Page 1

NAME OF WORK :
Withdrawing of 15HP and lowering of 7.5HP departmental Submersible pump motor set at site
near PWD elctrical section offic, MPU, Barrackpore during the year 2018-19

Ref: N.I.T. no. 07/ KWSD-III of 2018-19.


Assistant Engineer, P.W.D. Kolkata West Sub-Division-III, Govt. of West Bengal

Sl. No. - 1 page No. item no :


Withdrawing the damage Monoblock submersible pump motor set and installation the loan submersible
pump motor set with special type of tools and tackles.

Total = 1 No
Rs. 3332.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 3332.00/ No Rs. 3332.00

Sl. No. - 2 page No. item no :


Hire charges for installation of loan submersible pump motor set (7.5 HP , 3 phase) with special type of
tools and tackles and fixing temporary pipe line and cable with its accessories and making temporary
electrical connection to throw out the logged water inside the reservoir and making the place suitable for
work and withdrawing the same.

Total = 1 No
Rs. 6381.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 6381.00/ No Rs. 6381.00

Sl. No. - 3 page No. item no :


Jointing the talling cable with proper vulcanizing, dressing and testing.

Total = 12 Point
Rs. 83.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) Point
Rate = @ Rs. 83.00/ Point Rs. 996.00

Sl. No. - 4 page No. item no :


Rewinding the motor stator coil with polly double coated proper winding wire with proper dressing
unsulation cable vulcanizing & testing. 7.5 HP

Total = 1 Set
Rs. 12654.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) Set
Rate = @ Rs. 12654.00/ Set Rs. 12654.00

Sl. No. - 5 page No. item no :


Supplying fitting and fixing upper & lower bush & grinding the journal bush. . 7.5 HP
Total = 4 No.s
Rs. 450.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 450.00/ No.s Rs. 1800.00

Sl. No. - 6 page No. item no :


Repairing the thrust bearing S/F GM Block & grinding machining & matching withs the thrust plate with S/F
linner clutch plate with circuit lock.(complete unit). . 7.5 HP

Total = 1 Set
Rs. 1524.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) Set
Rate = @ Rs. 1524.00/ Set Rs. 1524.00

Sl. No. - 7 page No. item no :


Overhauling the pump portion with chemical solution inside and outside each cover and the impeller for
iron segment.
Total = 1 Set
Rs. 648.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) Set
Rate = @ Rs. 648.00/ Set Rs. 648.00

Sl. No. - 8 page No. item no :


S/F Water seal…. 7.5 HP
Total = 2 No.s
Page 2
Rs. 100.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 100.00/ No.s Rs. 200.00

Sl. No. - 9 page No. item no :


S/F necking fixing on the cover and matching and matching with the impeller. 7.5 HP
Total = 2 No.s
Rs. 1157.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 1157.00/ No.s Rs. 2314.00

Sl. No. - 10 page No. item no :


S/F Impeller. . . . . . . . 7.5 HP
Total = 2 No.s
Rs. 2400.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 2400.00/ No.s Rs. 4800.00

Sl. No. - 11 page No. item no :


Painting the Pump motor set
Total = 1 set
Rs. 450.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) set
Rate = @ Rs. 450.00/ set Rs. 450.00

Sl. No. - 12 page No. item no :


S/F Gasket
Total = 6 No.s
Rs. 83.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 83.00/ No.s Rs. 498.00

Sl. No. - 13 page No. item no :


S/F Nut bolt & washers
Total = 12 No.s
Rs. 27.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 27.00/ No.s Rs. 324.00

Sl. No. - 14 page No. item no :


S/F single phase preventor G.I.C make model no.
MAC04D0100/MAC15B with 6 Nos. lid wire approx 4 mtr.

Total = 1 set
Rs. 1948.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) set
Rate = @ Rs. 1948.00/ set Rs. 1948.00

Sl. No. - 15 page No. item no :


Checking and testing the insulation of the submersible pump motor set and the starter with 1000 V Megar
and use of clamp meter for mesuring the load current and also mesuring the Voltage at on load and off load
with 2 nos. men power.

Total = 1 set
Rs. 1467.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) set
Rate = @ Rs. 1467.00/ set Rs. 1467.00

Sl. No. - 16 page No. item no :


After repairing the submersible pump motor set withdrawing the loan submersible pump motor set and
installation the repaired submersible monoblock pump motor set with special type of tools and tackles.

Total = 1 set
Rs. 3332.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) set
Rate = @ Rs. 3332.00/ set Rs. 3332.00

Sl. No. - 17 page No. item no :


Laying out the cable within the cable protection pipe from Pump Motor set to the stator
Total = 40.00 m
Rs. 68.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 68.00/ m Rs. 2720.00
Page 3
Sl. No. - 18 page No. item no :
S/F Aotumation Wire 1.5 sqmm. From the stator to the inside of the reservior above the motor flange with
specalized GM Nut Bolt and 220V Magnen coil Cat No. SS90044.

Total = 1 set
Rs. 1693.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) set
Rate = @ Rs. 1693.00/ set Rs. 1693.00

Sl. No. - 19 page No. item no :


S & F 3 core flat submersible cable of 4.0 sq. mm. Finolex make IS 694 1100V

Total = 40.00 m
Rs. 175.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 175.00/ m Rs. 7000.00

Sl. No. - 20 page No. item no :


Opening out the existing 3 inch / 2 inch / 1 inch dia pipe line partly above and below floor by part and
joining the new line.

Total = 1 set
Rs. 733.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) set
Rate = @ Rs. 733.00/ set Rs. 733.00

Sl. No. - 21 page No. item no :


S/F 2.5 inch dia flange heavy type ISI marked.
Total = 2 No.s
Rs. 439.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 439.00/ No.s Rs. 878.00

Sl. No. - 22 page No. item no :


S/F 2.0 inch dia flange heavy type ISI marked.
Total = 2 No.s
Rs. 368.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 368.00/ No.s Rs. 736.00

Sl. No. - 23 page No. item no :


S/F 2.5 inch dia foot valve (plastic)
Total = 1 No.s
Rs. 648.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 648.00/ No.s Rs. 648.00

Sl. No. - 24 page No. item no :


Prepairing the DOL starter LT/LK make 2 set checking and cleaning it thoroughly S/F relay Cat no 918580BO
& 918580AO and contact Kit cat no SS95305 and contact Kit cat no SS95305. 2 sets and fitting the same on
panel board.

Total = 1 No.s
Rs. 4179.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 4179.00/ No.s Rs. 4179.00

Sl. No. - 25 page No. item no :


Transport charges side to work and back carring tripod 2" dia pipe of 10 ft. long 6 nos. and withdrawing /
installation materials tools & tackles and pump motor set by matador motor vehicle.

Total = 2 sets
Rs. 1467.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) sets
Rate = @ Rs. 1467.00/ sets Rs. 2934.00

TOTAL = Rs. 64189.00


Add 3% as Contingency = Rs. 1926.00
GROSS AMOUNT = Rs. 66115.00
Page 4

A TOTAL = Rs. 64189.00


B 12% OF [A] = Rs. 7703.00
C [A] + [B] = Rs. 71892.00
D 1% OF [C] = Rs. 719.00
E 3% OF [C] = Rs. 2157.00
GROSS AMOUNT = Rs. 74768.00
Page 5
NAME OF WORK :
Installation of the 15 HP Pump motor with allied works, for drawing water from the tube well, in
location near PWD Electrical Section Office by the SSF battalion Field - Mangal Pandey Uddyan,
Barrackpore during the year 2018 - 19"

Sl. No. - 1 ref.: RATE ANALYSIS item no : 1


Supplying, fitting and fixing starter L&T make(model no ML3FASD Fully automatic Star-Delta Starter CAT No.
SS90730
TOTAL = 1 Set
Analysis Rate @ Rs. 51874.06/ Set Rs. 51874.00

Sl. No. - 2 ref.: RATE ANALYSIS item no : 2


Supplying, fitting and fixing single phase preventor relay L&T make SPPR TYPE SDz5 (for MU-
G30/40/50/75) CAT No. XM818070000

TOTAL = 1 Set
Analysis Rate @ Rs. 3451.60/ Set Rs. 3452.00

Sl. No. - 3 ref.: RATE ANALYSIS item no : 3


Supplying, fitting and fixing 3 core flat submersible cable of 4.0 sq. mm. Finolex make IS 694 1100V.

2 x ( 26.21 + 36.58 + 12.21 ) = 150.00 m


TOTAL = 150.00 m
Analysis Rate @ Rs. 174.58/ m Rs. 26187.00

Sl. No. - 4 ref.: RATE ANALYSIS item no : 4


Supplying and installation of 440 volts 2900 R.P.M. , 15HP Submersible Pump motor set (make KSB model
No. BPD 302/7, UMAI/H150-13/22(S.D.) into the tube well incl., erection of tripod stand by co's own tools &
tackles.

TOTAL = 1 Set
Analysis Rate @ Rs. 87529.55/ Set Rs. 87530.00

Sl. No. - 5 ref.: RATE ANALYSIS item no : 5


Supplying, fitting and fixing of G. I. pipes of TATA make (h) 80 mm dia. Heavy quality

column pipe 4 x 6.00 = 24.00 m


hor. 2 x 6.00 + 2.00 = 14.00 m

TOTAL = 38.00 m
Analysis Rate @ Rs. 1552.56/ m Rs. 58997.00

Sl. No. - 6 ref.: RATE ANALYSIS item no : 6


Supplying, fitting and fixing Wheel valve of approved brand and make tested to 21 Kg per Sq. cm. (for water
lines only) 80 mm dia.

