C IM CNG TRNH ................................................ 6
II. TEST PILE CONSTRUCTION / THI CNG CC TH......................................................... 6
B. PREPARATION / CNG TC CHUN B ..................................................................................... 7
I. ORGANIZATION / T CHC THI CNG ................................................................................ 7
II. MATERIAL AND EQUIPMENT / VT LIU V THIT B THI CNG .................................. 7
III. TEMPORARY FACILITIES / CNG TRNH PH TR......................................................... 8
C. SPECIFIC OF TEST PILE CONSTRUCTION / CHI TIT CA THI CNG CC TH ........... 9
I. SURVEY / CNG TC TRC C .......................................................................................... 9
II. GUIDE WALL / TNG DN ................................................................................................... 9
III. POLYMER SLURRY PREPARATION / CHUN B DUNG DCH POLYMER .................. 12
IV. TEST PILE EXCAVATION / THI CNG O CC TH. .................................................. 15
V. PLACING OF REINFORCEMENT / LP T LNG THP ............................................... 17
VII. PLACING CONCRETE / CNG TC BTNG .......................................................... 19
VIII. GROUTING (FOR SHAFT GROUTED PILES ONLY) / CNG TC PHT VA (CH P
CHO CC C PHT VA)......................................................................................................... 23
X. EQUIPMENT / THIT B THI CNG ..................................................................................... 28
D. INCIDENT SOLUTIONS / CNG TC X L S C TRONG THI CNG ............................ 29
I. TREMIE CLOGGING SOLUTION / X L S C KHI TC NG ............................... 29
II. OVERCOMING OBTACLES SOLUTION / X L KHI GP VT CN KHI O ............. 31
III. TRENCH COLLAPSE SOLUTION / X L KHI SP THNH H O ........................... 32
IV. WAITING FOR CONCRETE SOLUTION / X L KHI CH BTNG ............................ 33
V. TREMIE PIPE FALLING SOLUTION / X L KHI RI NG BTNG ..................... 33
VI. INCLINING TRENCH SOLUTION / X L KHI H O KHNG THNG ..................... 34
APPENDIX / PH LC ...................................................................................................................... 34
APPENDIX 1 - POLYMER TECHNICAL CHARACTERISTIC AND TESTING FREQUENCY
& MSDS ......................................................................................................................................... 35
PH LC 1 - TN S KIM TRA V C TNH K THUT CA POLYMER & THNG S
AN TON VT LIU .................................................................................................................... 35

Page 4

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th
APPENDIX 2 ACCEPTANCE PROCEDURE AND TIME FRAME FOR ENGINEERS
SIGNATURE ................................................................................................................................. 36
PH LC 2 QUY TRNH NGHIM THU V THI GIAN K CHP THUN NGHIM THU
....................................................................................................................................................... 36
APPENDIX 3 - GENERAL SPECIFICATION OF TREMIE METHOD CONCRETE SUPPLY
....................................................................................................................................................... 39
PH LC 3 - YU CU K THUT I VI B TNG THNG PHM BNG NG
TREMMIE...................................................................................................................................... 39
APPENDIX 4 - SHAFT GROUTING INSTRUCTIONS AND STOP CRITERIA ...................... 50
PH LC 4 - CNG TC KHOAN PHT, CH DN V TIU CHUN DNG..................... 50

Page 5

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

A. GENERAL / GII THIU CHUNG


I. BUILDING CHARACTERISTICS / C IM CNG TRNH
The Project is named Dai Minh Quang Zone 2 Project Polt 5.5, located at no.
10 Mai Chi Tho, District 2, Ho Chi Minh City, invested by Cong ty CP dau tu dia oc
Dai Quang Minh Corporation. Bachy Soletanche Viet Nam (BSV) is the contractor
of item Test Pile Works and as outline as follows:
TP1 : Bored pile D1500mm, 72.2 m deep
TP2 Barrette 800mm x 2800mm, 62.2 m deep,
TP3 Shaft grouted barrette 800mm x 2800mm, 62.2 m deep, shaft grouting
from 50 m to toe 59 m leve
D n c tn Dai Minh Quang Zone 2 Project Polt 5.5, ta lc ti s 10 Mai
Ch Th qun 2, tp. H Ch Minh, c u t bi cng ty c phn u t a c
i Quang Minh v n v thi cng cho hng mc cc th l nh thu Bachy
Soletanche Vit Nam. Cc Barrette & cc khoan nhi c thit k nh sau:
TP1 : Cc khoan nhi D1500mm, su 72.2 m
TP2 : Cc Barrette kch thc 800mm x 2800mm, su 62.2
TP3 : Cc Barrette kch thc 800mm x 2800mm c s l bm va thn
cc, su 62.2 m, bm va t cao -50 m n -59 m ti mi cc.

II. TEST PILE CONSTRUCTION / THI CNG CC TH


Construction technique of reinforcement concrete piles is constructing with the
design in works order: excavating with slurry in trench, installing rebar cage,
concreting for TP1 and TP2, cracking & shaft grouting for barrette TP3 .
Determine the design depth of panel, excavating with clamshell or grab.
Pumping polymer slurry to keep the stability of trench during excavation.
Installing rebar cage into trench which is filled up polymer slurry.
Casting concrete by tremie pipe method.
Cracking & shaft grouting TP3 to increase the load capacity of barrette piles
and bored piles.
During the concrete rising in the hole, the polymer slurry is pumped back to the
silos to reuse or disposed.

Page 6

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

K thut thi cng cc btng ct thp l vic thi cng theo trnh t: o h trong
t s dng dung dch gi thnh, h lng thp, btng cho cc TP1 v TP2, ph
nc v pht va cho cc TP3. C th l:
Xc nh chiu su o theo thit k, o bng gu ngom.
Bm dung dch polymer gi thnh trong sut qu trnh o.
H lng thp c gia cng xung h o trong dung dch gi thnh.
btng t dng theo phng php t dng trong ng tremie.
Pht va cc th TP3 vi cp phi va c duyt nhm tng kh nng
chu ti ca cc
Khi btng dng ln trong h o, dung dch gi thnh tha ra s c bm v
ri cha vo cc bn cha ti s dng hoc loi b.
B. PREPARATION / CNG TC CHUN B
I. ORGANIZATION / T CHC THI CNG
Establish the construction arrangement plan including barrette ( TP2, TP3) and
bored piles ( TP1) position, temporary facilities such as site installation including
working platform, office area, equipment such as excavation crane, slurry supplying
system, water supplying and drainage system, power supplying system, internal
road
Lp bn v mt bng thi cng tng th bao gm v tr cc barrette ( TP2, TP3) v
cc khoan nhi ( TP1), b tr cc cng trnh ph tr nh: sn cng tc, khu vc vn
phng, thit b thi cng nh my o, h thng cung cp v tun hon dung dch gi
thnh h o, h thng cp thot nc, h thng cp in, ng ni b
II. MATERIAL AND EQUIPMENT / VT LIU V THIT B THI CNG
The ready mixed concrete graded 50Mpa is used for the barrette piles, bored
piles and delivered to site by trucks. The ready mix concrete is designed to satisfy
the workability requirement during the transporting and casting period. Concrete will
be tested to assess the quality and the mix composition. Concrete has to be quality
certification and design mix certification. The concrete specification is attached in
Appendix 3.
Btng s dng thi cng cc barrette v cc khoan nhi ti cng trnh l btng
thng phm mc 50Mpa c vn chuyn t nh my n cng trng bng xe
chuyn dng. Btng c thit k cp phi m bo kh nng lm vic cho
php trong sut thi gian vn chuyn v btng. Btng s c kim tra
nh gi cht lng v thnh phn cp phi. Btng phi c kt qu th nghim

Page 7

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

nh gi cht lng v nh gi thnh phn cp phi. Cc yu cu k thut ca


btng c nh km trong ph lc 3.
The rebar used for this project is high strength steel SD390 (fy = 390 MPa)
Rebar, with quality certificate, will be tested (tension test, bending test) and has to
be approved before using.
Ct thp s dng trong cng trnh l thp cng cao loi SD390 (fy = 390
MPa) Thp phi c giy chng nhn cht lng sn phm, kt qu th nghim mu
th (cng chu ko, chu un) v phi c nghim thu trc khi a vo s
dng.
The other material such as polymer, additive, must be approved by Engineer
prior to using and will be submitted with the certification of manufacture.
Cc loi vt liu khc nh polymer, ph gia, phi c chp thun bi T vn
gim st trc khi s dng v c trnh cng vi chng ch cht lng ca nh
sn xut.
Equipment used for this project is heavy plants such as excavation rigs, drilling
machine, service cranes, backhoes, which were cablirated by legal department
according to the regulation and approved before using.
Cc my mc thit b s dng trong thi cng l cc thit b thi cng hng nng
nh my o,my khoan, cu phc v, my xc c ng kim bi c quan
chc nng theo ng cc quy nh hin hnh v phi c nghim thu kim tra
trc khi a vo s dng.
III. TEMPORARY FACILITIES / CNG TRNH PH TR
Before starting the test piles construction, the temporary facilities are built based
on site installation. / Trc khi thi cng tng vy, nh thu thi cng xy dng cc
cng trnh ph tr da trn bn v b tr mt bng thi cng:
Site management offices area. / Khu vc vn phng ca Ban ch huy cng
trng.
Drainage and water supplying system includes water source ( local system),
drainage system, pumps, pits / H thng cp thot nc bao gm ngun
nc ( nc thy cc), mng dn nc, my bm, h lng,
Power supplying system used for construction. / H thng cung cp in s
dng trong thi cng.
Polymer slurry supplying and recycling system includes: storage, additive,
mixing station, pipe line. / H thng cung cp v tun hon dung dch gi

Page 8

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

thnh h o bao gm: kho cha bt bentonite & polymer, ph gia, trm trn
dung dch Bentonite & polymer h thng ng ng.
Storage of cement, cement mixer for grouting and pumping unit. / Kho cha xi
mng, my trn va xi mng s dng cho pht va v thit b bm.
C. SPECIFIC OF TEST PILE CONSTRUCTION/ CHI TIT CA THI CNG CC TH
I. SURVEY / CNG TC TRC C
1. Benchmarks / Mc trc c cng trnh
Benchmarks of project includes / Mc trc c cng trnh bao gm:
Benchmark system provided by Client. / H thng mc trc c do Ch u
t cp.
Axis plan. / Mt bng li trc cng trnh.
Secondary benchmark system. / H thng mc th cp phc v trong qu
trnh thi cng.
Survey team, including the experienced members, will continuous monitor the
displacement of benchmarks during the construction period. The survey team is
responsible for setting up the test piles positions. / T trc c vi cc thnh vin c
kinh nghim trong chuyn ngnh trc c gim st lin tc s chuyn v ca cc
mc ny trong qu trnh thi cng. T trc c cng c nhim v nh v v tr cc cc
th.
2. Equipment / Thit b s dng
The survey equipment used for construction shall satisfy the accuracy
requirement and shall be certified by authorized department. / Thit b trc c c
s dng phi p ng cc yu cu v chnh xc v c kim nh bi n v c
thm quyn.

