DQ Sheet No DQ-NS2-DD09-P0ZEN-169027-B-WSP1B-WSP1
Document Title Method Statement for General Concreting Work
Document No NS2-DD09-P0ZEN-169027 Rev B
Status Description Approved Status Code 1
These comments and/or approval by the Owner / Owners Engineer’s in no way relieves the Contractor from his obligations to ensure conformance with the requirements of
the Contract. Any Contract deviations found subsequent to approval are to be corrected by the Contractor to the satisfaction of the Owner / Owners Engineer’s.
Sl No Cl. No & page no Item description Comment details
2 Sec 3 Calibration Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
Please add”All equipments shall be calibrated by authorised agency as applicable”
3 Sec 3 Equipment Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
In addition to the list, pl add ‘boom placers’ and “concrete levelling machine”
550208686.docx Page 1 of 5
Sl No Cl. No & page no Item description Comment details
4 Sec 6.1.1 Third party test Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
Third party tests shall be done at regular intervals, in addition to manufacturers certificate.
5 6.1.4 Test certificates Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
Water test certificate shall also be submitted to client in addition to other tests certificates.
6 6.1.7 Batching slip Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
All the concrete carrying transit mixers shall leave the batching plant along with batching slip, which shall be handed
over to the site engineer at the work place before concrete is poured.
550208686.docx Page 2 of 5
Sl No Cl. No & page no Item description Comment details
7 6.3.9 Shuttering Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
Application of shuttering oil is missing. Please include
8 6.3.10.1 Inspection Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
It is mentioned that “the contractor ------------, reinforcement and embedded parts”--------, but at this stage only form
work has been done and hence delete from this sentence and add later suitably. Also pl give RFI only for inspection of
shuttering scaffolding only.
9 6.6.1 General Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
Please also include embedment’s, bolts and pipes also.
550208686.docx Page 3 of 5
Sl No Cl. No & page no Item description Comment details
Noted.
10 6.11.4 Deshuttering Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
Please specify DE shuttering time in terms of days in line with local codes for beams, slabs etc
11 6.12 Construction joint Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
Please refer the drawing for construction joint location. In addition, pl also mention that in case of difficulty, the site
engineer shall take permission of project manager to provide construction joint at the place other than mentioned in
the drawing. Please refer the standard drawings for details of construction joint.
12 6.9.4 Rectification Owner /OE’s Comment dated 29-07-2018 Commented by: OE’s(WSP)
method
Please add “After completing concreting work, the contractor shall take a round of the area both on top and bottom to
check whether any local problems/disturbances/bulging/plumb out, etc has taken place and initiate immediate
rectification methods”.
Owner /OE’s Comment dated 07-09-2018 Commented by: OE’s(WSP)
Noted. But not revised in the document. Please mention in the document
550208686.docx Page 4 of 5
550208686.docx Page 5 of 5