TOTAL = 3 Set
Analysis Rate @ Rs. 11390.87/ Set Rs. 34173.00

Sl. No. - 7 page No. 03 item no : 02


Supplying, fitting and fixing in position G.I. pipes of TATA make for underground works with all necessary
accessories,specials viz.socket, bend, tee, union, cross, elbow, nipple, short piece etc.including cost of all
materials,jointing materials ,cutting pipes,making threads,cutting trenches upto 1.5 metre below surface in
(v) 40 mm
all sorts of dia. medium
soil and quality
refilling the same as directed with two coats of painting on G.I. pipes and specials with
bituminous paint complete
cable protection pipe in all 6.00
5 respect.
x (Payment+ will be made on the centre line =measurement
3.50 33.50ofmthe
total pipe line including all specials No separate payment will be made for accessories,
TOTAL = specials.Payment
33.500 m for `
paintingITEM
will Rate
be made seperately)
add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
Item rate [A] + [B] Colm [C]

[A] [B] [C] [D] [E]


Rs.400.00 Rs.48.00 Rs.448.00 Rs.4.48 Rs.452.48
Rs. 452.48 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Page 6
Rate = @ Rs. 452.48/ m Rs. 15158.00

Sl. No. - 8 ref.: RATE ANALYSIS item no : 7


Laying out the cable within the cable protection pipe from Pump Motor set to the stator
Sl. No. - 7 33.50 m
TOTAL = 33.50 m
Analysis Rate @ Rs. 68.00/ m Rs. 2278.00

Sl. No. - 9 ref.: RATE ANALYSIS item no : 8


Supplying, fitting and fixing 80 mm M.S. housing clamp of approved quality.
TOTAL = 2 Set
Analysis Rate @ Rs. 1885.73/ Set Rs. 3771.00

Sl. No. - 10 ref.: RATE ANALYSIS item no : 9


Supplying, fitting and fixing 80 mm dia flange with washer heavy type ISI marked.
TOTAL = 2 Set
Analysis Rate @ Rs. 419.80/ Set Rs. 840.00

Ref: N.I.T. no. 07/ KWSD-III of 2018-19.


Assistant Engineer, P.W.D. Kolkata West Sub-Division-III, Govt. of West Bengal

Sl. No. - 11 page No. item no :


Jointing the talling cable with proper vulcanizing, dressing and testing.
Total = 12 Point
Rs. 83.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) Point
Rate = @ Rs. 83.00/ Point Rs. 996.00

Sl. No. - 12 page No. item no :


Supplying fitting and fixing upper & lower bush & grinding the journal bush. . 15 HP
Total = 4 No.s
Rs. 450.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 450.00/ No.s Rs. 1800.00

Sl. No. - 13 page No. item no :


Repairing the thrust bearing S/F GM Block & grinding machining & matching withs the thrust plate with S/F
linner clutch plate with circuit lock.(complete unit). . 15 HP

Total = 1 Set
Rs. 1524.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) Set
Rate = @ Rs. 1524.00/ Set Rs. 1524.00

Sl. No. - 14 page No. item no :


S/F Water seal…. 15 HP
Total = 2 No.s
Rs. 100.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 100.00/ No.s Rs. 200.00

Sl. No. - 15 page No. item no :


S/F necking fixing on the cover and matching and matching with the impeller. . . . . .15 HP
Total = 2 No.s
Rs. 1157.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 1157.00/ No.s Rs. 2314.00

Sl. No. - 16 page No. item no :


S/F Impeller. . . . . . . . 15 HP
Total = 2 No.s
Rs. 2400.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 2400.00/ No.s Rs. 4800.00

Sl. No. - 17 page No. item no :


Page 7
S/F Gasket
Total = 6 No.s
Rs. 83.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 83.00/ No.s Rs. 498.00

Sl. No. - 18 page No. item no :


S/F Nut bolt & washers
Total = 12 No.s
Rs. 27.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No.s
Rate = @ Rs. 27.00/ No.s Rs. 324.00

Sl. No. - 19 page No. item no :


Checking and testing the insulation of the submersible pump motor set and the starter with 1000 V Megar
and use of clamp meter for mesuring the load current and also mesuring the Voltage
Total = at on load and off load
1 set
with 2 nos. men power.
Rs. 1467.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) set
Rate = @ Rs. 1467.00/ set Rs. 1467.00

Sl. No. - 20 page No. item no :


Transport charges side to work and back carring tripod 2" dia pipe of 10 ft. long 6 nos. and withdrawing /
installation materials tools & tackles and pump motor set by matador motor vehicle.

Total = 2 sets
Rs. 1467.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) sets
Rate = @ Rs. 1467.00/ sets Rs. 2934.00

PWD schedule of rate w.e.f. 01.11.2017

Sl. No. - 21 page No. 268 item no : 19


Clearing compound premises of shurbs, plants, jungles etc. by cutting and removing as directed (Specific
permission of Engineer-in-Charge prior to execution will be necessary).

by the line 1 x 21.60 x 8.15 = 176.04 m2


by the pump room 1 x 7.50 x 4.50 = 33.75 m2
TOTAL = 209.79 m2
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.11.00 Rs.1.32 Rs.12.32 Rs.0.12 Rs.12.44
Rs. 12.44 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m2
Rate = @ Rs. 12.44/ m2 Rs. 2610.00

Sl. No. - 22 page No. 10 item no : 01


Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable
materials at site and removing rubbish as directed within a lead of 75 m.

a) In ground floor including roof.


1 x 21.60 x 1.850 x 0.150 = 5.994 m3
1 x 7.50 x 1.725 x 0.150 = 1.941 m3
TOTAL = 7.935 m3
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.447.00 Rs.53.64 Rs.500.64 Rs.5.01 Rs.505.65
Rs. 505.65 + ( Rs. 50.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 505.65/ m3 Rs. 4012.00

Sl. No. - 23 page No. 10 item no : 02


Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing
rubbish as directed within a lead of 75 m.

(a) upto 150 mm. thick


1 x 21.60 x 1.950 x 0.150 = 6.318 m3
1 x 7.50 x 1.725 x 0.150 = 1.941 m3
Page 8
TOTAL = 8.259 m3
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.939.00 Rs.112.68 Rs.1051.68 Rs.10.52 Rs.1062.20
Rs. 1062.20 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 1062.20/ m3 Rs. 8773.00

Sl. No. - 24 page No. 01 item no : 01


Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but
excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m.
as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming
the bottom, bailing out water as required complete.

(a) Depth of excavation not exceeding 1,500 mm.


around the tube well 1 x 1.80 x 1.80 x 0.625 = 2.03 m3
columns 6 x 0.90 x 0.90 x 1.400 = 6.80 m3
TOTAL = 8.830 m3
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.119.27 Rs.14.31 Rs.133.58 Rs.1.34 Rs.134.92
Rs. 134.92 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 134.92/ m3 Rs. 1191.00

Sl. No. - 25 page No. 12 item no : 13


Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in
conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site
in all respect as per direction of Engineer in charge

existing heap of rubbish 1 x 4.52 x 2.55 x 1.050 = 12.10 m3


masonry Sl. No. - 22 = 7.935 m3
plain cement concrete Sl. No. - 23 = 8.259 m3
excavated earth Sl. No. - 24 = 8.83 m3
Gross Volm = 37.12 m3
Deduct 1/9 th = -4.12 m3
Net Vol = 33.004 m3
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.166.00 Rs.19.92 Rs.185.92 Rs.1.86 Rs.187.78
Rs. 187.78 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 187.78/ m3 Rs. 6197.00

Sl. No. - 26 page No. 226 item no : 01


Brick soling with picked jhama bricks including preparation of bed as necessary with brick joints properly
filled in and packed with powdered earth and including necessary cushion of similar material below the
soling (and in between layers when more than one layer is used) completes as per direction.

(a) Single brick flat soling (thickness 75 mm.)


around the tube well 1 x 1.800 x 1.800 = 3.24 m2
columns 6 x 0.900 x 0.900 = 4.86 m2
Total = 8.100 m2
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.339.00 Rs.40.68 Rs.379.68 Rs.3.80 Rs.383.48
Rs. 339.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m2
Rate = @ Rs. 339.00/ m2 Rs. 2746.00

Sl. No. - 27 page No. 34 item no : 22


I) Cement concrete with graded stone ballast (40 mm size excluding shuttering)
(A) [Pakur Variety] (a) 1:3:6 proportion
around the tube well 1 x 1.800 x 1.800 x 0.100 = 0.324 m3
columns 6 x 0.900 x 0.900 x 0.100 = 0.486 m3
Total = 0.810 m2
ITEM Rate add GST Add Labour Cess Final Rate
Page 9
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.5190.00 Rs.622.80 Rs.5812.80 Rs.58.13 Rs.5870.93
Rs. 5870.93 + ( Rs. 95.00 x 0 floor + Rs. 116.00 x 0 floor ) m2
Rate = @ Rs. 5870.93/ m2 Rs. 4755.00

Sl. No. - 28 page No. 26 item no : 10


Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering
and reinforcement if any, in ground floor as per relevant IS codes.

a) Pakur Variety
around the tube well 1 x 1.800 x 1.800 x 0.200 = 0.648 m3
column footings 6 x 0.900 x 0.900 x 0.200 = 0.972 m3
columns 6 x 0.250 x 0.250 x 2.450 = 0.919 m3

Total = 2.539 m3 `
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.5783.43 Rs.694.01 Rs.6477.44 Rs.64.77 Rs.6542.21
Rs. 6542.21 + ( Rs. 95.00 x 0 floor + Rs. 116.00 x 0 floor ) m3
Rate = @ Rs. 6542.21/ m3 Rs. 16611.00

Sl. No. - 29 page No. 43 item no : 40


Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups,
binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking
and bending to correct shape, placing in proper position and binding with 16 gauge-black annealed wire at
every intersection, complete as per drawing and direction.

