Project: NH:37 Contract package – EW – II (AS-02/AS-18) Doc. no.

EW-CL-06

Rev. 0
Date
Received
Ref. RFI.
Checklist for : Earthworks (Approval for embankment fill)
No:

Location : Other Information:

Item Description Con Con SC Remarks


Yes No Y N

1 Previous date of FDT-------------------------

2 Setting out
a) Toe pegs installed?
b) Cross fall check?

3) Layer thickness control


a) Maintained as per specification (200mm max)

4) Benching for next layer (min 300mm )

5) Is vegetation removed before filling?

6 Any soft spot area / unsuitable area?


a) If yes, soft spot rectified?

7) Is F.D.T. result okay?

8 Final Inspection with comments P F Date.

Signed for Contractor Designation : Date :

Signed for SC Designation : Date :