II. GUIDE WALL / TNG DN


Prior to construct the test piles, a guide wall is built. This guide is reinforced
concrete wall ( TP2 & TP3) or steel casing type ( TP1). The guide wall is designed
according to the requirement. The distance between two internal surfaces of guide
wall is 5cm larger than the diameter of test piles. This 5cm larger allow the clamshell
/ grab to excavate properly without obstruction.
Trc khi thi cng cc th, tng dn c thi cng trc. Tng dn c s
dng l loi tng btng ct thp ( TP2 & TP3) hoc tng dn thp ( TP1). Tng

Page 9

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

dn c thit k theo yu cu bn v thit k thi cng. Chiu rng trong lng tng
dn ln hn chiu rng ca cc l 5cm. 5cm ln hn ny cho php gu o d dng
o m khng gp tr ngi.
1. Guide wall function / Tc dng ca tng dn
Guiding the grab during the excavation and guarantee the correct position
and alignment of the test piles. / Dn hng gu o trong sut qu trnh o
t v m bo cc th c nh v ng v thng hng.
Supporting the equipment of the test piles (reinforcement cages, tremie
pipes,, etc.). / H tr cho thit b thi cng cc th (lng thp, ng tremie).
Supporting the top layer of the trench during excavation. / Tng n nh
ca nh h o trong sut thi gian o.
Allowing a reliable reference marking system for test piles. / Cho php to h
thng kim tra tin cy ca cc cc th.
2. Equipment / Thit b thi cng tng dn
Backhoes. / My o.
The formwork and prop pipes. / B cp pha v h thanh ging.
3. Type of guide wall / Cc loi tng dn
a) Cast in-situ concrete guide wall / Tng dn btng ct thp.
Description of scope of work / Trnh t thi cng:
Locating position and bottom level of trench by total station, excavation of the
trench is done by backhoe. / nh v v tr v cao y tng dn bng my
ton c.
Excavation of the trench is done by backhoe. / o bng my o
Installing the reinforcement as shop drawing. / Lp t ct thp theo bn v
thit k.
Installing the formwork. / Lp t cp pha.
Control the formwork by surveyor / i trc c kim tra ta ca cp pha.
Casting concrete / btng.
Dismantel the formwork 24 hours after concreting / Tho cp pha tng dn
sau khi b tng 24 gi ng h

Page 10

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Trench between the 2 walls is backfilled by soil right after dismanteling the
formwork to avoid any fall / Rnh o gia hai mt tng dn s c lp li
bng t sau khi tho cp pha trnh st thnh.

Figure 1a Cast in-situ Concrete Guide wall Section for TP2- TP3
Hnh 1a - Mt ct ngang tng dn btng ct thp ti cng trng
b) Casing for bored pile TP1/ ng chng vch cho cc khoan nhi TP1.
The casing is installed under ground level with approximately 6m depth. The
plump line is used for checking the verticality during the installation period to ensure
the permitted tolerance. The casing location is determined by the intersection point
of two perpenticular lines

Page 11

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

ng vch tm thi s c h xung di mt t t nhin n chiu su xp x


6m. Thc thy bnh hoc dy di s c dng kim tra thng ng ca ng
vch trong qu trnh h ng nhm bo m lch cho php. V tr ng vch tm
thi trn mt bng s c khng ch bng cch s dng im trn 2 ng vung
gc nhau ti tim ng vch.

Figure 1b Casing installation of bored pile TP1


Hnh 1b Lp t ng vch ca cc trn TP1
The top of casing will be higher than ground level from 0.2 to 0.3m after installing
to keep the stability of trench and prevent the hole from water & debris.
Sau khi c h, ng vch ng vch tm s c dng cao hn mt sn cng
tc khong t 0.2-0.3m, ng vai tr gi n nh nh h khoan cng nh ngn nc
mt v cc tp cht ri vo h khoan.
The survey team will recheck the casing center point position and determine the
top level of casing after installing.
Sau khi h ng vch xong, trc c vin s kim tra li ln na ta tim ng
vch nm trong khong sai s cho php v xc nh chnh xc cao trnh u ng
vch.
III. POLYMER SLURRY PREPARATION / CHUN B DUNG DCH POLYMER
Polymers for drilling mud are products that can be used in powder form or in
liquid form. When dispersed into water, macromolecules chains of polymer are
hydrated to produce viscosity effect. The characteristics of polymer slurry are
specified in appendix 1.

Page 12

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

For all material interested to be used, a material safety data sheet will be
submitted together with the request of approval for material.This is a friendly material
with environment, encourage to using.
The polymer is delivered to site in 25kg unimpregnated bags which are stored
under cover. The polymer is mixed in tank with aerating pipeline and the slurry is
stored in silos or reservoirs until used during the excavation.
When the hole is full of polymer slurry, polymer has tendency to generate
membrance to prevent the trench from osmosis of the underground water because
the pressure of polymer slurry is higher than underground water pressure. Polymer
pressure makes a stable force to the side of the hole.
Bentonite + Polymer dng cho cng tc khoan (o) l sn phm c s dng
dng bt hoc dung dch. Khi c khuch tn trong dng nc, chui i phn t
ca polymer s c hydrat ha to nht cn thit. Cc thng s ca loi
polymer ny c nu trong ph lc 1.
i vi cc loi vt t s dng trn cng trng, bng thng s an ton nguyn
vt liu s c gi km vi phiu yu cu nghim thu vt liu. y l mt vt liu
thn thin mi mi trng v khuyn khch s dng.
Polymer c tp kt n cng trng trong bao 25kg v c bo qun bng
cch ph bt. Polymer c trn trong bn trn vi h thng ng sc kh v dung
dch c cha trong nhng silo hoc b cha sao a ra s dng ti h o.
Khi h o y dung dch polymer, polymer s to ra mng ngn s thm
thu ca nc ngm vo h o do p lc ca dung dch polymer cao hn p lc
nc ngm. p lc polymer to ra mt lc n nh trn vch h o.
1. Polymer slurry preparation / Chun b dung dch Polymer
Polymer and bentonite slurry is mixed and stored in available silos or reservoirs.
The mixed design of slurry, which is supplied for excavating, will be around polymer
1.0 kg/m3 and bentonite 10 kg/m3 (Limitation refer to appendix 1)
Dung dch polymer v bentonite s c trn chung v cha trong cc silo lp
t sn hoc b cha. Polymer s dng khi o l loi c t l bnh thng khong
1.0 kg/m3 polymer v 10 kg/m3 bentonite (Gii hn cho php tham kho ph lc 1).
Bng cp phi s dng cho dung dch o Polymer cho 1m3
Polymer

1 kg

Bentonite

10 kg

Soda

0.48 kg

Page 13

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

2. Polymer slurry for excavation / S dng polymer khi o.


The excavation hole is full of polymer slurry to ensure the stability of trench. The
pump may be used when supplying slurry to excavation hole.
Khi o t, h o c y polymer m bo p lc n nh. Khi a
dung dch polymer vo h o s s dng my bm nu cn thit.
During construction,a technician will check periodically carefully the characteristic
of slurry to determine if the slurry still satisfying the requirement for reuse or not.
Trong sut qu trnh thi cng, mt k thut vin s nh k kim tra cn thn cc
c tnh ca polymer xem c iu kin ph hp c tip tc s dng hay
khng.
3. Apparatuses / Cc thit b kim tra
Apparatuses available in the site laboratory include the following / Cc thit b
kim tra ti phng th nghim cng trng bao gm:
1 Baroid filter press (free water test) / 1 my nn lc Baroid (kim mt
nc);
1 marsh cone (viscosity test) / 1 cn th nht;
1 mud balance (density test) / 1 cn t trng;
1 elutriometer (sand content test) / 1 b o hm lng ct;
Paper for measuring pH / giy o pH.
On fresh polymer and polymer slurry, before supplying to excavation hole will be
checked the following characteristics: density, viscosity, free water and pH. The test
results are recorded in a polymer test form with the approval of Client and
Consultant, and filed during the construction period. The frequency of testing is
attached in Appendix 1.
Polymer khi mi trn xong v Polymer trc khi bm vo h o s c s
c kim tra cc ch tiu: t trng, nht, tch nc v pH. Cc kt qu
ca mi t kim tra s c ghi li y theo mu kim tra polymer c s
ng ca Ch u t v T vn gim st, v lu gi trong sut thi gian thi cng
cng trnh. Tn sut kim tra c nh km trong Ph lc 1.

Page 14

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Figure 2a - Apparatuses for testing polymer slurry


Hnh 2a - B dng c th nghim polymer

Figure 2b Polymer storage


Hnh 2b Polymer

IV. TEST PILE EXCAVATION / THI CNG O CC TH.


1. General / Tng qut:
Barrette piles will be excavated by a rectangular grab, hung up to a crane,
operated by cable or hydraulic system of drilled by bucket. Bored piles will be bored
by a drilling-machine . During the excavation, the polymer slurry is kept around 0.4m
lower than the top level of guide wall and not less than 1.0m above the ground water
level. The verticality of the hole is monitored by visual checking of the crane cables
during successive lowering the grab into the hole.

Page 15

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Besides the visual checking of crane cables, the contractor can also measure the
grab cable to check verticality of trench (applying for hydraulic crane and mechanic
crane). The distance between the cable and the internal sides of guide wall will be
measured, the interval is carried out every 5m after completion of one bite. The soil
sample is also taken every 2m.
The minimum distance between the excavation crane & the hole is 3.0m. Any
crane movement will be monitored to satisfy this requirement.
Vic thc hin o cc barrette c thc hin bi gu ngom hnh ch nht
treo trn xe cu vn hnh bng dy cp hoc h thng truyn ng thy lc hoc
bng gu xoay. Cc khoan nhi s c khoan bi my khoan. Trong qu trnh
o, dung dch polymer c gi thp hn nh tng dn khong 0.4m v cao hn
mc nc ngm khng nh hn 1.0m. thng ng ca h o c gim st
trc quan thng qua nhng dy cp ca xe cu trong lc h gu xung trong h
o.
Ngoi vic kim tra thng ng ca h o bng phng php quan st trc
tip dy gu, th nh thu c th dng phng php s dng thc o dy gu
kim tra thng ng ca h o (phng php ny c p dng vi c hai loi
my o thy lc v my o dy cp). Thc o t dy gu ra mp trong tng
dn, cc bc ny c thc hin sau mi 5m chiu su ca h o sau khi o
xong mt nht o. C 2m th tin hnh ly mu t mt ln.
Xe cu phi gi khong cch ti thiu 3.0m n h o. Bt k di chuyn no
ca xe cu s c kim sot tun th i hi ny.

