Minutes of Meeting 5
(As at 24 Nov 2008)
Road Openings
Benoi - 16/10/2008 Noted. - - - - -
Tuas Ave 4 - 16/10/2008 Noted. - - - - -
Tuas View
Loyang
ECM Proposals
Benoi - 20/10/2008 Noted. -
Tuas Ave 4 - 16/10/2008 Noted. - - 14/11/2008 Noted 1) Approved by PUB
Tuas View
Loyang
Site Office - 3/11/2008 Noted. 20/11/2008 Noted 1) Approved by PUB
Precondition Reports
Pioneer Sector - 24/09/2008 Not Approved. 1) To include conditions of surrounding REV-01 3/11/2008 Noted.
To Re-Submit. buildings.
Tuas South Ave 4 - 24/09/2008 Not Approved. 1) To include conditions of surrounding REV-01 3/11/2008 Noted.
To Re-Submit. buildings.
Tuas South Ave 5 - 24/09/2008 Not Approved. 1) To include conditions of surrounding REV-01 3/11/2008 Noted.
To Re-Submit. buildings.
Pioneer Road - 24/09/2008 Not Approved. 1) To include conditions of surrounding REV-01 3/11/2008 Noted.
To Re-Submit. buildings.
Survey Drawings
Benoi
Tuas Ave 4
Control Points - 24/10/2008 Noted. - - - -
Setting-Out - 24/10/2008 Not Approved. 1) To re-submit upon receiving approval
To Re-Submit. to jack sewer underneath canal.
Tuas View
Pioneer Sector
Loyang
Trial Trench Reports / Services Drawings
Benoi - 20/10/2008 Noted. 1) To re-located Benoi manhole.
Tuas Ave 4 - 20/10/2008 Noted. -
Tuas View
Loyang
Method Statements
Benoi
Pipe-Jacking
Shaft Excavation
- MH-B1,MH-B1a and MH-B-2 14/11/2008 Not Approved. 1) Risk assessment matrix wrongly titled.
To Re-Submit.
Tuas Ave 4
Pg A1 of A2
D:\EDI\D528A Diversion Of Flows And Demolition Of 7 Pumping Installations\Meeting Minutes\Contractor's Submission to EDI.xls
DIVERSION OF FLOW & DEMOLITION OF TUAS VIEW PUMP SUMP AND OTHER PUMPING INSTALLATIONS ANNEX A for
Minutes of Meeting 5
(As at 24 Nov 2008)
- MH-T1,MHT2 and MHT2A 18/11/2008 Not Approved. 1) Risk assessment matrix wrongly titled.
To Re-Submit.
Tuas View
Pipe-Jacking
Shaft Excavation
Loyang
Pipe-Jacking
Shaft Excavation
Fortnightly Progress Report
Report #1 ( For 03/09/2008 ~ 10/10/2008) - 16/10/2008 Noted. -
Report #2 ( For 11/10/2008 ~ 23/10/2008) - 24/10/2008 Noted. -
Report #3 ( For 24/10/2008 ~ 07/11/2008) - 7/11/2008 Not Approved. 1) As discussed during meeting, to be
To Re-Submit. submitted in proper format.
Pg A2 of A2
D:\EDI\D528A Diversion Of Flows And Demolition Of 7 Pumping Installations\Meeting Minutes\Contractor's Submission to EDI.xls