(i) Tor steel/Mild Steel, TATA / RINL


conc. Volume percentage steel unit wt.
for 1:1.5:3 Concrete
around the tube well 0.648 m3 x @ 1.00 % x 7.850 MT/m3 = 0.051 MT
column footings 0.972 m3 x @ 1.00 % x 7.850 MT/m3 = 0.076 MT
columns 0.919 m3 x @ 1.75 % x 7.850 MT/m3 = 0.126 MT
Total = 0.253 MT
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.57163.88 Rs.64023.55
Rs.6859.67 Rs.640.24 Rs.64663.79
Rs. 64663.79 + ( Rs. 480.00 x 0 floor + Rs. 560.00 x 0 floor ) MT
Rate = @ Rs. 64663.79/ MT Rs. 16360.00

Sl. No. - 30 page No. 42 item no : 36


Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout
props andto
a) 25 mm thick hardthick
30 mm woodwooden
planks of approvedasthickness
shuttering per decisionwith&required
directionbracing for concrete slabs, beams
of Engineer-ln-Charge.
and columns, lintels curved or straight including fitting, fixing and striking out after completion of works
columns
(upto roof of ground floor) 6 x 1.000 x 2.450 = 14.700 m2
Total = 14.70 m2
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.335.00 Rs.40.20 Rs.375.20 Rs.3.75 Rs.378.95
Rs. 378.95 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m2
Rate = @ Rs. 378.95/ m2 Rs. 5571.00

(f) 25 mm to 30 mm shuttering without staging in foundation


1 x 7.200 x 0.300 = 2.160 m2
6 x 3.600 x 0.300 = 6.480 m2
Total = 8.64 m2
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.209.00 Rs.25.08 Rs.234.08 Rs.2.34 Rs.236.42
Rs. 236.42 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m2
Page 10
Rate = @ Rs. 236.42/ m2 Rs. 2043.00

Sl. No. - 31 page No. 192 item no : 01


Labour for Chipping of concrete surface before taking up Plastering work.
shuttering total of Sl No. 30 = 14.70 m2
Total = 14.70 m2
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.21.00 Rs.2.52 Rs.23.52 Rs.0.24 Rs.23.76
Rs. 23.76 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m2
Rate = @ Rs. 23.76/ m2 Rs. 349.00

Sl. No. - 32 page No. 151 item no : 02


Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering
corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging
where necessary (Ground floor).[Excluding cost of chipping over concrete surface]
(i) With 1:6 cement mortar, (b) 20 mm thick plaster
total of Sl No. 31 = 14.70 m2
Total = 14.70 m2
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.167.00 Rs.20.04 Rs.187.04 Rs.1.87 Rs.188.91
Rs. 188.91 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m2
Rate = @ Rs. 188.91/ m2 Rs. 2777.00

Sl. No. - 33 page No. 200 item no : 01


b) Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality
including smoothening surfaces by sand papering etc.

Dia. length perimeter


Sl. No. - 5 80 mm pipe length = 38.00 m x 0.28 = 11.00 m2
Sl. No. - 7 40 mm pipe length = 33.50 m x 0.15 = 5.00 m2
Total = 16.00 m2
ITEM Rate add GST Add Labour Cess Final Rate
@ 12 % of Colm @ 1% of Colm [C] + [D]
[A] [B]rate
Item [A][C]
+ [B] [D][C]
Colm [E]
Rs.29.00 Rs.3.48 Rs.32.48 Rs.0.32 Rs.32.80
Rs. 32.80 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m2
Rate = @ Rs. 32.80/ m2 Rs. 525.00

Sl. No. - 34 page No. 200 item no : 02


(A) Painting with best quality synthetic enamel paint of approved make and brand including smoothening
surface by sand papering etc. including using of approved putty etc. pn the surface, if necessary :

b) On steel or other metal surface:


With super gloss (hi-gloss) - [iv) Two coat (with any shade except white)
total of Sl. No. - 30 = 16.00 m2
Total = 16.00 m2
Rs. 81.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m2
Rate = @ Rs. 81.00/ m2 Rs. 1296.00

Sl. No. - 35 page No. 196 item no : 08


Applying Exterior grade Acrylic primer of approved quality and brand on plastered or concrete surface old
or
(a)new
One surface
Coat to receive decorative textured(matt finish) or smooth finish acrylic exterior emulsion paint
including scraping and preparing the surface thoroughly, complete as per manufacturer's specification
and as per direction of the EIC. Qty = Sl. No. - 32 = 14.70 m2
Total = 14.70 m2
Rs. 31.40 + ( Rs. 0.72 x 0 floor + Rs. 0.83 x 0 floor ) m2
Rate = @ Rs. 31.40/ m2 Rs. 462.00

Sl. No. - 36 page No. 197 item no : 17


Page 11
Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer's
specification and as per direction of EIC to be applied over acrylic primer as required. The rate includes cost
of material, labour, scaffolding and all incidental charges but excluding the cost of primer.

(Two Coat) b) Premium 100% Acrylic Emulsion


Total = 14.70 m2
Rs. 84.00 + ( Rs. 0.72 x 0 floor + Rs. 0.83 x 0 floor ) m2
Rate = @ Rs. 84.00/ m2 Rs. 1235.00

TOTAL = Rs. 378630.00


Add 3% as Contingency = Rs. 11359.00
GROSS AMOUNT = Rs. 389989.00
Page 12

A TOTAL = Rs. 1158608.00


B 12% OF [A] = Rs. 139033.00
C [A] + [B] = Rs. 1297641.00
D 1% OF [C] = Rs. 12976.00
E 3% OF [C] = Rs. 38929.00
GROSS AMOUNT = Rs. 1349546.00
Page 13

RATE ANALYSIS
Installation of the 15 HP Pump motor with allied works, for drawing water from the tube well, in
location near PWD Electrical Section Office by the SSF battalion Field - Mangal Pandey Uddyan,
Barrackpore during the year 2018 - 19"

ITEM No. 1
Supplying, fitting and fixing starter L&T make
(model no ML3FASD Fully automatic Star-Delta Starter CAT No. SS90730

Cost of one set 1 Set @ Rs. 37525.00 /set = Rs. 37525.00


Loading & un loading 1 Set @ Rs. 500.00 /set = Rs. 500.00
Labour charges for fitting & fixing with tools and
tackles 1 Set @ Rs. 900.00 /set = Rs. 900.00

Sum = Rs. 37525.00 + Rs. 500.00 + Rs. 900.00 = Rs. 38925.00


Sundries @1% + water charges @1% = @ 2 % of Rs. 38925.00 = Rs. 778.50
Sum = Rs. 38925.00 + Rs. 778.50 = Rs. 39703.50
OverHead Charges @ 5% = @ 5 % of Rs. 39703.50 = Rs. 1985.18
Sum = Rs. 39703.50 + Rs. 1985.18 = Rs. 41688.68
Contractors Profit @10% = @ 10 % of Rs. 41688.68 = Rs. 4168.87
Sum = Rs. 41688.68 + Rs. 4168.87 = Rs. 45857.55
GST @12% = @ 12 % of Rs. 45857.55 = Rs. 5502.91
Sum = Rs. 45857.55 + Rs. 5502.91 = Rs. 51360.46
Labour Cess @1% = @ 1 % of Rs. 51360.46 = Rs. 513.60
Sum = Rs. 51360.46 + Rs. 513.60 = Rs. 51874.06

Recommended Rate = Rs. 51874.06 /Set

ITEM No. 2
Supplying, fitting and fixing single phase preventor relay L&T make SPPR TYPE SDz5 (for MU-
G30/40/50/75) CAT No. XM818070000

Cost of one set 1 Set @ Rs. 1190.00 /set = Rs. 1190.00


Loading & un loading 1 Set @ Rs. 500.00 /set = Rs. 500.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 900.00 /set = Rs. 900.00
tackles Sum = Rs. 1190.00 + Rs. 500.00 + Rs. 900.00 = Rs. 2590.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 2590.00 = Rs. 51.80
Sum = Rs. 2590.00 + Rs. 51.80 = Rs. 2641.80
OverHead Charges @ 5% = @ 5 % of Rs. 2641.80 = Rs. 132.09
Sum = Rs. 2641.80 + Rs. 132.09 = Rs. 2773.89
Contractors Profit @10% = @ 10 % of Rs. 2773.89 = Rs. 277.39
Sum = Rs. 2773.89 + Rs. 277.39 = Rs. 3051.28
GST @12% = @ 12 % of Rs. 3051.28 = Rs. 366.15
Sum = Rs. 3051.28 + Rs. 366.15 = Rs. 3417.43
Labour Cess @1% = @ 1 % of Rs. 3417.43 = Rs. 34.17
Sum = Rs. 3417.43 + Rs. 34.17 = Rs. 3451.60

Recommended Rate = Rs. 3451.60 /Set

ITEM No. 3
Page 14

Supplying, fitting and fixing 3 core flat submersible cable of 4.0 sq. mm.
Finolex make IS 694 1100V.

Cost of one set 1 Set @ Rs. 116.00 / m. = Rs. 116.00


Loading & un loading 1 Set @ Rs. 5.00 / m. = Rs. 5.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 10.00 / m. = Rs. 10.00
tackles Sum = Rs. 116.00 + Rs. 5.00 + Rs. 10.00 = Rs. 131.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 131.00 = Rs. 2.62
Sum = Rs. 131.00 + Rs. 2.62 = Rs. 133.62
OverHead Charges @ 5% = @ 5 % of Rs. 133.62 = Rs. 6.68
Sum = Rs. 133.62 + Rs. 6.68 = Rs. 140.30
Contractors Profit @10% = @ 10 % of Rs. 140.30 = Rs. 14.03
Sum = Rs. 140.30 + Rs. 14.03 = Rs. 154.33
GST @12% = @ 12 % of Rs. 154.33 = Rs. 18.52
Sum = Rs. 154.33 + Rs. 18.52 = Rs. 172.85
Labour Cess @1% = @ 1 % of Rs. 172.85 = Rs. 1.73
Sum = Rs. 172.85 + Rs. 1.73 = Rs. 174.58

Recommended Rate = Rs. 174.58 / m.

OR
ITEM No. 3
S & F 3 core flat submersible cable of 4.0 sq. mm. Finolex make IS 694 1100V.
Ref: N.I.T. no. 07/ KWSD-III of 2018-19.
Assistant Engineer, P.W.D. Kolkata West Sub-Division-III, Govt. of West Bengal

Recommended Rate = Rs. 175.00 / mtr.

ITEM No. 4
Supplying and installation of 440 volts 2900 R.P.M. , 15HP Submersible Pump motor set (make KSB
model No. BPD 302/7, UMAI/H150-13/22(S.D.) into the tube well incl., erection of tripod stand by
co's own tools & tackles.