2. Method of checking and monitoring verticality and stability / Phng php kim
tra v gim st thng ng v n nh:
a) The verticality of the excavation hole is continuously monitored basing on the
verticality of grab cable as a plumb line. The reparation is carried out
immediately to ensure the quality of the product and the general schedule of
project.
thng ng ca h o c gim st lin tc da vo thng ng ca
dy cp gu o xem nh l con di. Cng tc sa cha h o b nghing s
c tin hnh ngay khi pht hin h o b nghing, bo m tin thi cng
v thng ng ca h o.
b) During excavation, monitoring will be carried out by measuring.
Trong qu trnh o, vic gim st lin tc c thc hin bng thc o.

Page 16

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

c) The verticality tolerance of trench for barrette piles is 1:100. The verticality
tolerance of trench for bored piles is 1:100 / Sai s thng ng ca h o
cho cc barrette l 1:100. Sai s thng ng cho cc trn l 1:100.
3. Cleaning bottom of trench / V sinh y h o
The excavation is finished when reaching the required depth. The polymer slurry
that mixed with soil particles in the excavation trench will be waited for the
suspended particles settling at the bottom.
Khi t c su cn thit, cng tc o kt thc. Dung dch polymer ln t
trong h o s c ch cc ht l lng trong dung dch lng xung y h
o.
During the wating time, the bottom is thoroughly cleaned by the clamshell if the
sediment is higher than 10cm. This step continuosly repeats until the slurry reaches
all characteristics before concreting.
Trong qu trnh ch lng, h o s c vt bng gu o nu lng vt
qua 10cm. Cng tc vt ny s c thc hin lin tc cho n khi dung dch trong
h t cc ch tiu trc khi b tng.

V. PLACING OF REINFORCEMENT / LP T LNG THP


Steel cages are pre-fabricated on site, and upon completion of polymer recycling,
the cage is lowered into the slurry trench by crawler crane.
The circular concrete spacers (grade is equivalent to test pile concrete garde) are
installed during installing the rebar cage to ensure the required cover of rebars.
The steel cage are generally composed of 11.7m long steel cage elements (or
longer) connected by steel screwed U-bolts the designed overlap length during
lowering down into the excavation hole or at the steel yard, based on the condition of
construction. Once all the steel cage are lowered, they are suspended to the
required level from the guide walls by measured suspension bars connected with the
calculated lengths in preparation for concreting. The Surveyor will check level of 4
points at top of steel cage to comply with the designed level.
Lng thp c ch to trc ti cng trng, khi vic ti ch polymer, lng thp
c h xung rnh o bng cn cu bnh xch.
Lng thp c gn cc con k btng hnh trn c cng tng ng vi
btng cu kin, m bo lp btng bo v theo thit k a ra.

Page 17

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Lng thp c cu to bi nhng on lng di 11.7m ( hoc di hn ) v lin


kt vi nhau bng cch bt bulng hnh ch U trn chiu di on ni chng theo
thit k trong khi h xung rnh h o hoc ti khu vc gia cng lng thp, ty
thuc vo iu kin thc t cng trng. Mt khi tt c cc on lng thp c
h xung, chng c treo ti cao trnh theo yu cu t nh tng dn bng nhng
thanh thp treo vi chiu di tnh ton cho vic btng. V c trc c kim tra
cao 4 im ca nh lng thp theo ng cao thit k.
The lifting and lowering rebar cage down to excavation hole is done as following
steps, using the two winches:
A spreader bar is connected to top of steel cage by cable, clamps, hanging
bars (pre-installed during rebar cage fabrication period) and lifted up by the
main hock of service crane.
A system of cable, clamps, pulleys are connected to the length of the cage at
dedicated hanging bars, and the cage is lifted up by the single cable of the
service crane in order to equilibrate the lifting up steel cage.
All this procedure will be clearly descriped in the different project lifting plan.
Vic cu lng thp lp t xung h o c thc hin theo cc bc sau,
s dng hai ti:
H thng thanh chia ti lin kt vi u trn lng thp bng cp, m n, thanh
cu lng (t sn khi gia cng lng thp) v c nng bi cp t ca cu
phc v.
H thng cp, m n, rng rc lin kt vi lng thp ti cc im t thanh cu
lng v c nng bi cp n ca cu phc v nhm gi cn bng trong
qu trnh dng lng theo phng thng ng
Qui trnh ny s c trnh by c th trong k hoch nng ca d n.

Page 18

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Figure 4 Rebar cage installation


Hnh 4 Lp t lng thp
VII. PLACING CONCRETE / CNG TC BTNG
1. Specification of concrete / Yu cu k thut ca btng:
When the trucks are arriving to site, the slump of concrete has to be checking. If
the slump of concrete reaches the requirement, casting concrete is carried out. And
taking test samples for compressive strength test of concrete is conducted in
accordance with the specification.
The concrete specification is attached in Appendix 3.
The required slump of concrete is 20020mm and the required flowtable is 550650mm when arriving on site. At least 4 concrete trucks achieved the above
requirements arrives on site before concreting.
Khi xe btng n cng trng phi tin hnh kim tra st. Nu st t
yu cu th tin hnh btng v cng tc ly mu th nghim kim tra cng
ca btng c tin hnh theo ng tiu chun k thut.

Page 19

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Tiu chun k thut ca btng c nh km trong ph lc 3.


Khi xe btng n cng trng phi tin hnh kim tra st. Nu st t
yu cu th tin hnh btng v cng tc ly mu th nghim kim tra cng
ca btng c tin hnh theo ng tiu chun k thut.
st yu cu ca b tng khi n cng trng l 20020mm, chy yu cu
ca b tng khi n cng trng l 550-650mm. Yu cu phi c 4 xe b tng
t yu cu k thut ( st, cp phi...) tp kt ti cng trng trc khi bt u
b tng.
2. checking the excavation bottom before casting/ Kim tra y h o trc khi
b tng
The sediment at the trench bottom shall be checked to reach the Specifications
requirement before casting concrete is allowed.
lng y h o s c kim tra v tha cc yu cu trong tiu chun k
thut trc khi btng.
In case the sediment at the bottom is over-limit, the Contractor will take the
proper measures to clean the bottom as follow: using the PDP pump and tremie pipe
to suck up the over-limit sediment layer at the bottom. In case these measures do
not work out properly, the steel cage will be lifted up and re-cleaning hole bottom.
Trong trng hp lng y h o vt qu quy nh cho php trc khi
btng, Nh thu s c bin php lm sch y h o, c th nh sau: s dng
my bm PDP cng vi ng btng bm lp lng qu mc cho php ti y
h o ln. Trong trng hp bin php ny khng lm gim lng, tan b lng
thp s c rt ln v y h o s c lm sch li.
3. Casting concrete of test pile / btng cc th
Concrete is poured into the trench through tremie pipes. The tremie pipes are
D270mm and are made up of coupled sections 0.5m, 1m, 2m and 3m in length. The
tremie pipes are divided into these dimensions to reach the following requirements:
- Giving the convenience of pipes combination while pouring concrete, guarantee
the submerged length of pipe in concrete.
- Easily arranging in tremie rack, keep the site tidy.
- Guarantee the lifting activities on safety due to the suitable dimension.
The tremie is attached with funnel lead directly concrete to bottom of trench. The
mixed concrete is poured directly to funnel from trucks. Pouring concrete to funnel
side (not directly pour a line to the bottom), at the bottom of funnel, the polymer

Page 20

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

slurry and the concrete are kept in separate by spongy plug or cellulose plug in order
to prevent the concrete from impuring by polymer slurry.
As the level of concrete in the trench rises, the tremie pipe column is raised
whilst always ensuring a minimum 3m embedment into the concrete.
Hn hp btng c vo trong h o qua ng tremie. ng tremie c ng
knh 270mm v c to thnh nhng on 0.5m, 1.0m, 2.0m v 3.0m di. Cc ng
tremie c chia vi cc chiu di nh trn vi cc mc ch sau:
- Thun li trong vic t hp ng , bo m chiu di ng ngp trong btng
khi btng.
- D dng lu tr trong gi ng tremie, bo m cng trng lun gn gng.
- Bo m an ton khi nng h ng tremie do kch thc ng tremie khng qu
ln.
u ng tremie c gn vo phu thu dn btng trc tip xung y h
o. Btng trn sn t xe trn s trc tip vo phu thu ny. Khi , rt btng
ngang vo thnh phu (khng rt trc tip vo hng xung y phu) ti y phu
lp sn mt nt chn bng xp hoc nt chn bng mt ca nhm ngn khng cho
btng trn ln vi dung dch polymer.
V cao b tng trong h dng ln, ct ng phi c ko ln sao cho phi
m bo ti thiu 3m ng c ngp trong b tng.
Mixed concrete with slump suits to tremie method is poured into funnel with a
slowly and steady line. In the progress, concrete level is continuously checked by
dropping reference. The results are showed on the monitoring chart includes depth
and volume. When necessary, some of the tremie pipe(s) will be cut to ensuring
tremie embedded into concrete 3m as least. By this way, the concrete will rise up
and replace polymer slurry in trench, and tremie embedment in the concrete control
will prevent the mixing of the polymer and concrete.
While casting concrete, a diary chart (time delivery, volume and level) is recorded
in the form has been approved by Owner and Consultant. The advantages of diary
chart are given the quantity prediction of concrete, preventing the high waste
material percenetage. In another hand, the diary chart also show the level where the
buldged concrete is existing, and it helps to estimate the equipment, material and
manpower for remedial work later. Test samples are taken to assess the strength of
concrete.
Btng trn sn vi st thch hp vi iu kin bng ng tremie s c
x vo phu bo m dng chy btng xung trong ng dn lin tc vi tc u

Page 21

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

v chm. Trong qu trnh , dng btng trong h o s c kim tra lin tc


bng cch th di. Kt qu thc t c biu hin trn biu lin h gia su
v th tch. Khi cn thit, mt s on ng tremie s c ct i trong khi vn bo
m ngp 3m trong lng btng. Vi cch ny, btng s dng ln v chim ch
ca dung dch polymer cng vi vic khng ch chiu su ngp vo btng ca ng
tremie s ngn chn c s trn ln gia polymer v btng.
Trong khi btng, nht k biu thi gian phn phi, th tch v cao trnh
btng c ghi li theo mu c Ch u t v T vn gim st ph duyt.
Nht k biu btng gip d dng c lng trc khi lng btng thc t cn
vo h o, trnh lng ph vt t. Nht k biu btng cng gip pht hin cc
v tr btng b ph, phc v cho cng tc sa cha v sau. Mu btng s c ly
nh gi cng btng.

