08 November 2016
Company Name
PT. Jaya CM David Leong
Raja Manik
Fajrie
Wahyu
Rino
Haris
PT. Brahmayasa Bahtera Yong Seok Cha
Rudi
Ronny
Rina
PT. Tatamulia Nusantara Indah Bayu
Herry
Jalidin
Yatman
Fazar
PT. Caturgriya Naradipa Andi
PT. Gema Graha Sarana Arief
PT. Surya Toto Indonesia Yudhi
PT. Emporindo Alam Raya Alex
PT. Jaga Citra Inti Yanus
Hafiz
PT. Star Delta Utama Sakti Sutrisno
Fazar
PT. Cahaya Teknindo Mandiri Oky
PT. Cipta Sejahtera Lestari Salam
Riki
CGN
Plastering not finish but ceiling
already installed. Not follow
sequence of work.
Tower 2,
3
Level 13
TATA
Temporary cable to remove
before do plastering on
blockwall.
TATA
Blockwall installation not follow
approved MOW. Adhesive
Tower 2, mortar bedding is not filled fully.
4
Level 13
SDUS
Poor workmanship of pipe
installation. Not follow MOW.
JCI
No clip found on pipe conduit
installation. Not follow approved
MOW.
CSL
Tower 2, No frame suspension for ducting
5
Level 13 to drywall. Not follow approved
MOW.
CGN
Ceiling installation not follow
approved MOW.
TATA
No subframe found at the top.
TATA
Tower 2,
6 Chipped structure not finished
Level 13
off with skim coating.
Tower 2, TATA
8
Level 13 No patching to MEP hole.
TATA
Tower 2,
9 Structure clearance not done
Level 13
properly.
TATA
Blockwall installation not follow
approved MOW. No practical
Tower 2,
11 column found in intersection of
Level 13
blockwall. Adhesive
mortar bedding is not filled fully.
TATA,JCI,CSL,SDUS
20 Level 13 Wrong work sequence – plaster
not finished but MEP services
done
TATA
21 Level 12 Blockwall surface preparation
not done proper and start
waterproof
CSL
23 Level 12 FCU back pan not install
correctly but ceiling frame
started
TATA
25 Level 12
Incomplete grouting work
TATA, CGN
34 Level 13
In complete work
TATA
40 level 12
Incomplete blockwall joints
42 level 12
Ceiling frame closing before
MEP service work are
completed