You are on page 1of 4

DESIGN OF FLASH MIXER AT KURAWAR - 1A

3
Density of water = 9.81 kN/m
3
Density of concrete = 25 kN/m
Density of soil = 18 kN/m3
3
S.B.C of Soil= 100 kN/m

TOP LVL = 473.25 m


WSL = 472.750 m
N.G.L = 469.50 m
BED LVL = 469.000 m

L= 1.2 m
B= 1.2 m
H= 4.25 m
L/H = 0.282
MOMENT COEFFICIENT FOR WALL PANEL TOP FREE, BOTTOM & VERTICAL EDGE FIXED :
( Ref IS:3370 -Part IV)
3
Max Moment MH = -0.014 x 9.81 x 4.25 = -10.54 KNm
3
Max Moment MV = 0.007 x 9.81 x 4.25 = 5.27 KNm

a) CANTILEVERED WALKWAY DESIGN Span = 1.000 m


Let thickness = 150 mm
Self wt. = 3.750 KN/m2
LL = 5.0 KN/m2
Finishes = 1.0 KN/m2
Total Load = 9.750 KN/m2
M= 5.88 KNm
Duncracked = 67.23 mm
Provide ,Doverall = 150 mm deff = 120 mm
2
Ast = 235.47 mm
2
Dia. Of Bar used = 10 mm Astbar = 78.525 mm
Spacing required = 333.48598 mm
Spacing Provided = 200 mm
Provide 10 mm dia @ 200 c/c as main bars & 8 mm dia @150 c/c as d/s bars.
Design Moment = 11.15 KNm
DESIGN OF THICKNESS OF TANK WALLS
For no crack section
Overall Depth of section required
D2 = M*6*106/2.0*103
D= 182.9 mm
Provide D= 230 mm
d = 181 mm

AstV = 11.15 x 10 6 = 550.8 mm2


130 x 0.86 x 181
Provide 10mm dia @125 c/c vertically on inner face.

AstH = 10.54 x 10 6 = 521.01 mm2


130 x 0.86 x 181
Provide R/F 10 mm dia @ 150 c/c horizontally on both faces

Pr. At base lvl. due to earth= 9.81 x 0.50 + (18-9.81) x 0.500 x.333 = 6.27 KN/m2
2
Max BM = 0.0070 x 6.27 x 0.500 = 0.01 KNm
Ast min = 0.24 x 230 x1000/100 = 552 mm2 (on both faces)
Provide R/F 8mm dia @ 175 c/c vertically on outer face.

BASE SLAB
Let thickness of base slab = 200 mm
Projection all around = 200 mm
2
Area of Base slab = 4.24 m
length of salb = 1.2 m
LOAD CALCULATONS
2
Due to Base slab = 0.200 x 25 = 5.00 kN/m
2
Due to wt. of soil over base slab = 0.5 x 18 = 9.0 kN/m
2
due to weight of water inside = 4.25 x 10 = 42.5 kN/m
2
Total load = 56.50 kN/m

considering as interior pannel : Ly/Lx = 1

Negetive moment at continuous edge = 2.6035 kNm


Duncrack = 88.377 mm
Dprovided = 200 mm deff. = 150 mm
2
Astrequired = 164.83 mm
Provide 8 mm dia. @150 c/c squiremesh.

DESIGN OF BASE BEAM :


Size Of Beam = 300 x 300 mm
c/c Length of beam = 1.5 m
Height of wall Above Beam= 4.25 m
Loads due to wall= 0.23 x 4.25 x 25 = 24.438 kN/m
Self weight of Beam= 0.3 x 0.3 x 25 = 2.25 kN/m
Load from Slab = 22.6 kN/m
Total Loads = = 49.288 kN/m

Muat support= 9.241 kNm


Muat midspan= 4.62 kNm
drequired = 304.0 mm
Doveral = 300 mm deff, provided = 250 mm
2
Astreq. = 351.05 mm
2
Provide 12 mm dia bar. Astb = 113.08 mm
Provided 4 nos of 12 mm dia bar equially distributed
Provided 8 mm dia bar @150 mm c/c as stirrup
Load on Column- C1
Load transferred by beam = 49.29 x 1.500 = 73.93 kN
Self Wt. of Column = 0.3 x 0.3 x 3.25 x 25 = 7.3125 kN
Total Load = 81.24 kN
Total Wt. at the base of each col. = 80.00 kN
Checking of Slenderness ration of column
use longitudinal Bar= 12 mm
L= 3.25 m least lateral dimension= 192 mm
l= 2.6 m or, 300 mm
Slenderness Ratio= 8.67 < 12 we take 300 mm
(hence it is Short Column)

Assume Column SIZE = 300 x 300


Provide col. Size of dia. 300 mm with 8 - 12 mm dia bars
Ties : 8mm dia @ 100 c/c upto h/6 dist. from each support +rest @ 150 c/c
Load carrying capacity of sugg. size= (From IS 456 : 2000 cl B-3.1)
= 830362 N σ cc = 8 N/mm2 (M30)
= 830.36 kN > 80.0 kN σ sc = 130 N/mm2 (Fe500)
SAFE

DESIGN OF FOUNDATION F-2


vertical load on col. C-1 = 80.00 kN
vertical load on col. C-2 = 80.00 kN
Self weight of footing (10%) = 16.00 kN
Total load on footing = 176.00 kN
2
S.B.C of Soil at 1.5 m depth = 100.00 kN/m

Size Of footing
2
Area of footing = 1.760 m
Adopt a footing size 2000 x 1000 mm
c/c dist. Between columns,l = 1.50 m

a1 = 0.25 m
a2 = 0.3 m
Clear proj. of slab from col. Face,a =.5 x (B-b) = 0.35 m

2.0

1.50

1.00
0.30 0.30

80 KN 80
1.50

88.00 kN/m
Net upward soil reaction, po = 176.00 = 88.00 kN/m
1.0 x 2

DESIGN OF FOOTING SLAB


Let footing beam width = 400 mm
Proj. of footing slab beyond beam face = 1 x ( 1 - 0.4 ) = 0.3 m
2
2
BM = 88.00 x 0.3 = 3.960 kNm
2
d.eff = 109.0 mm
PROVIDE doverall = 200 mm d.eff = 142 mm
Ast = M /σst x j x d
2
= 264.83688 mm
Astmin. = 0.12% of Ggross-section = 240 mm2
PROVIDE 10 mm dia @ 200 mm c/c as main bars and 3 nos 8 mm dia on each side of beam as distribution
steel.
Check for 1-way shear
Shear force F =po (a-.142) = 18.30 kN 18.304

τv =V/bd = 18304 = 0.129 N/mm2


1000 x142
p= Ast x 100 = 0.276 %
bd
2
For M-30 ,Permissible shear stress,τc = 1x 0.238 = 0.238 N/mm
As τv < τc HENCE SAFE

DESIGN OF FOOTING BEAM :FB-1


Sizwe of Beam = 300 x 300 mm
Upward load intensity on beam = 176.00 = 88.00 kN/m
2.00
2
Maximum BM = 88.00 x 0.3 = 3.96 kNm
2
d.effective from BM consideration = √ M /Q x b = 85.63 mm
PROVIDE doverall = 300 mm d.eff = 247 mm
2
Ast = 152.25 m
PROVIDE (2-16t+1-12t) mm dia at top & at bottom of beam.
PROVIDE stirrups 8 mm dia. 2 L @ 100 c/c throughout

You might also like