Figure 5a Slump test and flowtable test


Hnh 5b - Kim tra st v linh ng ca btng

Page 22

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Figure 5b Casting concrete and taking test cubes


Hnh 5b btng v ly mu th cng
VIII. GROUTING (FOR SHAFT GROUTED PILES ONLY) / CNG TC PHT VA
(CH P CHO CC C PHT VA)
1. Grout Tubes / ng pht va:
Grout tube is 49mm outside diameter steel pipes and holes will be drilled - which
covered by 1 rubber sleeve per 1.0 meter will be fixed on the steel cage prior to
installation - called manchette. The pipe position will be secured by fixing them to the
rebar cage during the installation.
The rubber sleeves of the grout tubes will be opened with water under pressure
from 8 to 24 hours after concreting of the test piles and records will be kept in order
to show which sleeves have been successfully opened and at what pressure.
ng pht va l ng thp ng knh ngoi D49 c khoan nhng l nh c
gi l manchette, cc manchette ny c bo v bng ng cao su trn ng pht
vi khong cch 1.0 m v c lp t ln lng thp trc khi h xung h o. V
tr ca ng s c gi bi lng thp trong xung qu trnh h lng.
ng cao su bo v tng manchette s b ph bi nc p lc cao sau khong t
8 n 24 gi btng cc th v c ghi li nhng thng s v p lc ti mi
manchette sau khi ph nc xong.
2. Grouting Targets / Mc tiu v th tch ca cng tc pht va:
a) Grout Volume / Th tch va pht:
The target grout volume per manchette is 35litres/m2. The shaft grout zone is to
be measured from 500mm above the 1st manchette to 500mm below the bottom

Page 23

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

manchette. Should the target grout volume not be achieved in a particular manchette
then the manchette above, below or to the side will be injected with additional grout
so as to ensure that an overall minimum average grout take for the test pile is
greater than 25 litres/ m2.
Mc tiu v th tch cn t c ca cng tc pht l 35lt/m2. Khu vc pht
va c o t v tr 500mm pha trn manchette u tin xung v tr 500mm pha
di manchette di cng. Mc tiu cn t c v th tch va pht khng nh
gi da trn tng manchette ring bit m da trn th tch va trung bnh ca ton
b ng manchette trn cng mt cc th phi ln hn 25lt/m2.

3
4

8
7

Six manchettes are preferable to be grouted out of the total eight manchettes
installed per level. Rest of them is spare (2nd and 6th manchette).
Su ng manchette va c bm va trn tng s tm ng c lp t trn
cng mt cao trnh. Hai ng cn li s lm ng d phng (ng s 2 v ng s 6).
Particular procedures and stop criteria are presented in Appendix 5.
Cc bc chi tit v tiu chun dng tham kho Ph lc 5.
b) Grout Sequence and Backfill / Cng tc lp va:
Each tube will be grouted by using a PH2x5 grout pump or similar, until the stop
criteria in (a) above is met. After successful grouting the grout tubes will be backfilled
from the bottom upwards using tremmie method.
Mi ng bm pht s c pht bng mt bm PH2x5 hoc thit b tng t cho
n tiu chun dng bm nh nu phn a). Sau khi hon thnh cng tc bm
pht, ng ch bm pht s c lp y bng phng php va dng.
c) Mix composition / Cp phi va:
The grout mix to be used in the works will be the same as that used in the trial.
The mix per 100 litre of grout shall be as follows:
Cp phi va c thit k s dng cho cng tc khoan pht ging nh cp phi
trn th. Cp phi cho 100 lt va pht bao gm cc thnh phn sau:

Page 24

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Cement / Ximng

100 kg

Water / Nc

62.9 litres

Bentonite

0.57 kg

Bentocryl 86

143 ml (or equivalent additive / hoc tng ng )

Daracem 100

381 ml

A trial grout mix shall be carried out in accordance with the above mix proportion.
One sample of the grout from the trial mix shall be divided into two specimens and
each specimen shall be tested to show compliance with the density and viscosity
requirements as specified. Three sets of three nos. of 100 mm cubes shall be taken
and tested after 21 days strength per each grouting execution.
Va trn th nn tin hnh theo hn hp trn. Mt t mu va th nghim trn
th s c t cp phi trn tha mn cc yu cu v nht v t trng. Mi ln
khoan pht ly ba (03) t mu, mi t mu c ba (03) vin mu kch thc
100x100x100mm v nn sau 21 ngy tui.
Grout cube strength at 21 days shall be obtained from sets of three cubes and
the average for the pile shall be at least 20 MPa respectively.
Grout cube strength at 21 days ( average of three cubes) for the pile shall be at
least 20 MPa will be consulted for Loading test.
This value shall be used to justify the grout cube strength in mass pilling phase
later.
Cng ti thiu ca khi va vo 21 ngy t nht s l 20MPa, s c thu
thp t cc tp hp ba khi v tng ng tr s trung bnh.
Cng va trung bnh ti 21 ngy cho cc t nht s l 20MPa s c xem
xt cho vic th ti.
Kt qu ca cc th s c p dng cho giai on cc i tr m khng cn
trn th li.
3. Sampling and Testing / Ly mu v th nghim:
The sampling and testing will be carried out in accordance with the
Specifications. An Inspection and Test Plan will be discussed and agreed with the
Engineer prior to grouting works commencement.
Generally, three sets of three nos. of 100mm cubes shall be taken and tested
after 21 days strength at each shift (11 hours / shift) and the marsh cone viscosity

Page 25

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

and mud balance density of the grout shall be tested and recorded for every ten
batches or Engineers requirements.
Cng tc ly mu th nghim da trn tiu chun k thut. Mt quy trnh nghim
thu v th nghim mu c tho lun v c s ng ca t vn trc khi bt
u thi cng khoan pht.
Thng thng, c 3 t mu hnh hp kch thuc 100x100x100mm s c ly
trong mt ca lm vic (11 gi) v th nghim cng sau 21 ngy. Cc th nghim
v nht v t trng s c th nghim ghi li sau mi 10 m trn hoc c yu
cu ca t vn gim st.
4. Grouting Record / Ghi nhn qu trnh pht va:
To achieve the required accuracy in recording the grout volume and pressure, an
automatic recorder, namely the SINNUS System, will be used. / t c nhng
yu cu v th tch v p lc trong khi khoan pht, mt h thng t ng c s
dng c trn l ht thng SINNUS.
* The SINNUS System.
The SINNUS System is a fully electronic process, which can monitor the grouting
pumps. The grouting pressure is measured with an analog to numeric pressure
transducer, which has a measuring scale from 0 to 100 bars. The flow rate is
measured with an electromagnetic flow meter, which can measure any flow rate
(depending on the diameter of the grouting pipe). The instantaneous values
recorded by transducers and flow meter from each grouting line are transmited 100
times per second to the regulation box called Arc-SINNUS.
H thng SINNUS l mt t hp in t hon chnh iu khin my bm pht.
p lc ca va c o bng mt b bin i tnh hiu, mi ng h o t 0 n
100 bar, vi ng h ny c th o vi mi lu lng (ph thuc vo ng knh
ca ng khoan pht). Nhng gi tr hin th s c ghi li ngay bng b chuyn i
v my o dng cho mi ng khoan pht pht tn hiu 100 ln ti hp iu khin gi
l Arc-SINNUS.
The Arc-SINNUS receives the values from the pressure transducer and the flow
meter and sends to the display computer. Each Arc-SINNUS is able to manage two
(02) grouting lines. / Arc-SINNUS nhn gi tr t b chuyn i p sut v my o
lu lng truyn tn hiu n my tnh. Mi Arc-SINNUS c kh nng iu khin hai
(02) ng ng pht.
On the screen, each pump window displays the instantaneous values of volume,
pressure and flow rate. The real-time pressure and flow rate curves are also shown.
The operator uses the SINNUS system with the assistance of the computer to

Page 26

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

conduct the grout process in accordance with the pre-defined parameters (target
volume, target flow rate and limiting pressure) to ensure the best control of the
grouting works. Every value of volume, pressure and flow rate is recorded for
subsequent analysis.
Trn mn hnh, mi bm th hin gi tr tc thi ca th tch v phn loi dng
chy. Mi tng quan gia thi gian, p lc v dng chy c th hin bng biu
. Ngi vn hnh h thng Arc-SINNUS vi s h tr ca my tnh s iu khin
va i ph thuc vo h thng s mc nh ban u (th tch mc tiu, lu lng
mc tiu v p sut gii hn) m bo s iu khin ti u cho cng tc khoan
pht. Mi gi tr ca th tch, p sut v lu lng ca dng chy c ghi li cho
nhng phn tch tip theo.
The flowmeter is used by the computer to measure the volume of grout injected.
A site check will be carried out to verify the flowmeter at the required intervals. This
check involves pumping a set volume of water through the flowmeter into a
measuring vessel and checking that the measured volume equals the recorded
volume of the SINNUS system.
Thit b o dng c s dng bng my tnh o th tch ca va pht. Cng
tc kim tra trn cng trng nhm xc nh lu lng yu cu ca dng chy. Vic
kim tra ny bao gm mt my bm nc bm qua thit b o v kim tra th tch
tng ng vi th tch o c bi h thng SINNUS hay khng.
The following parameters will be recorded for each stage of grouting / Nhng
thng s sau y s c lu tr cho mi giai on khoan pht.
Date and time of beginning and ending of the stage / Ngy gi bt u v kt
thc mt giai on.
Pump number / S lng bm.
Grout hole number, stage number and depth / S l pht va, s giai on v
chiu su.
Accumulative volume of the stage / Th tch cng dn ca tng giai on.
Pressure during the open sleeve process and final pressure / p sut trong
sut qu trnh m ng cao su v p sut cui cng.
Total grout volumn / Tng lu lng.
The causes of pump stop, automatic or manual / Nguyn nhn ca vic dng
bm, iu khin tt my t ng hay bng tay.

Page 27

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

X. EQUIPMENT / THIT B THI CNG


A full list of equipment necessary to carry out the works is given as follow / Danh
sch y cc thit b cn thit cho thi cng bao gm:
Excavation crawler crane ( LIEBHERR 872)
Cu o
Drilling-machine ( SUMITOMO)
Xe khoan
Clamshell or grab
Gu ngom
Polymer mixing unit
My trn polymer
Polymer storage: silo(s) or reservoirs
Lu tr dung dch polymer: thng cha hoc b cha
Various pumps and tremie pipe for pouring concrete
Cc loi bm, ng tremie phc v cho vic btng
Shaft grouting equipment includes:
Cc thit b phc v cng tc pht va bao gm:

Computer and Sinnus system / My tnh v h thng Sinnus.


Pumps, flowmeters and pressure sensors / My bm, ng h o lu
lng va v ng h o p sut.
Mixer and Mission pump / My trn va v my o va.
Hose winder and packer / Xe bm v thit b bm.

Mud laboratory
Dng c th nghim
Offices, workshops and others.
Vn phng, kho v nhng vt dng cn thit
The number of excavation rigs will be adjusted depending on the construction
period, the soil condition and the available room. / S lng thit b thi cng s c
iu chnh ty thuc vo giai on thi cng, iu kin a cht v khng gian thc t
trn cng trng.

