I.

Reporting Period

Reporting period: February 2018 Report submitted on (date): February 19, 2018
Due date: February 18,2018
Planned project duration: 10 days
Planned target date of implementation Actual date started: August 2, 2017
Total Project Cost: 23,100.00 Extended until:

II. IDENTIFYING INFORMATION

Project Title: COMMUNAL GARDEN IN GUMINTA AND PULOG

Type of Project: Cash for work within 10 days

Project Proponent/s: MCCT-IP in GIDA

Number of Beneficiaries: 15 MCCT-IP

Project Beneficiaries: MCCT-IP in GIDA


Project Partner stakeholders: BLGU, MAO

Location of Beneficiaries: Brgy. Guminta and Pulog Buug, ZSP

Area of Project Implementation: Guminta and Pulog

Project Cost:
a. Grants- 32,100.00
b. Local counterpart Contribution
c. BLGU/MLGU- seedlings, bamboo, nails
d. Community/Individual contribution

Summary of the project progress (bullet type)


1. No. of days of implementation (applicable for CBLA/CFW)
 10 days
2. Activities completed (such as training conducted for ST)
3. No. of beneficiaries involved
 11
4. Physical accomplishment/activity accomplishment (descriptive)
 The communal garden of both barangays that they establish was still there but
unfortunately the communal garden of barangay Pulog was not able already to maintain
by the beneficiaries.

5. Issues/gaps/problems/challenges encountered during the implementation


 The communal garden of barangay Pulog as per visited/monitored by the CF that the
beneficiaries weren’t able to maintain their garden.
6. Actions taken and needed assistance

 During the conduct of CFDS the CF reminded the beneficiaries to maintain their
communal garden.

Photo documentation (beneficiaries in action, before and during implementation of the activity/pictures
showing accomplishments):
In Barangay Guminta before the implementation of communal garden

After the implementation of cash for work.

In barangay Pulog, during the implementation of cash for work.


After the implementation of cash for work.

Prepared by: Checked by:

KALYN M. TAYCO ABNIER A. MUALLAM


CF MCCT Provincial Officer

Reviewed by: Noted by:

LEONNIEL C. LAMPERO JONATHAN H. LIMBAGA


SWO III OIC – Pantawid
I. Reporting Period (monthly reporting)

Reporting period: September 25, 2016 Report submitted on (date):9/25/16


Due date:
Planned project duration
Planned target date of implementation Actual date started: July 20, 2016
Total Project Cost: 39,150 Extended until:

II. IDENTIFYING INFORMATION

Project Title: (Planting 9,000 pcs. Mangrove Seedlings in Brgy.


Galas, Dipolog City: A Mangrove Rehabilitation Project)

Type of Project: (cash for work within 11 days)

Project Proponent/s: (MCCT-IP in GIDA)

Number of Beneficiaries: (15 MCCT-IP)

Project Beneficiaries: (Urban poor)

Project Partner stakeholders:BLGU, CSWDO

Location of Beneficiaries: (Bry. Galas, Dipolog City)

Area of Project Implementation: Purok Kamunggay, Sitio North Baybay, Galas, Dipolog City)

Project Cost:
e. Grants- 39,150.00
f. Local counterpart Contribution
g. BLGU/MLGU
h. Community/Individual contribution
Summary of the project progress (bullet type)
7. No. of days of implementation (applicable for CBLA/CFW)
 11 days
8. Activities completed (such as training conducted for ST)
9. No. of beneficiaries involved
 15 days
10. Physical accomplishment/activity accomplishment (descriptive)
 15 MCCT-IP beneficiaries planted 9,000 pcs of mangrove in Brgy. Galas
 - the project was physically completed last August 3, 2016
11. Issues/gaps/problems/challenges encountered during the implementation
 during this time, the beneficiaries have abled complied their individual daily time
record that compensate required 11 working days and submitted to CF. The CF
submitted the documents for payment amounting to 39, 150 to the region and waited
those documents be reviewed.

12. Actions taken and needed assistance

Photo documentation (beneficiaries in action, before and during implementation of the activity/pictures
showing accomplishments):

BEFORE

The MCCT-IP Beneficiaries gathered mangrove seedlings ready for planting and cleaned the
project site.

AFTER
The mangrove seedlings are already planted and require project monitoring for sustainability.

Prepared By: Reviewed By: Noted By:


DIANA ROSE T. SULIMAN MA. MAE S. SALADA MA. CLEOFE M. SOLAMILLO
CF SWO III Provincial Link

I. Reporting Period (monthly reporting)

Reporting period: October 25, 2016 Report submitted on (date):10/25/16


Due date:
Planned project duration
Planned target date of implementation Actual date started: July 20, 2016
Total Project Cost: 39,150 Extended until:

II. IDENTIFYING INFORMATION

Project Title: (Planting 9,000 pcs. Mangrove Seedlings in Brgy.


