DQ Sheet No DQ-NS2-DD09-P0ZEN-740006-5-WSP1
Document Title Method Statement for GRP Piping Installation
Document No NS2-DD09-P0ZEN-740006 Rev 5
Status Description Approved Status Code 1
These comments and/or approval by the Owner / Owners Engineer’s in no way relieves the Contractor from his obligations to ensure conformance with the requirements of
the Contract. Any Contract deviations found subsequent to approval are to be corrected by the Contractor to the satisfaction of the Owner / Owners Engineer’s.
Cl. No
Sl & Item
Comment details
No page description
no
1 Owner /OE’s Comment dated 17-06-2019 Commented by: Owner/OE’s
1) The GRP pipe was not submitted as material for approval.
2) There is no information for what systems the proposed pipes will be used.
3) MS shall also contain the installation details in underground.
4) Please provide Lilama subsidiary organization chart who do GRP installation work.
5) Please provide erection work flow chart.
6) Please submit erection manual from vendor for information.
529289035.docx Page 1 of 7
Cl. No
Sl & Item
Comment details
No page description
no
2) Revised as per comment. Please refer to MS at page 3. The major GRP Piping work is quenching system. And partially will use for
chlorination system, water box vacuum…etc.
3) The MS was applied for all GRP included above ground piping and underground piping at NS2PC Project. Please refer to MS at page 3 of
Scope work. And revised as per comment. Please refer to MS at page 7, 8, 20 and 21.
529289035.docx Page 2 of 7
Cl. No
Sl & Item
Comment details
No page description
no
4) Revised as per comment. Please refer to MS at page 4.
5) Revised as per comment. Please refer to MS at page 6.
6) Revised as per comment. Please refer to vendor erection manual as attachment in MS.
529289035.docx Page 3 of 7
Cl. No
Sl & Item
Comment details
No page description
no
1.4 Owner /OE’s Comment dated 23-07-2019 Commented by: Owner/OE’s
2) Noted and closed
3) What about the section next to discharge canal, where the GRP CW pipe is alone? What about the 3 elbows, to compensate for the
reaction forces when the pump starts?
529289035.docx Page 4 of 7
Cl. No
Sl & Item
Comment details
No page description
no
- DVN has changed the hydro test holding time from the pressure and leak test of piping method statement NS2-DD09-P0ZEN-740014
and mentioned that the test pressure holding time 10 minutes instead of 2 hours. DVN is required to mention in which standard
describe the test pressure holding time 10 minutes for GRP piping. And also, please revise the pressure and leak test of piping
method statement NS2-DD09-P0ZEN-740014 accordingly.
- During pressure test all the field joints shall be left fully exposed for inspection. Half exposed for inspection is not acceptable.
Please revise in the MS.
529289035.docx Page 5 of 7
Cl. No
Sl & Item
Comment details
No page description
no
DVN’s proposal of Golden Joints instead of hydro test for test package-3 is not acceptable. The purpose of hydro test is not only for pipe
joints and also ensure the pipe materials quality without any defects and leakages. DVN is required to do the hydro test for pipeline test
package-3
Contractors response dated 01-08-2020
Noted. As discussed on date 22-July-2020. DVN shall testing pressure 2.5 bar for all sections in one time.
Owner /OE’s Comment 3-09-2020
Noted and Closed.
2. Contractors response dated 01-09-2020
0
DVN added branch (Tee) Lamination in the MS.
529289035.docx Page 6 of 7
Cl. No
Sl & Item
Comment details
No page description
no
529289035.docx Page 7 of 7