Page 28

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Figure 7a Excavation crane and Grab for Barratte piles


Hnh 7a Cu o v Gu o cho cc barrette

Figure 7b - The Equipment bored piles/ Thit b khoan cc trn


D. INCIDENT SOLUTIONS / CNG TC X L S C TRONG THI CNG
I. TREMIE CLOGGING SOLUTION / X L S C KHI TC NG
The tremie pipes are blocked when casting concrete is happened rarely, but the
method to prevent the incidents have to be prepared:
Vic tt ng btng tuy him khi xy ra nhng cn phi phng nga trnh s c
xy ra nh:
Well-prepared in tremie pipes: the quality of product and the spare pipes; and
the ability of concrete suppiler, the quality of concrete (slump, flowable,)

Page 29

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Chun b tt mi khu lin quan cht lng ng btng, s lng ng d


phng, kh nng cung cp btng, cht lng btng ( st, linh
ng,)
Monitoring closely the casting concrete execution.
Kim tra cht ch cc thao tc trong qu trnh v rt ng btng.
If the tremie pipes are blocked, the solution is / Nu b tt ng btng phi thc
hin cc thao tc sau y:
Determine the concrete level, calculating the length of tremie pipe which is
embeded in concrete to give the space in which the tremie pipe can be
compacted.
o chnh xc cao btng trong h o, chiu di ng ngp trong
btng quyt nh chiu cao nng h ng.
Using the wood bar to hit the tremie pipe body or compact the tremie pipe to
push the concrete out or use in parallel. The lifting and compacting of tremmie
pipe must be guaranteed the 2 to 5 meter embedment into concrete.
S dng v g g vo thnh ng hoc dng bin php ko ln h xung
nhanh btng tt ra, thng thng vic x l tc ng nn kt hp c 2
phng php ny. Qu trnh nng h ng nhanh phi bo m chiu su
ngp ng trong btng t 2-5m.
Do not shake the tremie pipe in horizontally or metal bar to hit the tremie pipe
body.
Nghim cm vic lc ngang ng hoc dng n hoc vt kim loi g vo
thnh ng.
The following steps are carried out when the above mention is not effect / Khi cc
gii php s dng trn khng c hiu qu, th gii php sau c th thc hin:
Determine the concrete level when the clog happens
Xc nh chnh xc cao mt btng khi b tc ng.
Determine the bottom level of tremie pipe when the clog happens
Xc nh cao mi ng tremie ti thi im b tc ng.
Lift up whole the tremie pipe, then clean the pipes body
Rt ton b ng tremie ln, thng ng v lm sch ng.
Again measure the concrete level in order to calculate the length of tremie
pipe that needs to lower back

Page 30

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

o li cao mt btng xc nh chiu di ng cn h xung tr li.


Lower the tremie pipe contact the concrete surface in trench
t li ng tremie chm mt btng.
Pouring concrete enough to replace the polymer slurry in tremie pipe V = 0.07
x x 0.32 x L (L: is calculated from polymer level to concrete level)
lng btng y ton b lng polymer chim ch trong lng ng
V = 0.07 x x 0.32 x L (vi L l chiu di ng k t cao mt polymer
n mt btng).
Embedding the tremie pipe in to concrete about 0.5m depth
n cho ng ngp su vo khi btng khong 0.5m.
Connect more pipes and push the pipe into concrete as least 2m
Ni thm ng v nhn su xung ti a 2m vo khi btng
Continue to casting concrete, the tremie pipe must be embedded into
concrete 3m at least during the construction until reach the concrete level.
Tip tc btng bnh thng, m bo mi ng ngp trong phn btng t
nht 3m cho n khi t c cao trnh ngng .
II. OVERCOMING OBTACLES SOLUTION / X L KHI GP VT CN KHI O
Dependent upon the nature and size of the obstruction, several alternative
methods can be adopted for removal of obstacles / Ty thuc vo bn cht v kch
thc ca chng ngi vt, mt vi phng php c chn di di chng ngi
vt:
a) By grabbing where the size of the obstruction is compatible with the size of the
grab;
Bng cch o nu kch thc chng ngi vt tng thch vi kch thc gu
ngom;
b) By alternative use of the grab and heavy chisel;
Bng cch s dng lun phin gu ngom v ba c nng;
c) By drilling in order to weaken the obstruction prior to use of the grab/chisel as
item b).
Bng cch khoan lm yu chng ngi vt trc khi dng gu ngom, ba
c nh mc b).

Page 31

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

The most frequently used methods are those listed above under item a) and b).
All three methods have been used successfully, however, during the construction of
numerous piles in Hong Kong, Singapore, Malaysia and Vietnam.
Cc phng php thng c s dng nht c lit k trn l mc a) v b).
Tuy nhin, c ba phng php c s dng thnh cng trong vic thi cng cc
Hng Kng, Singapore, Malaysia v Vit Nam.
For obstacles removal, in specially, the mass obstacle or bar which has the
dimension extend the perimeter of trench, it has to pay attention about stability of
trench when removing and excavating in next phase. If the trench side has collapsed
in small area, the density of polymer slurry is increased or installing casing in the
collapsed position if it is nearly the ground level.
Vic x l ly chng ngi vt ln, nht l i vi cc dng khi ln hay thanh
di nm ln khi bin thnh l, phi ch n n nh ca thnh l khi ly
chng ngi vt ln v sau khi o tip phn bn di. Nu khu vc ny b l thnh
h o phi tng cng x l vi dung dch polymer t trng cao hoc h ng vch
thm khi khu vc st l (nu khu vc st l nm su khng qu 6m so vi ming
h o).
III. TRENCH COLLAPSE SOLUTION / X L KHI SP THNH H O
The trench can collapse in the following cases / Sp thnh h o thng xy ra
trong cc trng hp sau:
Before pouring concrete / Trc khi btng:
The collapse happens near the guide wall surface level due to the vibration of
vehicles and the low pressure of polymer lurry to trench sides. / Sp thnh h
o gn cao trnh t tng dn v cao trnh ny c nhiu chn ng do
xe o gy ra, ng thi do p lc dung dch polymer ln thnh h o thp
hn so vi cc im bn di.
The collapse happens in the trench / Sp thnh trong lng h o.
The preventing and repairing solutions are / Khi gp trng hp ny th bin
php phng nga v x l l:
The unnecessary equipment will be removed out of trench diameter with a
safe distance / Trc khi o, cc trang thit b khng cn thit s c di di
ra xa phm vi ming h o.
Increasing density of polymer slurry supplied to trench / Tng t trng dung
dch polymer cung cp cho h o.

Page 32

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Using pumping concrete method in stead of pouring concrete method. If the


collapse is serious, the trench is backfilled by stone / gravel and will be
excavated after 24 hours. / S dng btng bm thay v x btng. Nu h
o b sp nghim trng, lng h o nn c lp y bng v o li
sau 24 ting.
During pouring concrete period / Trong khi btng:
In this case, the concrete is poured without stopping to push the contaminated
concrete out of trench. In another hand, requiring suppliers increase the slump of
concrete above 180mm. / Trong trng hp ang btng m thnh h o b st
th vn tip tc btng, ng thi yu cu nh cung cp btng iu chnh st
ca hn hp btng sao cho t t 180mm tr ln, d dng y btng xu ln
khi h o.
IV. WAITING FOR CONCRETE SOLUTION / X L KHI CH BTNG
The concrete pouring process is interrupted, the concrete in trench is compacted
every 15 to 20 minutes by tremie pipe while wating new supplying concrete. / Nu
qu trnh btng b gin on, trong lc ch btng tip, c 15 n 20 pht
dng ng btng nhi btng 1 ln.
The concrete pouring process is interrupted due to two following reasons /
btng b gin on c th l do hai nguyn nhn sau:
Objective: because of traffic jam, incident at supplying station. The spare
supplying station is required to prevent the interruption extend more than 2
hours.
Khch quan: do tc ng, do s c ti trm cung cp btng. Trm trn
btng d tr lun trong tnh trng sn sng tip tc cung cp btng,
trnh trng hp ch btng qu 2 gi.
Subjective: because of equipment. The equipment is required to be under the
working condition and replace immediately if they are broken to ensure the
interruption does not extend more than 2 hours.
Ch quan: do s c v my mc thit b. Nh thu c trch nhim bo m
cc my mc thit b lun hot ng tt v thay th ngay cc my mc thit b
v tip tc btng trong khong thi gian 2 gi.
V. TREMIE PIPE FALLING SOLUTION / X L KHI RI NG BTNG
When the tremie pipe falled in trench, the falled parts are left and removing the
rest ones. Then, lengthening the rest ones and lowering them to trench again, the
following steps are carried out as the tremie clogging solution. It is paid attention on
the length of tremie pipe submerged in the concrete, as least 3m is required.

Page 33

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Trng hp ng btng b ri th b phn ng b ri, rt phn cn li ca ng


ln. Sau ni di v h ng xung v trnh t cc bc tip theo tng t trng
hp b tc ng. Lu ng btng phi c h n ng cao trnh ng b rt v
ngm su 3m trong btng.
VI. INCLINING TRENCH SOLUTION / X L KHI H O KHNG THNG
The reparation is done immediately (with grab, chisel) when the inclination of
trench extends the specification.
Khi nghing ca h o vt qu gii hn cho php, cng tc sa cha h
o c tin hnh ngay bng cc dng c cn thit (gu o, ba c) bo
m thng ng ca h o.

Page 34

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

APPENDIX 1 - POLYMER TECHNICAL CHARACTERISTIC AND TESTING


FREQUENCY & MSDS
PH LC 1 - TN S KIM TRA V C TNH K THUT CA POLYMER &
THNG S AN TON VT LIU
FRESH
POLYMER
DUNG DCH MI
TRN

AS SUPPLIED
TO PANEL
DUNG DCH
TRONG H KHI
O

SAMPLE FROM
PANEL PRIOR TO
PLACING
CONCRETE
TRC KHI
BTNG

Mud balance
Cn t trng

1.00

1.00 to 1.10

1.00 to 1.10

Viscosity
(second)
nht (giy)

Marsh cone
1500 / 1000
Cn o nht

50 to 80

50 to 80

50 to 80

Sand content
(%)
Hm lng ct

Sand screen set


B o % ct

Irrelevant
Khng thng
xuyn

Irrelevant
Khng thng
xuyn

< 2%

pH

pH paper
Giy pH

8 to 12

8 to 12

8 to 12

Once per day


1 ln / ngy

Once per day on


sample coming
from reservoirs
or silos
1 ln / ngy cho
mu ly t b
cha hoc silo

Once per trench prior


to concreting
Mt ln cho mt h
o trc khi
btng

PROPERTY TO
BE MEASURED
CC THNG
S KIM TRA

TEST METHOD
AND
APPARATUS
DNG C KIM
TRA

Density (g / ml)
T trng

Frequency of
tests
Tn sut th
nghim

Page 35

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

APPENDIX 2 ACCEPTANCE PROCEDURE AND TIME FRAME FOR ENGINEERS


SIGNATURE
PH LC 2 QUY TRNH NGHIM THU V THI GIAN K CHP THUN NGHIM
THU
ACCEPTANCE PROCEDURE
QUY TRNH NGHIM THU
1. START / BT U
The contractor submit the
inspection request to the Engineer
Nh thu trnh phiu yu cu
nghim thu ti nh t vn
2. Inspection of location and
polymer / Nghim thu nh v
h o v polymer cp cho h
o
3. Excavation /
Cng tc o
4. Inspection of trench depth /
Nghim thu chiu su h o
No /
Cha t

5. Inspection of trench depth


after cleaning trench bottom /
Nghim thu chiu su h o
sau khi lm sch y.

