4th Fl, A1 Bldg, 55 Giai Phong St., Hai Ba Trung Dist., Hanoi City
Reference/Tham chiu: Ex2/C/................
Hung Yen 16 th Jan 2012
thng 01 nm 2012 To:
Hng Yn, Ngy 16
Namkwang Engineering Construction Co.,Ltd
Tu Ho, Yen My, Hung Yen
Attention: Mr. Hwang Sun Ki, Project Manager
Cc
Subject: V/v:
Mr. Nguyn c Cng. PMB Director / Gim c PMB
Construction Method Statement of B35 Brigde . Bin php t chc thi cng cu B35
Dear Mr. Hwang,
Tha Qu ng Sau khi xem xt th s NK.EX2.PCT.1312 ngy 10 thng 01 nm 2012 ca Nh thu v bin php t chc thi cng cu B35. TVGS c kin nh sau : 1 Construction Method Statement of B35 Bridge / V bin php thi cng: + For abutments A1, A2 and piers P1, P2, P5, P6 / M A1, A2 tr P1, P2, P5 v P6 : - B sung thit b thi cng o t h mng, phng php v thit b b tng cho b, thn v x m tr, m. - B sung cu to chi tit v b tr vn khun thp cho b, thn v x m. i vi cc tr s dng ct nh hnh, ngh Nh thu ch r quy cch, trng lng . . . - V chi tit do vn khun y x m tr - Phng php lp dng do , vn khun v ct thp + For piers P3, P4 / Tr P3, P4 : - Nu r tn loi cc vn thp s dng trong vng vy. S lng cc vn thp l 208 thanh (Trong c 8 cc gc). Bng tnh ton khung vy cc vn thp - B sung thit b o t h mng, thit b v phng php b tng b, thn v x m tr. 2 B sung khi lng vt t lun chuyn huy ng n cng trng nh do , vn khun . . .Summery table of equipments with the profile and certificate of the equipment and operator / Tng hp my mc thi cng, nh km h s chng ch v ngi vn hnh. 3 Organization of construction team / S t chc i thi cng 4 Safety control plan during the construction process / K hoch kim sot an ton trong thi cng 5 Clarification of payment amount and payment item, clarification of provision on payment measurement method in Specification / Nu r khi
lng thanh ton, cc khon mc thanh ton, nu r iu khon quy nh
phng php o c thanh ton trong ch dn k thut Yours sincerely, Trn trng,
Resident Engineer, EX-2/ K s thng tr gi thu EX-2
Apply -
to: (1) (2) (3) (4) (5)
Mr. Nguyn c Hip
Mr. T Minh Tin Mr. Nguyn Vn Ngc MI-VJEC Head Office Package EX-2s office