Cost of one set 1 Set @ Rs. 63430.00 /set = Rs. 63430.00


Loading & un loading 1 Set @ Rs. 750.00 /set = Rs. 750.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 1500.00 /set = Rs. 1500.00
tackles Sum = Rs. 63430.00 + Rs. 750.00 + Rs. 1500.00 = Rs. 65680.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 65680.00 = Rs. 1313.60
Sum = Rs. 65680.00 + Rs. 1313.60 = Rs. 66993.60
OverHead Charges @ 5% = @ 5 % of Rs. 66993.60 = Rs. 3349.68
Sum = Rs. 66993.60 + Rs. 3349.68 = Rs. 70343.28
Contractors Profit @10% = @ 10 % of Rs. 70343.28 = Rs. 7034.33
Sum = Rs. 70343.28 + Rs. 7034.33 = Rs. 77377.61
GST @12% = @ 12 % of Rs. 77377.61 = Rs. 9285.31
Sum = Rs. 77377.61 + Rs. 9285.31 = Rs. 86662.92
Labour Cess @1% = @ 1 % of Rs. 86662.92 = Rs. 866.63
Sum = Rs. 86662.92 + Rs. 866.63 = Rs. 87529.55
Page 15

Recommended Rate = Rs. 87529.55 /Set

ITEM No. 5
Supplying, fitting and fixing of G. I. pipes of TATA make (h) 80 mm dia. Heavy quality

Cost of one set 1 Set @ Rs. 1066.00 / m. = Rs. 1066.00


Loading & un loading 1 Set @ Rs. 5.00 / m. = Rs. 5.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 94.00 / m. = Rs. 94.00
tackles Sum = Rs. 1066.00 + Rs. 5.00 + Rs. 94.00 = Rs. 1165.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 1165.00 = Rs. 23.30
Sum = Rs. 1165.00 + Rs. 23.30 = Rs. 1188.30
OverHead Charges @ 5% = @ 5 % of Rs. 1188.30 = Rs. 59.42
Sum = Rs. 1188.30 + Rs. 59.42 = Rs. 1247.72
Contractors Profit @10% = @ 10 % of Rs. 1247.72 = Rs. 124.77
Sum = Rs. 1247.72 + Rs. 124.77 = Rs. 1372.49
GST @12% = @ 12 % of Rs. 1372.49 = Rs. 164.70
Sum = Rs. 1372.49 + Rs. 164.70 = Rs. 1537.19
Labour Cess @1% = @ 1 % of Rs. 1537.19 = Rs. 15.37
Sum = Rs. 1537.19 + Rs. 15.37 = Rs. 1552.56

Recommended Rate = Rs. 1552.56 / m.

ITEM No. 6
Supplying, fitting and fixing Wheel valve of approved brand and make tested to 21 Kg per Sq. cm.
(for water lines only) 80 mm dia.

Cost of one set 1 Set @ Rs. 8442.42 /set = Rs. 8442.42


Loading & un loading 1 Set @ Rs. 5.00 /set = Rs. 5.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 100.00 /set = Rs. 100.00
tackles Sum = Rs. 8442.42 + Rs. 5.00 + Rs. 100.00 = Rs. 8547.42
Sundries @1% + water charges @1% = @ 2 % of Rs. 8547.42 = Rs. 170.95
Sum = Rs. 8547.42 + Rs. 170.95 = Rs. 8718.37
OverHead Charges @ 5% = @ 5 % of Rs. 8718.37 = Rs. 435.92
Sum = Rs. 8718.37 + Rs. 435.92 = Rs. 9154.29
Contractors Profit @10% = @ 10 % of Rs. 9154.29 = Rs. 915.43
Sum = Rs. 9154.29 + Rs. 915.43 = Rs. 10069.72
GST @12% = @ 12 % of Rs. 10069.72 = Rs. 1208.37
Sum = Rs. 10069.72 + Rs. 1208.37 = Rs. 11278.09
Labour Cess @1% = @ 1 % of Rs. 11278.09 = Rs. 112.78
Sum = Rs. 11278.09 + Rs. 112.78 = Rs. 11390.87

Recommended Rate = Rs. 11390.87 /Set

ITEM No. 7
Laying out the cable within the cable protection pipe from Pump Motor set to the stator
Ref: N.I.T. no. 07/ KWSD-III of 2018-19.
Assistant Engineer, P.W.D. Kolkata West Sub-Division-III, Govt. of West Bengal

Recommended Rate = Rs. 68.00 / mtr.


Page 16

ITEM No. 8
Supplying, fitting and fixing 80 mm M.S. housing clamp of approved quality.

Cost of one set 1 Set @ Rs. 1360.00 /set = Rs. 1360.00


Loading & un loading 1 Set @ Rs. 5.00 /set = Rs. 5.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 50.00 /set = Rs. 50.00
tackles Sum = Rs. 1360.00 + Rs. 5.00 + Rs. 50.00 = Rs. 1415.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 1415.00 = Rs. 28.30
Sum = Rs. 1415.00 + Rs. 28.30 = Rs. 1443.30
OverHead Charges @ 5% = @ 5 % of Rs. 1443.30 = Rs. 72.17
Sum = Rs. 1443.30 + Rs. 72.17 = Rs. 1515.47
Contractors Profit @10% = @ 10 % of Rs. 1515.47 = Rs. 151.55
Sum = Rs. 1515.47 + Rs. 151.55 = Rs. 1667.02
GST @12% = @ 12 % of Rs. 1667.02 = Rs. 200.04
Sum = Rs. 1667.02 + Rs. 200.04 = Rs. 1867.06
Labour Cess @1% = @ 1 % of Rs. 1867.06 = Rs. 18.67
Sum = Rs. 1867.06 + Rs. 18.67 = Rs. 1885.73

Recommended Rate = Rs. 1885.73 /Set

ITEM No. 9
Supplying, fitting and fixing 80 mm dia flange with washer heavy type ISI marked.

Cost of one set 1 Set @ Rs. 260.00 /set = Rs. 260.00


Loading & un loading 1 Set @ Rs. 5.00 /set = Rs. 5.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 50.00 /set = Rs. 50.00
tackles Sum = Rs. 260.00 + Rs. 5.00 + Rs. 50.00 = Rs. 315.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 315.00 = Rs. 6.30
Sum = Rs. 315.00 + Rs. 6.30 = Rs. 321.30
OverHead Charges @ 5% = @ 5 % of Rs. 321.30 = Rs. 16.07
Sum = Rs. 321.30 + Rs. 16.07 = Rs. 337.37
Contractors Profit @10% = @ 10 % of Rs. 337.37 = Rs. 33.74
Sum = Rs. 337.37 + Rs. 33.74 = Rs. 371.11
GST @12% = @ 12 % of Rs. 371.11 = Rs. 44.53
Sum = Rs. 371.11 + Rs. 44.53 = Rs. 415.64
Labour Cess @1% = @ 1 % of Rs. 415.64 = Rs. 4.16
Sum = Rs. 415.64 + Rs. 4.16 = Rs. 419.80

Recommended Rate = Rs. 419.80 /Set

ITEM No. 10
Supplying, fitting and fixing 80 mm dia galvanised iron socket heavy type with I.S.I. mark.

Cost of one set 1 Set @ Rs. 352.80 /set = Rs. 352.80


Loading & un loading 1 Set @ Rs. 5.00 /set = Rs. 5.00
Page 17

Labour charges for fitting & fixing with tools and 1 Set @ Rs. 50.00 /set = Rs. 50.00
tackles Sum = Rs. 352.80 + Rs. 5.00 + Rs. 50.00 = Rs. 407.80
Sundries @1% + water charges @1% = @ 2 % of Rs. 407.80 = Rs. 8.16
Sum = Rs. 407.80 + Rs. 8.16 = Rs. 415.96
OverHead Charges @ 5% = @ 5 % of Rs. 415.96 = Rs. 20.80
Sum = Rs. 415.96 + Rs. 20.80 = Rs. 436.76
Contractors Profit @10% = @ 10 % of Rs. 436.76 = Rs. 43.68
Sum = Rs. 436.76 + Rs. 43.68 = Rs. 480.44
GST @12% = @ 12 % of Rs. 480.44 = Rs. 57.65
Sum = Rs. 480.44 + Rs. 57.65 = Rs. 538.09
Labour Cess @1% = @ 1 % of Rs. 538.09 = Rs. 5.38
Sum = Rs. 538.09 + Rs. 5.38 = Rs. 543.47

Recommended Rate = Rs. 543.47 /Set

ITEM No. 11
Supplying, fitting and fixing 80 mm dia galvanised iron plain equal elbow heavy type.

Cost of one set 1 Set @ Rs. 571.00 /set = Rs. 571.00


Loading & un loading 1 Set @ Rs. 5.00 /set = Rs. 5.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 50.00 /set = Rs. 50.00
tackles Sum = Rs. 571.00 + Rs. 5.00 + Rs. 50.00 = Rs. 626.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 626.00 = Rs. 12.52
Sum = Rs. 626.00 + Rs. 12.52 = Rs. 638.52
OverHead Charges @ 5% = @ 5 % of Rs. 638.52 = Rs. 31.93
Sum = Rs. 638.52 + Rs. 31.93 = Rs. 670.45
Contractors Profit @10% = @ 10 % of Rs. 670.45 = Rs. 67.05
Sum = Rs. 670.45 + Rs. 67.05 = Rs. 737.50
GST @12% = @ 12 % of Rs. 737.50 = Rs. 88.50
Sum = Rs. 737.50 + Rs. 88.50 = Rs. 826.00
Labour Cess @1% = @ 1 % of Rs. 826.00 = Rs. 8.26
Sum = Rs. 826.00 + Rs. 8.26 = Rs. 834.26

Recommended Rate = Rs. 834.26 /Set

ITEM No. 12
Supplying, fitting and fixing 80 mm dia galvanised iron plain Tee heavy type.

Cost of one set 1 Set @ Rs. 657.00 /set = Rs. 657.00


Loading & un loading 1 Set @ Rs. 5.00 /set = Rs. 5.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 50.00 /set = Rs. 50.00
tackles Sum = Rs. 657.00 + Rs. 5.00 + Rs. 50.00 = Rs. 712.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 712.00 = Rs. 14.24
Sum = Rs. 712.00 + Rs. 14.24 = Rs. 726.24
OverHead Charges @ 5% = @ 5 % of Rs. 726.24 = Rs. 36.31
Sum = Rs. 726.24 + Rs. 36.31 = Rs. 762.55
Contractors Profit @10% = @ 10 % of Rs. 762.55 = Rs. 76.26
Sum = Rs. 762.55 + Rs. 76.26 = Rs. 838.81
GST @12% = @ 12 % of Rs. 838.81 = Rs. 100.66
Sum = Rs. 838.81 + Rs. 100.66 = Rs. 939.47
Page 18

Labour Cess @1% = @ 1 % of Rs. 939.47 = Rs. 9.39


Sum = Rs. 939.47 + Rs. 9.39 = Rs. 948.86

Recommended Rate = Rs. 948.86 /Set

ITEM No. 13
Supplying, fitting and fixing 80 mm dia galvanised iron Nipple heavy type.