Galas, Dipolog City: A Mangrove Rehabilitation Project)

Type of Project: (cash for work within 11 days)


Project Proponent/s: (MCCT-IP in GIDA)

Number of Beneficiaries: (15 MCCT-IP)

Project Beneficiaries: (Urban poor)

Project Partner stakeholders:BLGU, CSWDO

Location of Beneficiaries: (Bry. Galas, Dipolog City)

Area of Project Implementation: Purok Kamunggay, Sitio North Baybay, Galas, Dipolog City)

Project Cost:
i. Grants- 39,150.00
j. Local counterpart Contribution
k. BLGU/MLGU
l. Community/Individual contribution

Summary of the project progress (bullet type)


13. No. of days of implementation (applicable for CBLA/CFW)
 11 days
14. Activities completed (such as training conducted for ST)
15. No. of beneficiaries involved
 15 days
16. Physical accomplishment/activity accomplishment (descriptive)
 15 MCCT-IP beneficiaries planted 9,000 pcs of mangrove in Brgy. Galas
 - the project was physically completed last August 3, 2016
17. Issues/gaps/problems/challenges encountered during the implementation
 the beneficiaries have already waited 2 months of their cash for work salary
since there was no payment yet being conducted nor scheduled, while the CF
needs to have a feedback regarding on the status of the documents for
payment being submitted to the region so that he/she can provide appropriate
and legitimate reason regarding on the unpaid cash for work payroll of the
beneficiaries

18. Actions taken and needed assistance

Photo documentation (beneficiaries in action, before and during implementation of the activity/pictures
showing accomplishments):

BEFORE

The MCCT-IP Beneficiaries gathered mangrove seedlings ready for planting and cleaned the
project site.
AFTER

The mangrove seedlings are already planted and require project monitoring for sustainability.

Prepared By: Reviewed By: Noted By:


DIANA ROSE T. SULIMAN MA. MAE S. SALADA MA. CLEOFE M. SOLAMILLO
CF SWO III Provincial Link
I. Reporting Period (monthly reporting)

Reporting period: November 25, 2016 Report submitted on (date):11/25/16


Due date:
Planned project duration
Planned target date of implementation Actual date started: July 20, 2016
Total Project Cost: 39,150 Extended until:

II. IDENTIFYING INFORMATION

Project Title: (Planting 9,000 pcs. Mangrove Seedlings in Brgy.


Galas, Dipolog City: A Mangrove Rehabilitation Project)

Type of Project: (cash for work within 11 days)

Project Proponent/s: (MCCT-IP in GIDA)

Number of Beneficiaries: (15 MCCT-IP)

Project Beneficiaries: (Urban poor)

Project Partner stakeholders:BLGU, CSWDO

Location of Beneficiaries: (Bry. Galas, Dipolog City)

Area of Project Implementation: Purok Kamunggay, Sitio North Baybay, Galas, Dipolog City)

Project Cost:
m. Grants- 39,150.00
n. Local counterpart Contribution
o. BLGU/MLGU
p. Community/Individual contribution

Summary of the project progress (bullet type)


19. No. of days of implementation (applicable for CBLA/CFW)
 11 days
20. Activities completed (such as training conducted for ST)
21. No. of beneficiaries involved
 15 days
22. Physical accomplishment/activity accomplishment (descriptive)
 15 MCCT-IP beneficiaries planted 9,000 pcs of mangrove in Brgy. Galas
 - the project was physically completed last August 3, 2016
23. Issues/gaps/problems/challenges encountered during the implementation
 Until now, the CF didn`t received feedbacks regarding on the status of the
unpaid cash for work payroll of the beneficiaries and there`s no payment yet
conducted nor being scheduled. The beneficiaries and the BLGU have
continued to monitor the area to see the sustainability of the project.
24. Actions taken and needed assistance

Photo documentation (beneficiaries in action, before and during implementation of the activity/pictures
showing accomplishments):

BEFORE
The MCCT-IP Beneficiaries gathered mangrove seedlings ready for planting and cleaned the
project site.

AFTER

The mangrove seedlings are already planted and require project monitoring for sustainability.

Prepared By: Reviewed By: Noted By:


DIANA ROSE T. SULIMAN MA. MAE S. SALADA MA. CLEOFE M. SOLAMILLO
CF SWO III Provincial Link