Date:

Date: January
January 18, 2023
, 2023
Ref. No: 266/EVNPMB2-KTAT+KTKH
Ref. No: ........../EVNPMB2-KTAT+KTKH

To: Consortium of Mitsubishi Corporation, Hyundai Engineering & Construction


Co., Ltd., Construction Corporation No.1 Joint Stock Company
Attn: Mr. Lee, Yun-Seok - Project Manager of MC-HDEC-CC1 Consortium
CC: Mr. Hidenao Igarashi - Deputy General Manager of MC
CC: Mr. Ha Dinh Nien - Deputy General Director of CC1
CC: Power Engineering Consulting JSC 1 (PECC1)

Project: QUANG TRACH I THERMAL POWER PLANT PROJECT


Contract No.38/2021/QT1-EVNPMB2-MC-HDEC-CC1
Reference: QT1-CC1-PMB2-T-0356 dated December 29., 2022.
146/TVĐ1-NĐNLM dated January 09, 2023.
Subject: Material list for Accommodation - MEP works (APD, Rev. 0)
Dear Sirs,
In response to your reference Letter, the Owner’s Representative would like to give our
comments as per attachments.
No. Number drawing/ Name drawing/ Document/ Letter REV Status Remark
Document/ Letter
QT1-0-Z-030-08- The Material list for Cars
1 0 APP
00004 Accommodation - MEP works 0382 R8
Yours sincerely,

Nguyen Van Thanh


Director
C.c.: As indicated above; BĐHDAQT; PECC1; Archives, P2, P3.

Note: Such approval by the Owner, however, shall not in any way relieve the Contractor from any
of its obligations to complete the Works or from any other obligations and liabilities of the
Contractor under the Contract.