Cost of one set 1 Set @ Rs. 410.00 /set = Rs. 410.00


Loading & un loading 1 Set @ Rs. 5.00 /set = Rs. 5.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 50.00 /set = Rs. 50.00
tackles Sum = Rs. 410.00 + Rs. 5.00 + Rs. 50.00 = Rs. 465.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 465.00 = Rs. 9.30
Sum = Rs. 465.00 + Rs. 9.30 = Rs. 474.30
OverHead Charges @ 5% = @ 5 % of Rs. 474.30 = Rs. 23.72
Sum = Rs. 474.30 + Rs. 23.72 = Rs. 498.02
Contractors Profit @10% = @ 10 % of Rs. 498.02 = Rs. 49.80
Sum = Rs. 498.02 + Rs. 49.80 = Rs. 547.82
GST @12% = @ 12 % of Rs. 547.82 = Rs. 65.74
Sum = Rs. 547.82 + Rs. 65.74 = Rs. 613.56
Labour Cess @1% = @ 1 % of Rs. 613.56 = Rs. 6.14
Sum = Rs. 613.56 + Rs. 6.14 = Rs. 619.70

Recommended Rate = Rs. 619.70 /Set

ITEM No. 14
Supplying, fitting and fixing 80 mm dia galvanised iron Short Piece heavy type.

Cost of one set 1 Set @ Rs. 410.00 /set = Rs. 410.00


Loading & un loading 1 Set @ Rs. 5.00 /set = Rs. 5.00
Labour charges for fitting & fixing with tools and 1 Set @ Rs. 50.00 /set = Rs. 50.00
tackles Sum = Rs. 410.00 + Rs. 5.00 + Rs. 50.00 = Rs. 465.00
Sundries @1% + water charges @1% = @ 2 % of Rs. 465.00 = Rs. 9.30
Sum = Rs. 465.00 + Rs. 9.30 = Rs. 474.30
OverHead Charges @ 5% = @ 5 % of Rs. 474.30 = Rs. 23.72
Sum = Rs. 474.30 + Rs. 23.72 = Rs. 498.02
Contractors Profit @10% = @ 10 % of Rs. 498.02 = Rs. 49.80
Sum = Rs. 498.02 + Rs. 49.80 = Rs. 547.82
GST @12% = @ 12 % of Rs. 547.82 = Rs. 65.74
Sum = Rs. 547.82 + Rs. 65.74 = Rs. 613.56
Labour Cess @1% = @ 1 % of Rs. 613.56 = Rs. 6.14
Sum = Rs. 613.56 + Rs. 6.14 = Rs. 619.70

Recommended Rate = Rs. 619.70 /Set


PREFACING REPORT
NAME OF WORK:

Tube Well boring & lowering of necessary pipes in location near PWD Electrical Section Office by
the SSF battalion Field - Mangal Pandey Uddyan, Barrackpore during the year 2018 - 19"

ESTIMATED AMOUNT : Rs. 753459.00 (INCLUDING 3% CONTINGENCY) :

REPORT:

This estimate has been prepared to meet up the cost of the above mentioned work. In order to cater the
increasing demand during summer and hot season, the higher authority has been decided to provide a
new tube well for the housing.

Clearing compound Premises .


Dismantling all types of plain cement concrete works and masonry
Earth work in excavation of foundation trenches or drains, in all sorts of soil.
Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound.
Labour for boring through any type of soil for sinking tube well of required dia. with top
enlargement by rig boring system.
Supply of PVC pipes & fittings Schedule 80 (medium duty) conforming to ASTMD – 1785. (150 mm
Dia. & 300mm Dia.pipe, Threaded End Cap, End Plug & Nipple) with Hosing Clamp, Reducing socket.
Supply of PVC screen pipe as I.S. (inside dia. 150 mm. Dia. And Side Dia. 165 mm.).
Geophysical investigation of the acquifer by electrologging system.
Labour for making arrangement for showing verticality test including the cost for hire charges of
tools and plants, scafolding, labour etc..
Packing the annular space between the outside of the tube well pipes & strainers and the bore with
pea size washed gravel of approved quality.
Packing annular space between the outside of the housing pipe and the bore with puddled clay balls
of approved size.
Washing and developing tube well with air compressor pumpfor testing the yield in gallons per
hour with 'V' notch.
Collecting sample of water for bacteriological and chemical test from any depth at any time during
execution of work.

PROBABLE TIME OF COMPLETION: 15 Days

MODE OF EXECUTION:
The work will be executed through the agency to be selected by inviting Tender as per Government norms
after obtaining fund from the competent authority and will be executed by P.W.D.
Junior Engineer, P.W.D. Assistant Engineer, P.W.D.
Barrackpore Sub Division-II Barrackpore Sub Division-II
Page 21

NAME OF WORK :

Tube Well boring & lowering of necessary pipes in location near PWD Electrical Section Office by
the SSF battalion Field - Mangal Pandey Uddyan, Barrackpore during the year 2018 - 19"

Sl. No. - 1 page No. 268 item no : 19


Clearing compound premises of shurbs, plants, jungles etc. by cutting and removing as directed (Specific
permission of Engineer-in-Charge prior to execution will be necessary).

1 x 18.00 x 10.50 = 189.00 m2


1 x 7.50 x 4.50 = 33.75 m2
TOTAL = 222.75 m2
Rs. 11.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m2
Rate = @ Rs. 11.00/ m2 Rs. 2450.00

Sl. No. - 2 page No. 10 item no : 01


Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable
materials at site and removing rubbish as directed within a lead of 75 m.

a) In ground floor including roof.


2 x 7.50 x 0.500 x 0.150 = 1.125 m3
2 x 7.50 x 0.375 x 0.150 = 0.844 m3
2 x 4.50 x 0.500 x 0.150 = 0.675 m3
2 x 4.50 x 0.375 x 0.150 = 0.506 m3
TOTAL = 3.150 m3
Rs. 447.00 + ( Rs. 50.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 447.00/ m3 Rs. 1408.00

Sl. No. - 3 page No. 10 item no : 02


Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing
rubbish as directed within a lead of 75 m.

(a) upto 150 mm. thick


2 x 7.50 x 0.600 x 0.150 = 1.350 m3
2 x 4.50 x 0.600 x 0.150 = 0.810 m3
TOTAL = 2.160 m3
Rs. 939.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 939.00/ m3 Rs. 2028.00

Sl. No. - 4 page No. 01 item no : 01


Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but
excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m.
as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming
(a) Depth
the bottom,of bailing
excavation
out not
water
exceeding
as required
1,500
complete.
mm.
1 x 7.20 x 4.50 x 1.450 = 46.98 m3
TOTAL = 46.980 m3
Rs. 119.27 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 119.27/ m3 Rs. 5603.00

Sl. No. - 5 page No. 12 item no : 13


Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in
conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site
in all respect as per direction of Engineer in charge

existing heap of rubbish 1 x 7.20 x 4.10 x 1.150 = 33.95 m3


existing heap of rubbish 1 x 4.52 x 2.55 x 1.050 = 12.10 m3
masonry Sl. No. - 2 = 3.150 m3
plain cement concrete Sl. No. - 3 = 2.160 m3
excavated earth Sl. No. - 4 = 46.98 m3
Gross Volm = 98.34 m3
Deduct 1/9 th = -10.93 m3
Page 22

Net Vol = 87.410 m3


Rs. 166.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 166.00/ m3 Rs. 14510.00

Sl. No. - 6 page No. 50 item no : 02


Labour for boring through any type of soil for sinking tube well of required dia. with top enlargement
by rig boring system (either by reserve circulation or by direct rotary method) including hire charges and
labour for rig machine, tools and plants, staging, force pumping set and making
arrangement for water required for boring etc. complete and lowering of pipes, strainers, blind pipes etc.
complete.

(c) For depth upto 250 metre for 150 mm dia. Tube well with top
enlargement of 300 mm dia.(upto 50 metre.)

(i) First 50 metre


Total = 50.00 m
Rs. 1078.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 1078.00/ m Rs. 53900.00
(ii) Next 50 metre
Total = 50.00 m
Rs. 1066.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 1066.00/ m Rs. 53300.00
(iii) Next 50 metre
Total = 50.00 m
Rs. 1271.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 1271.00/ m Rs. 63550.00
(iv) Rest 100 metre
Total = 45.00 m
Rs. 1446.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 1446.00/ m Rs. 65070.00

Sl. No. - 7 page No. 13 item no : 19 (III)


Supply of PVC pipes & fittings Schedule 80 (medium duty) conforming to ASTMD - 1785 and threaded to
match with GI Pipes as per IS : 1239 (Part - I).

(A) PVC Pipes, 150 mm Dia.


blank bore
1 x 5.00 m + 12 x 5.00 m = 65.00 m
Total = 65.00 m
Rs. 1420.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 1420.00/ m Rs. 92300.00
(A) PVC Pipes, 300 mm Dia.
housing 12 x 3.00 m = 36.00 m
Total = 36.00 m
Rs. 4071.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 4071.00/ m Rs. 146556.00
(v) Nipple (300 mm long) 300 mmDia.
Total = 1 No
Rs. 1568.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 1568.00/ No Rs. 1568.00
(j) Threaded End Cap 300 mmDia.
Total = 1 No
Rs. 1149.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 1149.00/ No Rs. 1149.00
9k) End Plug 150 mmDia.
Total = 1 No
Rs. 907.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 907.00/ No Rs. 907.00

Sl. No. - 8 page No. 56 item no : 27


Page 23

Supplying, fitting and fixing 300 mm M.S. housing clamp of approved quality.

Total = 2 No
Rs. 2235.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 2235.00/ No Rs. 4470.00

Sl. No. - 9 page No.


Tender Item No. 116 of
Tender No. 01/BKP of 2017-2018 of SE / Eastern Circle,
PWD.
Supply of PVC Reducing Socket including labour for fitting, fixing
(i) 300 mm x 200 mm
Total = 1 No
Rs. 2660.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 6794.00/ No Rs. 6794.00
(ii) 200 mm x 150 mm
Total = 1 No
Rs. 1445.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 1445.00/ No Rs. 1445.00

Sl. No. - 10 page No.


Tender Item No. 117 of
Tender No. 01/BKP of 2017-2018 of SE / Eastern Circle,
PWD.
Supply of PVC screen pipe as I.S. (inside dia. 150 mm. Dia. And Side Dia. 165 mm.)
including labour for fitting & fixing
strainer pipe 15 x 2.00 m = 30.00 m
Total = 30.00 m
Rs. 1399.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 0.00 m
Rate = @ Rs. 1399.00/ m Rs. 41970.00

Sl. No. - 11 page No. 56 item no : 28


Providing 200 mm centre guide.
i) With Clamp
Total = 10 No
Rs. 128.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 128.00/ No Rs. 1280.00
ii) With Flat
Total = 10 No
Rs. 71.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 71.00/ No Rs. 710.00

Sl. No. - 12 page No. 56 item no : 29


Geophysical investigation of the acquifer by electrologging system with all
tools and plants as necessary including supply of necessary report.