6b. Steel cage


installation / Lp t
lng thp

7. Inspection of trench depth


before concreting / Kim tra chiu
su h o trc khi btng

8. Pouring concrete /
btng
9. Cracking & Shaft
grouted / Ph nc v
pht va

10. END KT THC


Inspection of quantity
/ Nghim thu khi
lng hon thnh

Yes / t
6a. Approval of steel cage, sonic
tubes / Nghim thu lng thp,
ng siu m

TIME FRAME FOR ENGINEERS SIGNATURE

Page 36

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

THI GIAN K CHP THUN NGHIM THU


No
.

Activities / Nghim thu


Inspection form will ne
submitted to Engineer as
least 12 hours in advance.
Phiu yu cu nghim thu
c nh thu gi n nh
t vn trc 12 gi ng h

HP

W
P

4
6A

6B

Inspection / Record
forms
Bin bn nghim thu
Request of inspection /
approval.
Phiu yu cu nghim
thu

Inspection of location /
Nghim thu cng tc nh v

BMTC-01

Inspection of polymer /
Nghim thu polymer

BMTC-04

Inspection of excavaiton /
Nghim thu cng tc o
Inspection of polymer /
HP
Nghim thu polymer
Inspection of steel cage
HP fabrication / Nghim thu cng
tc gia cng lng thp
Inspection of steel cage
W
installation / Nghim thu
P
cng tc lp t lng thp
Inspection of trech depth
W before concreting / Nghim
P thu chiu su h o trc
khi btng.
Inspection of concreting /
W
Nghim thu cng tc
P
btng.
Inspection of cracking & shaft
W
grouting / Nghim thu cng
P
tc ph nc v pht va

BMTC-02
BMTC-04
BMTC-03

BMTC-03

BMTC-05A

BMTC-05A/B

BMTC-07A/B
BMTC-08A/B/C

Page 37

Time / Dead line


Thi gian nghim
thu
The Contractor
sends the request
as least 12 hours in
advance.
Nh thu gi phiu
yu cu nghim thu
trc 12 gi ng
h
Engineer consultant
signs immediately
after checking. / K
s T vn k ngay
sau khi nghim thu.

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Inspection of quantity /
Nghim thu khi lng hon
thnh.

BMTC-06A/B

10

Chief
consultant
signs
within
24
hours
after
concreting finished.
T vn trng k
nghin thu khi
lng hon thnh
trong vng 24 ting
sau khi kt thc
cng tc btng.

Note / Ghi ch:


1) Hold point / im nghim thu (HP)
The Contractor shall not progress the Works beyond the hold point until otherwise
advised by the Supervisor. The Contractor shall advise the Supervisor in due time to
maintain the progress of the Work in a continuous line during the hold point.
Nh thu s khng tip tc cng vic tip theo n khi nhn c kin cho php
t nh t vn. Nh thu s tham vn Nh t vn kp thi cho cng vic bo m tin
, khng b tr hon qu lu v ch ph duyt.
2) Witness point / im chng kin (WP)
The Contractor shall advise the Supervisor to witness or measure progress and
workmanship of the Works, at his discretion. The Contractor shall advise the
Supervisor in due time to maintain the progress of the Work can a the continuous
line during the witness point.
Nh thu s mi nh t vn chng kin hoc nh gi vi chuyn mn quan im
ca mnh. Nh thu s tham vn Nh t vn kp thi cho cng vic bo m tin ,
khng b tr hon qu lu v trong qu trnh chng kin.

Page 38

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

APPENDIX 3 - GENERAL SPECIFICATION OF TREMIE METHOD CONCRETE


SUPPLY
PH LC 3 - YU CU K THUT I VI B TNG THNG PHM BNG
NG TREMMIE
GENERAL SPECIFICATION FOR TREMIE MIX CONCRETE SUPPLY
YU CU K THUT I VI B TNG THNG PHM BNG
NG TREMMIE
I. SPECIFICATION FOR DELIVERY / YU CU V CUNG CP
All deliveries shall be made in accordance with sites order. The Supplier will
provide the necessary quantity and organize the transportation facilities in such a
way that all requirements will be respected to follow:
Expectant dates and quantity is provided in 24 hours before concreting
Expectant time and quantities must be confirmed the day before concreting.
Exactly time to be confirmed with 1.5 hours notice in advance within the pre
booked approximate time.
Ton b vic cung cp phi tun theo yu cu t hng v btng. Nh cung
cp b tng phi cung cp khi lng v phi t t chc vic vn chuyn b tng
t nh my n cng trng theo ng thi gian cam kt v ph hp vi cc yu
cu i vi b tng.
Ngy v khi lng cung cp d kin phi c ln k hoch trc 24 gi.
n v thi cng s khng nh khi lng c th trc 1 ngy.
Thi gian b tng chnh xc s c n v thi cng cam kt khng nh
trc 1.5 gi Nh cung cp chun b v cp b tng n cng trng
II. RATE OF DELIVERY / TC CUNG CP B TNG
Pouring rate will be as follow / Tc cung cp c yu cu nh sau:
a) A minimum of 4 trucks which delievers required quality concrete present on
site at the beginning of each concreting. The next trucks must be on time to ensure
the execution is carried out without any obstruction.
Ti thiu phi c 4 xe b tng c st v tnh cng tc tt nht c mt cng
trng trc khi bt u b tng. Cc xe b tng tip theo phi c mt ng lc
m bo vic b tng khng b gin on v ch.

Page 39

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

b) Quantity after the first 4 trucks to be supplied at a rate from 60 to 80 cubic


meters per hour, according to BSV Sites instruction.
Tc cp b tng sau 4 xe u tin phi t t 60-80m3/gi, v phi theo s
hng dn iu phi ca bn n v thi cng.
c) Any started pour must be carried out up to completion in a non-stop operation,
unless otherwise instructed by Site Engineer.
Vic cp b tng phi m bo vic phi lin tc tr khi c nhng ch dn
khc ca k s cng trng.
We outline the importance of strictly respecting the above rules as stoppage or
slowing of concreting rates may lead to complete failure of our work.
Vic a ra nhng yu cu v quy nh nu trn trnh/hn ch n mc ti
thiu nhng ri ro xy ra cho cng tc thi cng b tng v nhng ri ro ny c th
dn n vic thi cng b tng khng th hon tt.
III. MIXED CONCRETE CHARACTERISTICS / C IM YU CU CA B TNG
THNG PHM
The characteristics of mixed concrete shall comply with local and international
regulations and standards, in particular the current Building Construction
Regulations and / or all other requirements specified under the Contract. In addition
to the above, please note that we require the following to be taken into account.
Cc c im yu cu ca b tng thng phm phi tun theo cc yu cu v
b tng nu trong tiu chun k thut v cc quy nh, tiu chun hng dn ang
c p dng trong nc v quc t. Bn cnh cn phi nhn mnh nhng ch
tiu sau y
1-Water/Cement ratio value: 0.4
T l Nc/Xi mng: t 0.4 n 0.45
2-PFA content if used: should not be more than 25% of cementitious content
T l thnh phn PFA (nu dng): Khng ln hn 25%
3-Cement content / Hm lng xi mng
for Grade 50: form 450 - 500 kg/m3 / Vi mc 50Mpa: t 450 - 500kg/m3
4-Sand + fine / aggregates ratio: Not less than 0.4 in weight
T l ct + ct liu mn / ct liu th: Khng nh hn 0.4 tnh theo trng lng
5-Aggregate size: not larger than 20 mm

Page 40

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Kch thc ct liu th: Khng ln hn 20mm


Delivery should be in line with the accepted and approved trial mix, within
regulated tolerances.
Cc c tnh ca b tng giao n cng trng cho thi cng phi ph hp vi
b tng trn th c Nh t vn ph duyt.
IV. CONCRETE CHARACTERISTICS / CC C IM CA BTNG
The Supplier is fully responsible for achieving the required strength, flow
characteristics and slump of concrete. Concrete characteristics for foundations are
different from superstructure concrete as much that high workability must be
attained.
Nh cung cp trong phm vi trch nhim ca mnh phi cung cp loi btng c
cng , chy v st theo yu cu. Cc c tnh yu cu i vi btng
dng cho thi cng cc, c bit l yu cu v tnh cng tc ca btng, khc hon
ton vi yu cu v btng cp cho phn kt cu thng tng khc.
Flow table test is the dominant test to check concrete characteristics with figures
between 550 and 650 mm.
chy s c coi l ch tiu kim tra chnh, m bo yu cu l t 550 n
650mm.
A good workability is obtained for slump of 200 mm with figures between 180 and
220 mm still acceptable. Concrete from the first four trucks must have slump from
180 to 220mm and flow from 550 to 650mm.
Tnh cng tc ca btng cn c kim tra qua ch tiu v st, l tng l
200mm, v t yu cu khi t 180mm n 220mm. 04 xe b tng u tin phi
c st t t 190-220mm chy t 570-650mm.
The workability of the concrete needs to be maintained for a period at least 4
hours in excess of the anticipated pouring duration.
m bo tnh cng tc ca btng cho thi cng, st ca btng cn c
duy tr t nht l 4 gi ngoi thi gian cn thit cho thi cng.
The Supplier shall propose, and be responsible for the coded mix design of the
concrete in order to meet the requirements of strength, workability and stability of the
mix. This composition must be submitted for approval. The mix design is subject to
the approval of the Engineer or the Clients Representative.
Nh cung cp phi a ra c cp phi (c m s) tha mn cc yu cu nu
trn v chu trch nhim p ng c cng theo thit k v m bo duy tr

Page 41

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

c s n nh ca thit k ny sau khi trnh Nh t vn/ Ch u t v c Nh


t vn/Ch u t ph duyt.
V. CONCRETE TESTING / TH NGHIM KIM TRA CHT LNG B TNG
As far as workability of the concrete is concerned, the Supplier shall note that
BSV will perform the following tests. The minimum / range value to be reached for
each type of test is specified hereunder.
Theo thng nht v vic kim tra tnh cng tc ca b tng k trn, Nh cung
cp phi m bo rng n v thi cng s c ton quyn trong vic kim tra cht
lng ca b tng cp n cng trng cng vi s gim st ca Nh t vn. B
tng phi ti thiu t c cc ch tiu nh bng quy nh sau y
The Supplier is to maintain an experienced and competent staff on Site during all
deliveries to bear witness to all concrete tests and inspect the concrete quality.
Nh cung cp phi c n cng trng mt nhn vin c kinh nghim v trnh
gim st, chng kin v kim tra cht lng b tng trong sut qu trnh cung
cp.

