Nghi Son 2 BOT Thermal Power Plant Project

Design Query Sheet

DQ Sheet No DQ-NS2-DD09-P0ZEN-740006-5-WSP1
Document Title Method Statement for GRP Piping Installation
Document No NS2-DD09-P0ZEN-740006 Rev 5
Status Description Approved Status Code 1
These comments and/or approval by the Owner / Owners Engineer’s in no way relieves the Contractor from his obligations to ensure conformance with the requirements of
the Contract. Any Contract deviations found subsequent to approval are to be corrected by the Contractor to the satisfaction of the Owner / Owners Engineer’s.
Cl. No
Sl & Item
Comment details
No page description
no
1 Owner /OE’s Comment dated 17-06-2019 Commented by: Owner/OE’s
1) The GRP pipe was not submitted as material for approval.
2) There is no information for what systems the proposed pipes will be used.
3) MS shall also contain the installation details in underground.
4) Please provide Lilama subsidiary organization chart who do GRP installation work.
5) Please provide erection work flow chart.
6) Please submit erection manual from vendor for information.

1.1 Contractors response dated 30-06-2019


1) Please refer to our contract schedule as below.
According to EPC contract, the GRP no need to get approval by Owner. There is not mentioned GRP material in schedule 16 “Major and
Approved Subcontractors”. When GRP material inspection on site. DVN shall be attached quality document.

529289035.docx Page 1 of 7
Cl. No
Sl & Item
Comment details
No page description
no

2) Revised as per comment. Please refer to MS at page 3. The major GRP Piping work is quenching system. And partially will use for
chlorination system, water box vacuum…etc.
3) The MS was applied for all GRP included above ground piping and underground piping at NS2PC Project. Please refer to MS at page 3 of
Scope work. And revised as per comment. Please refer to MS at page 7, 8, 20 and 21.

529289035.docx Page 2 of 7
Cl. No
Sl & Item
Comment details
No page description
no
4) Revised as per comment. Please refer to MS at page 4.
5) Revised as per comment. Please refer to MS at page 6.
6) Revised as per comment. Please refer to vendor erection manual as attachment in MS.

1.2 Owner /OE’s Comment dated 23-07-2019 Commented by: Owner/OE’s


1) Noted
2) BOP piping, STG piping are too vague. Please clarify which lines of BOP and STG piping
3) Figure 11 at page 21 is showing bedding under the backfilled pipe. But there are no details about this trench at page 7 where the trench
work is described. More details should be given about the supporting and installation of the quenching line, which is 1700
4) Noted
5) Noted
6) Noted

1.3 Contractors response dated 16-08-2019


2) Revised as per comment. Please refer to MS at page 3.
3) Please refer to as below. Also,
Please refer to drawing No. NS2-
XB02-P0UPZ-164407 at page 2 of 7.

529289035.docx Page 3 of 7
Cl. No
Sl & Item
Comment details
No page description
no
1.4 Owner /OE’s Comment dated 23-07-2019 Commented by: Owner/OE’s
2) Noted and closed
3) What about the section next to discharge canal, where the GRP CW pipe is alone? What about the 3 elbows, to compensate for the
reaction forces when the pump starts?

1.5 Contractors response dated 27-08-2019


Please refer to drawing quenching water pipe line civil works plan and sectional drawing as below. Also, Please refer to drawing No. NS2-
XB02-P0PAB-164510.
The GRP Pipe will bedding by sand with sand compaction 90 ~95% of standard proctor.

1.6 Owner /OE’s Comment dated 28-08-2019 Commented by: Owner/OE’s


Noted and closed

1.7 Contractors response dated 21-02-2020


DVN is updated hydrostatic test for GRP at from page 17 to page 22.
Owner /OE’s Comment dated 24-02-2019

529289035.docx Page 4 of 7
Cl. No
Sl & Item
Comment details
No page description
no
- DVN has changed the hydro test holding time from the pressure and leak test of piping method statement NS2-DD09-P0ZEN-740014
and mentioned that the test pressure holding time 10 minutes instead of 2 hours. DVN is required to mention in which standard
describe the test pressure holding time 10 minutes for GRP piping. And also, please revise the pressure and leak test of piping
method statement NS2-DD09-P0ZEN-740014 accordingly.
- During pressure test all the field joints shall be left fully exposed for inspection. Half exposed for inspection is not acceptable.
Please revise in the MS.

1.8 Contractors response dated 09-03-2020


- Please refer to ASME NM.2-2018 at item 6-3.2.2 of page 86. DVN will be revised the pressure and leak test of piping method
statement no NS2-DD09-P0ZEN-740014.
- Revised as per comment. Please refer to MS at page 18.
Owner /OE’s Comment dated 23-03-2020
The Owner/OE does not agree the GRP piping test pressure holding time 10 minutes and concluded that 10 minutes holding time is
inadequate for leakage inspection. We would suggest a longer holding time of 30 minutes during pressure test.
Based on Hydro Test pressure holding time of 30 minutes and 2 hours which was done for the first test package DVN should give the
Guarantee for the GRP piping quality up to 35 years of the plant operation life period.
Contractors response dated 27-03-2020
As discussed on weekly meeting. It is 2 hours holding time for GRP test in ISO 14692-4.4 Petroleum and natural gas industries which is
applied in natural gas not water in power plant. It is specified 1.5 times of design pressure with at least 10 minutes holding time for GRP
hydraulic test according to ASME B31.1 Power Piping, which is generally applied in power plant system. However, DVN would propose
“30 minutes holding time under 1.5 times of design pressure” to ensure GRP safe operation.
Owner /OE’s Comment dated 30-03-2020
Noted and Closed.
1.9 Contractors response dated 08-06-2020
Revised hydro test package. Please refer to MS at page 23.
Owner /OE’s Comment dated 8-06-2020

529289035.docx Page 5 of 7
Cl. No
Sl & Item
Comment details
No page description
no
DVN’s proposal of Golden Joints instead of hydro test for test package-3 is not acceptable. The purpose of hydro test is not only for pipe
joints and also ensure the pipe materials quality without any defects and leakages. DVN is required to do the hydro test for pipeline test
package-3
Contractors response dated 01-08-2020
Noted. As discussed on date 22-July-2020. DVN shall testing pressure 2.5 bar for all sections in one time.
Owner /OE’s Comment 3-09-2020
Noted and Closed.
2. Contractors response dated 01-09-2020
0
DVN added branch (Tee) Lamination in the MS.

2.1 Owner /OE’s Comment 3-09-2020


Please mention the acceptance tolerance for T-Joints fit-up and lamination.
Please add the method statement on how to cut out the straight piping to have T branch if T fitting (factory fabricated) is not used.

2.2 Contractors response dated 09-09-2020


1. Please refer as below and MS at page 15 & 16.
2. Revise as per comment. Please refer to MS at page
16.

529289035.docx Page 6 of 7
Cl. No
Sl & Item
Comment details
No page description
no

Owner /OE’s Comment 18-09-2020


Noted.

529289035.docx Page 7 of 7