Total = 1 No
Rs. 8247.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 8247.00/ No Rs. 8247.00

Sl. No. - 13 page No. 55 item no : 22


Labour for making arrangement for showing verticality test including the cost for hire charges of tools
and plants, scafolding, labour etc. All complete.

Total = 1 No
Rs. 916.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 916.00/ No Rs. 916.00

Sl. No. - 14 page No. 55 item no : 24


Page 24

Packing the annular space between the outside of the tube well pipes & strainers and the bore with pea
size washed gravel of approved quality having size from 2 mm to 5 mm or the size approved by the
Engineer-in- charge including cost of all materials labour and equipment complete.
1 x 6.930 x 3.75 x 1.050 = 27.29 m3
Gross Vol = 27.29 m3
Deduct 1/9 th = -3.03 m3
Net Vol = 24.257 m3
Rs. 2029.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 2029.00/ m3 Rs. 49217.00

Sl. No. - 15 page No. 56 item no : 25


Packing annular space between the outside of the housing pipe and the bore with puddled clay balls of
approved size as per direction of the Engineer-in-charge with cost of all materials and labour complete.
carried earth 1 x 5.150 x 3.05 x 1.050 = 16.49 m3
Gross Vol = 16.49 m3
Deduct 1/9 th = -1.83 m3
Net Vol = 14.663 m3
Rs. 417.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m3
Rate = @ Rs. 417.00/ m3 Rs. 6114.00

Sl. No. - 16 page No. 55 item no : 20


Washing and developing tube well with air compressor pump and engine for 8 (eight) hours continuous
pumping per day with necessary arrangements for testing the yield in gallons per hour with 'V'
notch including hire and labour charges for all tools and plants and scaffolding
as required.

Total = 3 day
Rs. 7538.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) day
Rate = @ Rs. 7538.00/ day Rs. 22614.00

Sl. No. - 17 page No. 55 item no : 23


Collecting sample of water for bacteriological and chemical test from any depth at any time during
execution of work including hire and labour charges for tools and plants and sterilising the equipments,
paying all charges and fees, testing etc. complete in all respect as per direction.

Total = 1 No
Rs. 1231.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 1231.00/ No Rs. 1231.00

A TOTAL = Rs. 646857.00


B 12% OF [A] = Rs. 77623.00
C [A] + [B] = Rs. 724480.00
D 1% OF [C] = Rs. 7245.00
E 3% OF [C] = Rs. 21734.00
GROSS AMOUNT = Rs. 753459.00
Page 25

Rs. 753459.00
SL-0 page-43 Item- 40
Reinforcement for reinforced concrete work in all sorts of structures including
distribution bars, stirrups, binders etc initial straightening and removal of loose
rust (if necessary), cutting to requisite length, hooking and bending to correct
(i) Tor steel/Mild
shape, placing in Steel
proper position and binding with 16 gauge-black annealed wire
at every intersection, complete as per drawing
for TATAand direction.
/ RINL
STEP - 1
Item Rate Page - 43 Item No. 40

(i) TATA / RINL Rs. 58249.00/ MT = Rs. 58249.00/ MT

STEP - 2
Deduct issue rate Page - 304 Table - 1.1

(i) TATA / RINL Rs. 41300.00/ MT x 1.05 = -Rs. 43365.00/ MT

STEP - 3
Add Basic price Page - 304 Table - 1.1

(i) TATA / RINL Rs. 36530.00/ MT x 1.05 = Rs. 38356.50/ MT

STEP - 4
Add Contractor profit @ 10 % of Basic Price

(i) TATA / RINL Rs. 36530.00/ MT x 0.10 = Rs. 3653.00/ MT

STEP - 5

Add Cost of carriage from outlet to site with Charge for 1.05 MT steel
necessary loading, unloading and stacking

Road & Bridge Schedule 2015

Page - 224 Sl. - 1.03 ( h )


loading, unloading and stacking by manual means of STEEL

(i) TATA / RINL Rs. 96.00/ MT x 0.75 x 1.05 = Rs. 75.60/ MT

STEP - 6
Add Cost of carriage of steel Charge for 1.05 MT steel
Road & Bridge Schedule 2015

Page - 227 Sl. - 5

(i) TATA / RINL Distance 25.00 Km


up to 5 Km Rs. 82.00/ MT x 1.05 = Rs. 86.10/ MT
above 5 Km and up to 10 Km 5.00 Km Rs. 7.30/ MT x 1.05 = Rs. 38.33/ MT
above 10 Km and up to 20 Km 10.00 Km Rs. 6.70/ MT x 1.05 = Rs. 70.35/ MT
Final rate = Rs. 57163.88/ MT

SL-0 page-43 Item- 40


Reinforcement for reinforced concrete work in all sorts of structures including
distribution bars, stirrups, binders etc initial straightening and removal of loose
rust (if necessary), cutting to requisite length, hooking and bending to correct
(i) Tor steel/Mild
shape, placing in Steel
proper position and binding with 16 gauge-black annealed wire
at every intersection, complete as for
perother
drawing and
than direction.
TATA / RINL
STEP - 1
Item Rate Page - 43 Item No. 40

(ii) for other than TATA / RINL Rs. 55776.00/ MT = Rs. 55776.00/ MT

STEP - 2
Deduct issue rate Page - 304 Table - 1.1

(ii) for other than TATA / RINL Rs. 39300.00/ MT x 1.05 = -Rs. 41265.00/ MT

STEP - 3
Add Basic price Page - 304 Table - 1.1

(ii) for other than TATA / RINL Rs. 34630.00/ MT x 1.05 = Rs. 36361.50/ MT

STEP - 4
Add Contractor profit @ 10 % of Basic Price

(ii) for other than TATA / RINL Rs. 34630.00/ MT x 0.10 = Rs. 3463.00/ MT

STEP - 5
Add Cost of carriage from outlet to site with Charge for 1.05 MT steel
necessary loading, unloading and stacking
Road & Bridge Schedule 2015

Page - 224 Sl. - 1.03 ( h )


loading, unloading and stacking by manual means of STEEL

(ii) for other than TATA / RINL Rs. 96.00/ MT x 0.75 x 1.05 = Rs. 75.60/ MT

STEP - 6
Add Cost of carriage of steel Charge for 1.05 MT steel
Road & Bridge Schedule 2015

Page - 227 Sl. - 5

(ii) for other than TATA / RINL Distance 25.00 Km


up to 5 Km Rs. 82.00/ MT x 1.05 = Rs. 86.10/ MT
above 5 Km and up to 10 Km 5.00 Km Rs. 7.30/ MT x 1.05 = Rs. 38.33/ MT
above 10 Km and up to 20 Km 10.00 Km Rs. 6.70/ MT x 1.05 = Rs. 70.35/ MT
Final rate = Rs. 54605.88/ MT
RATE ANALYSIS
Page : 26 item no : 10 Bldg Schdl 2017
Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size)
excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes
(i) Pakur Variety

STEP - 1
Ref. Page : 14 item no : 07 Mark (A) = Rs. 4482.00
per Cum
STEP - 2
Ref. Page : B-61 Table No. 01
Quantity of stone aggregate to be considered per Cu.m. of Concrete

Railway Stackyard = Barrckpur


20 mm Nominal size = 0.573Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 787.88
10 mm Nominal size = 0.287Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 357.03
TOTAL = 0.860Cu.m (B1) + (B2) = Mark (B) = Rs. 1144.91

STEP - 3
Ref. Page : Table No. 02
Cost of carriage of stone aggregate from Barrckpur railway yard

and upto Dr. B.N. BOSE Sub-Divisional HOSPITAL

Distance = 1.10 km
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1)
Distance from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2)
Distance from10 km to 20 km 0 @ Rs.10.10/km = Rs. 0.00 (C3)
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
for 0.860 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 106.64

STEP - 4
Ref. Page : Table No. 03
Cost of loading and unloading
(a) Stone aggregate below 40 mm nominal size
20 mm Nominal size = 0.573 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 33.23
10 mm Nominal size = 0.287 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 16.65
(D1) + (D2) = Mark (D) = Rs. 49.88

FINAL RATE OF ITEM : - FOR GROUND FLOOR


Mark(A) + Mark(B) + Mark(C) + Mark(D)
4482.00 1144.91 106.64 49.88 = Rs. 5783.43 per Cu.m.

Ref. Page : 25 item no : 11


for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor

RATE ANALYSIS
Page : 24 item no : 04 Bldg Schdl 2017
Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size)
excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes
(i) Pakur Variety

STEP - 1
Ref. Page : 11 item no : 05 Mark (A) = Rs. 3886.00
per Cum
STEP - 2
Ref. Page : B-61 Table No. 01
Quantity of stone aggregate to be considered per Cu.m. of Concrete
Railway Stackyard = Barrckpur
20 mm Nominal size = 0.660Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 907.50
10 mm Nominal size = 0.220Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 273.68
TOTAL = 0.880Cu.m (B1) + (B2) = Mark (B) = Rs. 1181.18

STEP - 3
Ref. Page : Table No. 02
Cost of carriage of stone aggregate from Barrckpur railway yard
and upto Dr. B.N. BOSE Sub-Divisional HOSPITAL
Distance = 1.10 km
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1)
Distance from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2)
Distance from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3)
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
for 0.880 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 109.12

STEP - 4
Ref. Page : Table No. 03
Cost of loading and unloading
(a) Stone aggregate below 40 mm nominal size
20 mm Nominal size = 0.66 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 38.28
10 mm Nominal size = 0.22 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 12.76
(D1) + (D2) = Mark (D) = Rs. 51.04

FINAL RATE OF ITEM : - FOR GROUND FLOOR


Mark(A) + Mark(B) + Mark(C) + Mark(D)
3886.00 1181.18 109.12 51.04 = Rs. 5227.34 per Cu.m.