TESTS TO BE CONDUCTED ON SITE FOR FOUNDATION CONCRETE


CC PHP TH C THC HIN I VI BTNG
Test /
Phng
php th

Flow Table
test
(Dynamic
workability
test)
/ Th
chy (Tnh
cng tc
trng thi
ng)

Reference / Ti liu
tham kho

Acceptable
range of value /
Gi tr t yu
cu

BS 1881, part 105,:


Method for
determination of flow

Frequency / Tn sut kim tra

On every trucks supply to site

Tiu chun BS1881,


phn 105 Phng php
xc nh chy

Min = 550 mm

Add on photos from BS


1881, part 105 : 1984
version
(see appendix 1)

Max = 650 mm

Ti thiu l
550mm

Ti a l 650mm

Minh ha bng hnh nh

Page 42

p dng i vi mi xe b tng
cp n cng trng.
Concrete sample is to be taken to
test during the pouring time.
Btng ca xe u tin c
ly mu kim tra trong sut
qu trnh btng.

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

TCXDVN 326-2004 and


TCVN 3106-1993

Slump test
/ Th
st

CSI 1990, Construction


Standard, Testing
Concrete : Section 2:
Determination of Slump
Tiu chun
TCXDVN326-2004 v
TCVN 3106-1993

On every truck
p dng i vi tt c cc xe
Min = 180 mm

Slump lost of first truck

Ti thiu 180mm

Th mt st ca xe u tin

Max = 220 mm

Concrete sample is to be taken to


test during the pouring time.

Ti a 220mm

Btng ca xe u tin c
ly mu kim tra trong sut
qu trnh btng.

CSI 1990 Tiu chun xy


dng Phn 2
Xc nh st
Screen
Stability
test / Th
tnh n
nh ca
btng

See appendix 3

Max = 0.15

Only if necessary

Xem ph lc 3

Ti a l 0.15

Ch khi cn thit

When the workability test result is out of acceptable range of value a second test
will be conducted not more than 15 min after the first test. If the second one fails
again, the truck is rejected.
Nu kt qu kim tra tnh cng tc ca b tng khng nm trong phm vi gii
hn cho php th vic kim tra s c tin hnh 15 pht sau ln th u tin. Nu
ln th 2 cho kt qu khng t th xe btng khng c chp thun cho .
VI. QUANTITIES DELIVERED / KHI LNG B TNG CUNG CP
Quantities paid are the quantities actually delivered and accepted on site. Each
truck arrives on site have to be attached the approved mix composition code.
Khi lng btng cp l khi lng thc t giao n cng trng c cc bn
kim tra v xc nhn ngay sau khi vic btng kt thc. Mi xe giao n cng
trng u phi km theo cp phi c m s c duyt.
BSV reserves the right to measure the real quantity of concrete on any truck
delivering to the site.

Page 43

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Nh thu BSV c quyn kim tra theo cch ca mnh khi lng b tng cp n
cng trng.
Should there be a discrepancy between the real volume measured and the
theoretical volume, BSV would be entitled to make a discount on the previously
delivered quantities on that day.
Nu c s sai khc gia khi lng thc t o c v khi lng ghi trn phiu
xut th Nh thu BSV c quyn tr ton b khi lng chnh lch vo tt c cc xe
cp cho ngy hm .

Page 44

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

FLOW TABLE TEST SPECIFICATIONS


Extraction of BS 1881:1985 part 105: Method for determination of flow

Page 45

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

SCREEN STABILITY TEST


Test for characterization of segregation of self-compacting concrete
TH NGHIM N NH B MT
Th nghim cc c tnh phn tng ca b tng t m
1. PURPOSE OF TEST/ MC CH CA CNG TC TH NGHIM
The purpose of this test is to qualify self-compacting concrete with respect to the
risk of segregation. It can be used when self-compacting concrete mix designs are
prepared in the laboratory, or to check the stability of concrete delivered on site.
Mc ch ca th nghim ny l xc nh cc iu kin b tng t m
gim thiu cc nguy c ca s phn tng ca b tng trong cu kin. Vic ny c
th s dng thit k b tng t m ti phng th nghim hoc kim tra cht
lng b tng khi n cng trng.
By characterizing stability, this test complements the tests used to assess flow
ability in confined or unconfined situations.
c trng cho s n nh, th nghim ny b sung cho cc th nghim c s
dng nh gi kh nng chy ca b tng trong cc tnh hung.
Mix design/ Thit k cp phi
Take several measurements for different water contents. Then draw the curve
with the values obtained for the different quantities of water. The curve can then be
used to assess a range of slump flows corresponding to a range of water contents
for which the mix is suitable in terms of segregation and bleeding, in accordance
with the acceptance criteria defined below.
Thc hin th nghim cho mt s thnh phn nc nc khc nhau. Sau th
hin thnh nhng biu ng cong qua cc gi tr thu c bit s lng
khc nhau ca nc. Qua biu ny c th phn loi v nh gi thnh phn
nc ph hp v nhng yu cu tch nc, chy nc theo cc tiu ch chp thun
theo cc quy nh di dy:
On-site concrete inspection/ Nghim thu trn cng trng.
Refer to the acceptance criteria defined below/ Theo cc tiu ch v nghim thu
c th hin di y.
2. EQUIPMENT USED/ THIT B S DNG:
10 l bucket + lid/ thng 10 lt + np

Page 46

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

5 mm screen, 315 mm diameter + pan/ Tm dy 5mm, ng knh 315mm


v cho.
Scales-accurate to within 20 g, minimum range 20 kg./ Cn-chnh xc
trong vng 20 g, ti thiu khong 20 kg.
3. TEST PROCEDURE/ QUY TRNH TH NGHIM:
Sampling/ Mu th:
In the laboratory/ Trong phng th nghim:
On site, mix and pour 10 l of concrete directly into the bucket/ Ti cng trng,
trn v rt b tng trc tip vo thng 10 lt.
Waiting time between stoppage of mixer and sampling: < 30 s
Thi gian ch t khi dng trn n khi ly mu <30s
On site, ready-mixed concrete supplied by truck:/ Ti cng trng, b tng ti
c cung cp bi xe bn.
Mix at high speed for 1 minute/ Trn vi tc c cao trong 1 pht.
Fill the bucket with 10 l of concrete directly from the trucks chute/ y vo
thng 10 lt bng phng php trc tip t mng xe bn.
On site with mixing plant, placement by skip/ Ti trm trn, thay th bng cch.
Sample 10 l of concrete from the top of the skip to fill the bucket, using a
cylindrical scoop,/ Ly 10 lt b tng mu y thng bng xng.
Cover the bucket to prevent the concrete drying out, / y np thng li
trnh cho b tng b kh.
Wait 15 mn,/ Ch 15 pht.
Weigh the pan and the empty screen/ Cn cho v tm dy 5mm.
Weight the pan alone / Khi lng cho.
Place the screen + pan on the scales/ t cho v tm dy 5mm ln cn.
Zero the scales/ Cho gi tr cn v 0
Inspect the surface of the bucket for clear bleed water after 15 mn and record
it if there is any/ Kim tra b mt ca thng kim tra s r nc sau 15 pht,
nu c th ghi li.

Page 47

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Pour 4.8 kg of concrete (0.2 kg) onto the screen; pour it onto the center of
the screen from a height of 50 cm 5 cm/ Rt 4,8kg b tng ( 0.2kg) vo
tm dy 5mm. Rt vo trung tm ca tm t cao khong 50cm 5cm.
Record the weight of the sample as shown,/ Ghi chp li khi lng ca mu.
Wait 2 mn,/ Ch 2 pht.
Zero the scales,/ iu chnh cn v khng.
Weigh the pan with the slurry; / Khi lng ca cho vi dung dch
Calculate

Pslurry = Ppan + slurry Ppan

Cng thc tnh: Khi lng dung dch = Khi lng cho v dung dch- khi
lng cho.
calculate the percentage of slurry by weight relative to the weight of the
sample/ Tnh t l phn trm ca khi lng dung dch v khi lng ca
mu theo cng thc:
=

Plaitance x 100
Psample

4. ACCEPTANCE CRITERIA/ TIU CHUN CHO PHP


N.B. The following criteria are particularly applicable to the use of selfcompacting concrete in vertical elements.
Tiu chun di y l c p dng c bit cho vic s dng b tng t dm
vi cc cu kin ng (nh ct, cc).
Measurement of the percentage of slurry classifies self-compacting concrete mix
designs as follows/ o t l phn trm ca dung dch phn loi b tng t m theo
bng sau:
Pslurry Value

Stability factor

Status

Gi tr

Yu t n nh

Tnh trng

0% % Pslurry 15%

satisfactory stability

Truck accepted

n nh

Chp nhn xe bn.

Page 48

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

15% % Pslurry 30%

critical stability
Km n nh

carry out segregation test in


situ
Thc hin phn tch tnh trng
ca b tng.

% Pslurry > 30%

very poor stability :


systematic segregation,

Concrete unusable,
Truck rejected

Rt km n nh,

B tng khng dng c, loi


b.

In addition, it is not acceptable if bleed water is detected during the test. This
induces a risk of settlement, of washing out, and of modified permeability.
Ngoi ra, trong qu trnh th nghim c xut hin hin tng chy nc cng
khng th chp nhn c. iu ny gy ra nguy c phn tng ca b tng v/hoc
xut hin s thay i v m.

Page 49

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

APPENDIX 4 - SHAFT GROUTING INSTRUCTIONS AND STOP CRITERIA


PH LC 4 - CNG TC KHOAN PHT, CH DN V TIU CHUN DNG
TYPICAL SHAFT GROUTING INSTRUCTIONS AND STOP CRITERIA
SHAFT GROUTING INSTRUCTIONS
The two critical parameters for the shaft grouting are volume and pressure.
Hai thng s cn quan tm khi tin hnh pht va l th tch bm va v p lc
bm.
*Maximum volume per sleeve / Th tch yu
cu
Calculation of grout volumes per manchette for 35 litres per m2 / Th
tch va bm tnh ton ca mi cc: 35 lt / m2
1
8

3
4

axb
7

Six out of the eight manchettes at each level are to be grouted. Holes 2 and 6 are
spare tubes to be grouted in the event that one of the other tubes cannot be
grouted
Su trn tm l trn cng mt mt ct s c pht va. L s 2 v l s 6 s
c dung d phng trong trng hp cc l cn li khng th bm va.
Theory target volume for sleeve / Th tch l thuyt cho mi l
For barrette pile a x b section as followings / i vi cc c kch thc: a x b nh sau
Volume per sleeve / Th
tch trn mt l

= 35 x (a+b)x2x
1.0/ 6

= S litres per sleeve / lt trn l

For bored pile a diameter as followings /


i vi cc khoan nhi c ng knh a nh
sau
Volume per sleeve / Th tch trn mt l = 35 x 1.0 x a x / 4 = S litres
per sleeve / lt trn l
Limiting Pressure / p lc gii hn

Page 50

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

The limiting pressure shall be set at 40 bar


SHAFT GROUTING STOP CRITERIA / CC CH TIU DNG BM VA
There are three stop criteria for the grouting / C 3 ch tiu dng bm va c p dng:
- Maximum volume is reached (as defined above) / Th tch
ln nht ca mt l (nh tnh ton trn)
- Limiting pressure is reached (as defined above) / Gi tr p
lc gii hn (nh trn)
- Resurgence (grout flowing back up to the surface) is identified. / S tro
va c pht hin trn mt t.
In case of resurgence adopt following procedure / Trong trng hp s tro va c pht
hin, cc cng tc sau c tin hnh:
- Inspect pumps to identify source of problem / Kim tra my bm tm nguyn
nhn va tro.
- Remove and clean faulty pipes / Rt ng ln v v sinh ng.