Ref. Page : 25 item no : 11


for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor

RATE ANALYSIS
Page : 25 item no : 06 Bldg Schdl 2017
Controlled cement concrete with well graded stone chips ( 20mm nominal size) Controlled cement con
[ using concrete mixture ] (i) Pakur Variety (b) M25 grade [ using concrete mixtur

STEP - 1 STEP - 1
Ref. Page : 25 item no : 06 (b) Mark (A) = Rs. 4918.00 Ref.
per Cum
STEP - 2 STEP - 2
Ref. Page : B-59 Table No. 01 Ref.
Quantity of stone aggregate to be considered per Cu.m. of Concrete Quantity of stone aggr
Railway Stackyard = Barrckpur Railway Sta
20 mm Nominal size = 0.540Cu.m Cum@Rs. Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50 20 mm Nomin
10 mm Nominal size = 0.360Cu.m Cum@Rs. Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84 10 mm Nomin
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

STEP - 3 STEP - 3
Ref. Page : Table No. 02 Ref.
Cost of carriage of stone aggregate from Barrckpur railway yard Cost of c
and upto Dr. B.N. BOSE Sub-Divisional HOSPITAL and upto
Distance = 1.10 km Di
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1) Distance up
Distance from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2) Distance
Distance from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3) Distance
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
for 0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60 for

STEP - 4 STEP - 4
Ref. Page : Table No. 03 Ref.
Cost of loading and unloading Cost of loading and un
(a) Stone aggregate below 40 mm nominal size (a) Stone aggregate be
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32 20 mm Nomin
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88 10 mm Nomin
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR FINAL RATE OF ITEM : -


Mark(A) + Mark(B) + Mark(C) + Mark(D)
4918.00 1190.34 111.60 52.20 = Rs. 6272.14 per Cu.m.

Ref. Page : 25 item no : 11 Ref.


for additional floor for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor Extra above the rate of
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor Extra above the rate of

RMC M25
RATE ANALYSIS
Page : 32 item no : 18 Bldg Schdl 2017
supplying Ready Mixed cement concrete with well graded stone chips ( 20mm nominal supplying Ready Mixed
size) (ii) with approved concrete pump (i) Pakur Variety b) M25 grade size) (ii) with approve

STEP - 1 STEP - 1
Ref. Page : 32 item no : 09 (B) Mark (A) = Rs. 5868.00 Ref.
per Cum
STEP - 2 STEP - 2
Ref. Page : B-59 Table No. 01 Ref.
Quantity of stone aggregate to be considered per Cu.m. of Concrete Quantity of stone aggr
Railway Stackyard = Barrckpur Railway Sta
20 mm Nominal size = 0.540Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50 20 mm Nomin
10 mm Nominal size = 0.360Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84 10 mm Nomin
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

STEP - 3 STEP - 3
Ref. Page : Table No. 02 Ref.
Cost of carriage of stone aggregate from Barrckpur railway yard Cost of c
and upto Dr. B.N. BOSE Sub-Divisional HOSPITAL and upto
Distance = 1.10 km Di
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1) Distance up
Distance from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2) Distance
Distance from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3) Distance
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
for 0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60 for

STEP - 4 STEP - 4
Ref. Page : Table No. 03 Ref.
Cost of loading and unloading Cost of loading and un
(a) Stone aggregate below 40 mm nominal size (a) Stone aggregate be
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32 20 mm Nomin
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88 10 mm Nomin
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR FINAL RATE OF ITEM : -


Mark(A) + Mark(B) + Mark(C) + Mark(D)
5868.00 1190.34 111.60 52.20 = Rs. 7222.14 per Cu.m.

Ref. Page : 25 item no : 11 Ref.


for additional floor for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor Extra above the rate of
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor Extra above the rate of
Extra for lifting charge for approved concrete pump@ Rs.20 /Cu.m./floor Extra for lifting charge

RMC M25
RATE ANALYSIS
Page : 32 item no : 18 Bldg Schdl 2017
supplying Ready Mixed cement concrete with well graded stone chips ( 20mm nominal supplying Ready Mixed
size) (ii) without approved concrete pump (i) Pakur Variety b) M25 grade size) (ii) without app

STEP - 1 STEP - 1
Ref. Page : 32 item no : 09 (B) Mark (A) = Rs. 5685.00 Ref.
per Cum
STEP - 2 STEP - 2
Ref. Page : B-59 Table No. 01 Ref.
Quantity of stone aggregate to be considered per Cu.m. of Concrete Quantity of stone aggr
Railway Stackyard = Barrckpur Railway Sta
20 mm Nominal size = 0.540Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50 20 mm Nomin
10 mm Nominal size = 0.360Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84 10 mm Nomin
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

STEP - 3 STEP - 3
Ref. Page : Table No. 02 Ref.
Cost of carriage of stone aggregate from Barrckpur railway yard Cost of c
and upto Dr. B.N. BOSE Sub-Divisional HOSPITAL and upto
Distance = 1.10 km Di
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1) Distance up
Distance from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2) Distance
Distance from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3) Distance
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
for 0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60 for

STEP - 4 STEP - 4
Ref. Page : Table No. 03 Ref.
Cost of loading and unloading Cost of loading and un
(a) Stone aggregate below 40 mm nominal size (a) Stone aggregate be
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32 20 mm Nomin
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88 10 mm Nomin
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR FINAL RATE OF ITEM : -


Mark(A) + Mark(B) + Mark(C) + Mark(D)
5685.00 1190.34 111.60 52.20 = Rs. 7039.14 per Cu.m.

Ref. Page : 25 item no : 11 Ref.


for additional floor for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor Extra above the rate of
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor Extra above the rate of

RMC M30
RATE ANALYSIS
Page : 33 item no : 19 Bldg Schdl 2017
supplying Ready Mixed cement concrete with well graded stone chips ( 20mm nominal supplying Ready Mixed
size) (ii) with approved concrete pump (i) Pakur Variety b) M30 grade size) (ii) with approve

STEP - 1 STEP - 1
Ref. Page : 33 item no : 09 (B) Mark (A) = Rs. 6088.00 Ref.
per Cum
STEP - 2 STEP - 2
Ref. Page : B-59 Table No. 01 Ref.
Quantity of stone aggregate to be considered per Cu.m. of Concrete Quantity of stone aggr
Railway Stackyard = Barrckpur Railway Sta
20 mm Nominal size = 0.540Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50 20 mm Nomin
10 mm Nominal size = 0.360Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84 10 mm Nomin
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

STEP - 3 STEP - 3
Ref. Page : Table No. 02 Ref.
Cost of carriage of stone aggregate from Barrckpur railway yard Cost of c
and upto Dr. B.N. BOSE Sub-Divisional HOSPITAL and upto
Distance = 1.10 km Di
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1) Distance up
Distance from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2) Distance
Distance from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3) Distance
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
for 0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60 for

STEP - 4 STEP - 4
Ref. Page : Table No. 03 Ref.
Cost of loading and unloading Cost of loading and un
(a) Stone aggregate below 40 mm nominal size (a) Stone aggregate be
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32 20 mm Nomin
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88 10 mm Nomin
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR FINAL RATE OF ITEM : -


Mark(A) + Mark(B) + Mark(C) + Mark(D)
6088.00 1190.34 111.60 52.20 = Rs. 7442.14 per Cu.m.
Ref. Page : 25 item no : 11 Ref.
for additional floor for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor Extra above the rate of
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor Extra above the rate of
Extra for lifting charge for approved concrete pump@ Rs.20 /Cu.m./floor Extra for lifting charge

RMC M30
RATE ANALYSIS
Page : 33 item no : 19 Bldg Schdl 2017
supplying Ready Mixed cement concrete with well graded stone chips ( 20mm nominal supplying Ready Mixed
size) (ii) without approved concrete pump (i) Pakur Variety b) M30 grade size) (ii) without app

STEP - 1 STEP - 1
Ref. Page : 33 item no : 09 (B) Mark (A) = Rs. 5855.00 Ref.
per Cum
STEP - 2 STEP - 2
Ref. Page : B-59 Table No. 01 Ref.
Quantity of stone aggregate to be considered per Cu.m. of Concrete Quantity of stone aggr
Railway Stackyard = Barrckpur Railway Sta
20 mm Nominal size = 0.540Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50 20 mm Nomin
10 mm Nominal size = 0.360Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84 10 mm Nomin
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

STEP - 3 STEP - 3
Ref. Page : Table No. 02 Ref.
Cost of carriage of stone aggregate from Barrckpur railway yard Cost of c
and upto Dr. B.N. BOSE Sub-Divisional HOSPITAL and upto
Distance = 1.10 km Di
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1) Distance up
Distance from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2) Distance
Distance from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3) Distance
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
for 0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60 for

STEP - 4 STEP - 4
Ref. Page : Table No. 03 Ref.
Cost of loading and unloading Cost of loading and un
(a) Stone aggregate below 40 mm nominal size (a) Stone aggregate be
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32 20 mm Nomin
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88 10 mm Nomin
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR FINAL RATE OF ITEM : -


Mark(A) + Mark(B) + Mark(C) + Mark(D)
5855.00 1190.34 111.60 52.20 = Rs. 7209.14 per Cu.m.

Ref. Page : 25 item no : 11 Ref.


for additional floor for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor Extra above the rate of
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor Extra above the rate of
Page : 24 item no : 05 Bldg Schdl 2017
Controlled cement concrete with well graded stone chips ( 20mm nominal size)
[ using concrete mixture ] (i) Pakur Variety (b) M20 grade

Page : 24 item no : 06 (b) Mark (A) = Rs. 4578.00


per Cum

Page : B-59 Table No. 01


Quantity of stone aggregate to be considered per Cu.m. of Concrete
Railway Stackyard = Barrckpur
20 mm Nominal size = 0.540Cu.m Cum@Rs. Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50
10 mm Nominal size = 0.360Cu.m Cum@Rs. Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

Page : Table No. 02


Cost of carriage of stone aggregate from Barrckpur 0
Dr. B.N. BOSE Sub-Divisional HOSPITAL
Distance = 1.10 km
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1)
from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2)
from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3)
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60

Page : Table No. 03


Cost of loading and unloading
(a) Stone aggregate below 40 mm nominal size
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR


Mark(A) + Mark(B) + Mark(C) + Mark(D)
4578.00 1190.34 111.60 52.20 = Rs. 5932.14 per Cu.m.

Page : 25 item no : 11
for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor

RMC M40
RATE ANALYSIS
Page : 34 item no : 21 Bldg Schdl 2017
supplying Ready Mixed cement concrete with well graded stone chips ( 20mm nominal
size) (ii) with approved concrete pump (i) Pakur Variety b) M40 grade

Page : 34 item no : 09 (B) Mark (A) = Rs. 6312.00


per Cum

Page : B-59 Table No. 01


Quantity of stone aggregate to be considered per Cu.m. of Concrete
Railway Stackyard = Barrckpur
20 mm Nominal size = 0.540Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50
10 mm Nominal size = 0.360Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

Page : Table No. 02


Cost of carriage of stone aggregate from Barrckpur railway yard
Dr. B.N. BOSE Sub-Divisional HOSPITAL
Distance = 1.10 km
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1)
from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2)
from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3)
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60

Page : Table No. 03


Cost of loading and unloading
(a) Stone aggregate below 40 mm nominal size
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR


Mark(A) + Mark(B) + Mark(C) + Mark(D)
6312.00 1190.34 111.60 52.20 = Rs. 7666.14 per Cu.m.

Page : 25 item no : 11
for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor
Extra for lifting charge for approved concrete pump@ Rs.20 /Cu.m./floor

RMC M40
RATE ANALYSIS
Page : 25 item no : 09 (B)(e) Bldg Schdl 2017
supplying Ready Mixed cement concrete with well graded stone chips ( 20mm nominal
size) (ii) without approved concrete pump (i) Pakur Variety b) M40 grade

Page : 25 item no : 09 (B) Mark (A) = Rs. 6127.00


per Cum

Page : B-59 Table No. 01


Quantity of stone aggregate to be considered per Cu.m. of Concrete
Railway Stackyard = Barrckpur
20 mm Nominal size = 0.540Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50
10 mm Nominal size = 0.360Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

Page : Table No. 02


Cost of carriage of stone aggregate from Barrckpur railway yard
Dr. B.N. BOSE Sub-Divisional HOSPITAL
Distance = 1.10 km
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1)
from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2)
from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3)
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60

Page : Table No. 03


Cost of loading and unloading
(a) Stone aggregate below 40 mm nominal size
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR


Mark(A) + Mark(B) + Mark(C) + Mark(D)
6127.00 1190.34 111.60 52.20 = Rs. 7481.14 per Cu.m.

Page : 25 item no : 11
for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor

RMC M20
RATE ANALYSIS
Page : 32 item no : 17 Bldg Schdl 2017
supplying Ready Mixed cement concrete with well graded stone chips ( 20mm nominal
size) (ii) with approved concrete pump (i) Pakur Variety b) M30 grade

Page : 32 item no : 09 (B) Mark (A) = Rs. 5503.00


per Cum

Page : B-59 Table No. 01


Quantity of stone aggregate to be considered per Cu.m. of Concrete
Railway Stackyard = Barrckpur
20 mm Nominal size = 0.540Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50
10 mm Nominal size = 0.360Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

Page : Table No. 02


Cost of carriage of stone aggregate from Barrckpur 0
Dr. B.N. BOSE Sub-Divisional HOSPITAL
Distance = 1.10 km
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1)
from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2)
from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3)
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60

Page : Table No. 03


Cost of loading and unloading
(a) Stone aggregate below 40 mm nominal size
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR


Mark(A) + Mark(B) + Mark(C) + Mark(D)
5503.00 1190.34 111.60 52.20 = Rs. 6857.14 per Cu.m.
Page : 25 item no : 11
for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor
Extra for lifting charge for approved concrete pump@ Rs.20 /Cu.m./floor

RMC M20
RATE ANALYSIS
Page : 32 item no : 17 Bldg Schdl 2017
supplying Ready Mixed cement concrete with well graded stone chips ( 20mm nominal
size) (ii) without approved concrete pump (i) Pakur Variety b) M30 grade

Page : 32 item no : 09 (B) Mark (A) = Rs. 5319.00


per Cum

Page : B-59 Table No. 01


Quantity of stone aggregate to be considered per Cu.m. of Concrete
Railway Stackyard = Barrckpur
20 mm Nominal size = 0.540Cu.m @ Rs.1375.00 Per Cu.m. (B1) = Rs. 742.50
10 mm Nominal size = 0.360Cu.m @ Rs.1244.00 Per Cu.m. (B2) = Rs. 447.84
TOTAL = 0.900Cu.m (B1) + (B2) = Mark (B) = Rs. 1190.34

Page : Table No. 02


Cost of carriage of stone aggregate from Barrckpur 0
Dr. B.N. BOSE Sub-Divisional HOSPITAL
Distance = 1.10 km
Distance up to 5 km = L.S. =Rs.124.00 = Rs. 124.00 (C1)
from 5 km to 10 km 0.00 @ Rs.10.90/km = Rs. 0.00 (C2)
from10 km to 20 km @ Rs.10.10/km = Rs. 0.00 (C3)
(C1) + (C2) + (C3) = Rs. 124.00 per Cu.m.
0.900 Cu.m. @ Rs. 124.00 per Cu.m. Mark (C) = Rs. 111.60

Page : Table No. 03


Cost of loading and unloading
(a) Stone aggregate below 40 mm nominal size
20 mm Nominal size = 0.54 Cum@Rs. 58.00 Per Cu.m. (D1) = Rs. 31.32
10 mm Nominal size = 0.36 Cum@Rs. 58.00 Per Cu.m. (D2) = Rs. 20.88
(D1) + (D2) = Mark (D) = Rs. 52.20

FINAL RATE OF ITEM : - FOR GROUND FLOOR


Mark(A) + Mark(B) + Mark(C) + Mark(D)
5319.00 1190.34 111.60 52.20 = Rs. 6673.14 per Cu.m.

Page : 25 item no : 11
for additional floor
Extra above the rate of ground floor,up to 4th floor @ Rs.95/Cu.m./ floor
Extra above the rate of ground floor,above 4th floor@ Rs.116/Cu.m./floor
Page 43

NAME OF WORK :

Tube Well boring & lowering of necessary pipes in location near PWD Electrical Section Office by
the SSF battalion Field - Mangal Pandey Uddyan, Barrackpore during the year 2018 - 19"

Sl. No. - 1 page No. item no :


Supply of G. I. pipes of TATA make including necessary sockets
(h) 80 mm dia. Heavy quality
1 x 18.00 x 9.50 = 171.00 m
1 x 12.00 x 7.50 = 90.00 m
TOTAL = 261.00 m
Rs. 659.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 659.00/ m Rs. 171999.00

Sl. No. - 2 page No. 103 item no : 02


Supply of galvanised iron socket with I.S.I. mark.
viii) 80 mm dia.
No.
TOTAL = 0 No
Rs. 226.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 226.00/ No Rs. 0.00

Sl. No. - 3 page No. 103 item no : 04


Supply of G.I. plug
viii) 80 mm dia.
No.
TOTAL = 0 No
Rs. 226.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 226.00/ No Rs. 0.00

Sl. No. - 4 page No. 105 item no : 07


Supply of G.I. plain equal elbow of approved brand and make
viii) 80 mm dia.
No.
TOTAL = 0 No
Rs. 365.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 365.00/ No Rs. 0.00

Sl. No. - 2 page No. 21 item no : 33


(A) Labour for fitting and fixing G.I. pipes above ground (exposed) in structures with holder bat clamps
including cost of jointing materials, holder bat clamps etc.,as necessary, including cutting pipe, making
threads etc. complete in all respect with two coats of painting with approved paint any height.
(Payment will be made on the centre line measurement of the total pipeline including specials. Payment of
painting will be paid seperately)

(viii) 80 mm dia.
1 x 18.00 x 9.50 = 171.00 m
1 x 12.00 x 7.50 = 90.00 m
TOTAL = 261.00 m
Rs. 94.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) m
Rate = @ Rs. 94.00/ m Rs. 24534.00

Labour for fitting and fixing G.I. specials including cost of jointing materials.
Page 44

(a) Plug.
(iii) Above 50 mm upto 80 mm dia.

TOTAL = 0 No
Rs. 11.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 11.00/ No Rs. 0.00

(b) Socket, Reducing socket, Bend, Plain equal elbow, Reducing elbow,
Nipple, Short piece.
(iii) Above 50 mm upto 80 mm dia.
TOTAL = 0 No
Rs. 11.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 11.00/ No Rs. 0.00

(c) Plain tee, Reducing tee, Pendent tee, Jamnut, Socket and Nipple
(iii) Above 50 mm upto 80 mm dia.
TOTAL = 0 No
Rs. 11.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 11.00/ No Rs. 0.00

(d) Cross, Union, Long screw.


(iii) Above 50 mm upto 80 mm dia.
TOTAL = 0 No
Rs. 11.00 + ( Rs. 0.00 x 0 floor + Rs. 0.00 x 0 floor ) No
Rate = @ Rs. 11.00/ No Rs. 0.00
Page 45

A TOTAL = Rs. 196533.00


B 12% OF [A] = Rs. 23584.00
C [A] + [B] = Rs. 220117.00
D 1% OF [C] = Rs. 2201.00
E 3% OF [C] = Rs. 6604.00
GROSS AMOUNT = Rs. 228922.00

RATE ANALYSIS

ITEM No. 1
Supplying, fitting and fixing starter
(model no MU-G20H Fully automatic Star-Delta Starter SS95975

Cost of one set 1 Set @ Rs. 15865.00 /set = Rs. 15865.00


Loading & un loading 1 Set @ Rs. 500.00 /set = Rs. 500.00
Labour charges for fitting & fixing with tools and
tackles 1 Set @ Rs. 900.00 /set = Rs. 900.00

Sum = Rs. 15865.00 + Rs. 500.00 + Rs. 900.00 = Rs. 17265.00


Sundries @1% + water charges @1% = @ 2 % of Rs. 17265.00 = Rs. 345.30
Sum = Rs. 17265.00 + Rs. 345.30 = Rs. 17610.30
OverHead Charges @ 5% = @ 5 % of Rs. 17610.30 = Rs. 880.52
Sum = Rs. 17610.30 + Rs. 880.52 = Rs. 18490.82
Contractors Profit @10% = @ 10 % of Rs. 18490.82 = Rs. 1849.08
Sum = Rs. 18490.82 + Rs. 1849.08 = Rs. 20339.90
Page 46

GST @12% = @ 12 % of Rs. 20339.90 = Rs. 2440.79


Sum = Rs. 20339.90 + Rs. 2440.79 = Rs. 22780.69
Labour Cess @1% = @ 1 % of Rs. 22780.69 = Rs. 227.81
Sum = Rs. 22780.69 + Rs. 227.81 = Rs. 23008.50

Recommended Rate = Rs. 23008.50