Page 51

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

CRITERIA FOR GROUTING WORK ACCEPTANCE METHOD STATEMENT


BIN PHP & TIU CHUN BM VA CC I TR

A. GENERAL INSTRUCTION / GII THIU CHUNG


B. ACCEPTANCE CRITIERIA OF GROUTING WORK COMPLETION / CC TIU
CHUN XC NH HON THNH BM VA
1. Shaft grouting area / Din tch bm va
2. Designed grouting volume / Th tch bm thit k
3. Designed grouting volume per sleeve / Th tch bm qua l pht
4. Stop & approved criteria of grouting work completion / Tiu chun xc nh
vic hon thnh bm va cho mt cc.
C. RULES OF GROUTING WORK / QUY TC BM VA
D. RULES OF COMPENSATION GROUTING / QUY TC BM B
1. Condition of compensation grouting / iu kin bm b
2. Rules of compensation grouting / Quy tc bm b

A. GENERAL INSTRUCTION / GII THIU CHUNG


The document is established basing on the designed drawing and approved
method as well as the Contractors construction technology & experience. The
purpose of this document is to present criteria for the acceptance of the pile grouting
work completion.
Shaft grouted test pile is a pile which has the polymer particles on each side are
replaced a shaft layer, so that the friction force between the pile and soil is
increased. It means, the capacity of pile is increased too.
Ti liu ny c xy dng cn c vo bn v thit k, bin php thi cng c
ph duyt v cng ngh, kinh nghim s dng vn hnh h thng pht va ca Nh
thu. Ti liu nhm xc lp cc tiu chun cho vic thi cng v nghim thu cng tc
bm va gia c thn cc.
Cc th c pht va l cc c cng chu ti c tng cng bng cch
tng lc ma st thnh cc vi nn t. Lc ma st thnh cc tng ln nh cc c
pht mt lp va y cc ht polymer bm xung quanh cc trong qu trnh thi
cng. Do , sc chu ti ca cc cng tng ln.

Page 52

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

B. ACCEPTANCE CRITIERIA OF GROUTING WORK COMPLETION / CC TIU


CHUN XC NH HON THNH BM VA
1. Shaft grouting area / Din tch pht va:
For barrette pile / Cho cc barrette
Shaft grouting area is based on the following formula / Din tch bm va c
tnh da trn cng thc:
S = 2 * (a+b) * H * 1.0(1-1)
With / Trong :
a: The width of barrette section / Chiu rng mt ct ngang ca barrette (m)
b: The length of barrette section / Chiu di mt ct ngang ca barrette (m)
H: The height of grouting area and determined as following / Chiu cao vng pht
va c tnh nh sau:
H = - (T1-T 2)
with:
T1: is the bottom level of shaft grouting complying with shop drawing / Cao
trn cng ca vng bm va thit k, c xc nh theo bn v thi
cng.
T2: is the top level of shaft grouting area complying with shop drawing /
Cao trn cng ca vng bm va thit k, c xc nh theo bn v
thi cng.
For bored pile / Cho cc khoan nhi
Shaft grouting area is based on the following formula / Din tch bm va c
tnh da trn cng thc:
S = a * * H * 1.0

(1-1)

With / Trong :
a: The diameter of bored pile section / ng knh ca cc khoan nhi (m)
H: The height of grouting area and determined as following / Chiu cao vng pht
va c tnh nh sau:
H = - (T1-T2)
With / trong

Page 53

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

T1: is the bottom level of shaft grouting complying with shop drawing / Cao
trn cng ca vng bm va thit k, c xc nh theo bn v thi
cng.
T2: is the top level of shaft grouting area complying with shop drawing /
Cao trn cng ca vng bm va thit k, c xc nh theo bn v
thi cng.
2. Shaft grouting area / Din tch pht va:
Grouting volume is designed at 35l/m2 for all the grouting area S
Th tch bm va theo thit k l 35l/m2 tnh trn din tch bm va S.
3. Designed grouting volume per sleeve / Th tch bm qua l pht
The grouting work is carried out with 6 out of 8 pipe sleeves on the same level.
The injected volume to be achieved for each sleev as:
For barrette a x b section as followings
Vi = (a + b) x 2 x 1.0m x 35l/m2 / 6 = A litres per sleeves
Vic bm va c thc hin qua 6 l trn tng s 8 l trn cng mt cao trnh.
Th tch va c bm quy v cho tng l nh sau:
Vi cc barrette tit din a x b
Vi = (a + b) x 2 x 1.0m x 35l/m2 / 6 = A lt / l
For bored pile of a diameter as followings
Vi = a x x 1.0m x 35l/m2 / 4 = A litres per sleeves
Vic bm va c thc hin qua 4 l trn tng s 6 l trn cng mt cao trnh.
Th tch va c bm quy v cho tng l nh sau:
Vi cc khoan nhi c ng knh a
Vi = a x x 1.0m x 35l/m2 / 4 = A lt / l
4. Stop & approved criteria of grouting work completion / Tiu chun xc nh vic
hon thnh bm va cho mt cc barrette
a) In case of grouting pressure is less than 40bar / Khi p sut trong qu trnh
bm nh hn p sut thit k
- Vi A litres per sleeves with barrette a x b section / Vi A lt/ l cho barrette c
tit din a x b

Page 54

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

- Vi A litres per sleeves with bored pile of a diameter / Vi A lt/ l cho coc
khoan nhi c ng knh a
Grouting work stops when the target volume is reached. / Qu trnh bm s dng
li khi t th tch thit k.
b) In case of reaching maximum pressure but the volume is not sufficient or nogrout can be pumped out / Khi p sut ln hn p sut thit k nhng vn cha t
th tch thit k
Grouting work will be carried out in accordance with Item D RULES OF
COMPENSATION GROUTING. / Tin hnh bm b theo mc D - QUY TC BM
B.
35

25 (l/m2)

(1-3)

Whereas / Trong :
Vi - Grouted volume into a particular sleeve / Th tch bm l th i

- Total grouted volume into the barrette / Tng th tch va bm thc t

S- Shaft grouted area specified following (1-1) / Din tch vng pht va c
xc nh theo cng thc (1-1)
C. RULES OF GROUTING WORK / QUY TC BM VA
1

3
4

8
7

Figure 1a. Location of grouting pipes / Hnh 1a. V tr cc ng pht va.


Hereafter is the rules and sequence of grouting
1. The shaft grouting is to be carried out from the bottom sleeve to the top sleeve.
2. Main grouting pipes are 1, 3, 4, 5, 7 and 8. Reserved compensation pipes are 2 and
6.
Sequence of grouting

Page 55

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

- In case of grouting with 2 packer: Process commences at pipe no. 4 and no. 8 with
100% of target volume. Finishing pipe 1 and 5, grouting moves to pipe no. 3 and no. 7
- In case of grouting with 3 packer: Process commences at pipe no. 1, 4 and no. 8 with
100% of target volume then moves to pipe no. 3, 5 and no. 7
During grouting, if the pressure is more than 40bar the applying the rule in part D as
stated below COMPENSATION GROUT is applied. Reserved pipes 2 and 6 can be
used.
Cc quy tc bm va nh sau:
1. Trnh t bm t l di cng ln trn.
2. Cc ng c u tin bm l 1, 3, 4, 5, 7 v 8. Cc ng d phng l 2 v 6.
Trnh t bm cc ng:
- Khi s dng 2 packer: Bt u vi ng s 4 v 8 vi 100% th tch qui nh cho mi l.
Sau chuyn qua ng 1 v 5 ri 3 v 7.
- Khi s dng 3 packer: Bt u vi ng s 1, 4 v 8 vi 100% th tch qui nh cho mi
l. Sau chuyn qua ng 3, 5 v 7.
Trong qu trnh bm va, nu gp hin tng p sut bm ln hn 40 bar th thc hin
theo D -QUY TC BM B. C th bm cc ng 2 v 6.

D. RULES OF COMPENSATION GROUTING / QUY TC BM B


1. Condition of compensation grouting / iu kin bm b
Compensation can be carried out if any sleeve is found with pressure reached
40bar but no sufficient grouted volume that has mentioned in Item 4, Part B.
Vic bm b c th c tin hnh khi bt k l no t p sut thit k 40bar
m th tch cha t c quy nh phn 4 mc B.
2. Rules of compensation grouting / Quy tc bm b
The target grout volume per manchette will be 35litres/m2 of the surface area of
the test pile. Should the a target grout volume not be achieved in a particular
manchette mentioned in Item 4.a, then the manchette below, above or to the side
shall be injected with additional grout, if necessary, so as to ensure that the
minimum average grout take over the shaft grout zone is greater than 25litres/m2.

Page 56

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

The priority order is as following:


Try to come back to the below sleeve of the same pipe, if can not
Go up to the above sleeve of the same pipe (exclude the top sleeve).
At last, compensate to the side sleeve of next pipe at same level sleeves.
Compensate by pumping into reserved pipes 2 and 6 for barrette pile &
reserved pipes 2 and 6 for bored pile
Th tch bm va thit k l 35lt/m2 tnh trn din tch b mt ca cc. Khi 1 l
pht khng t iu kin ti iu 4.b (c th l th tch bm qua 1 l pht), nu cn
thit th vic bm b s c thc hin ti cc l pht bn di, bn trn hoc ln
cn vi lng va cn bm thm m bo rng lng va trung bnh ti thiu ti
khu vc c th t t nht l 25lt/m2.
Th t u tin nh sau:
C gng quay li bm b l pht ngay bn di trong cng mt ng.
Bm b ngay l pht bn trn trong cng mt ng (ngoi tr l pht trn
cng)
Bm b cc l cng cao cc ng ln cn
Bm cc ng s 2 v 6 cho cc barrette v cc ng 5 v 6 cho cc khoan
nhi.

Note / Lu
Compensated
lacking
volume.
lng va thiu.

grout volume is equal the


Lng va bm b bng

Compensated
Cc l bm b cho
ln cn lin k nhau.

sleeve must be adjacent /


nhau phi l cc l nm

Page 57

DAI QUANG MINH ZONE II PROJECT - POLT 5.5


Test pile works- Method Statement
Bin php thi cng cc th

Page 58