Professional Documents
Culture Documents
Satip F 001 04
Satip F 001 04
00 30-Sep-17
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
POWER BOILER - Packaged Type SATIP-F-001-04 30-Nov-17 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC-L-2010
2.5 PMI of alloyed materials SAIC-L-2010 SATR-A-2012 H W S. Aramco to witness the initial testing for PMI
SATR-A-2013
Verification & Visual inspection of Refer to the respective SATIPs for Electrical &
2.6 vendor supplied electrical & Instrumentation: ( SATIP-P-113-01, P-515-01, J-100-
instrumentation 01, J-200-01, J-300-01, J-902-03,J-400-01)
3.0 INSTALLATION
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC-L-2010
PMI of Welded joints of the power
3.9 SAIC-L-2010 SATR-A-2012 H W
piping.
SATR-A-2013
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
3.29 Refractory Installation / Verification See Remarks See Remarks Refer to SATIP-N-110-01, N-120-01or N-140-01
4.0 PRE-COMMISSIONING
Instrumentation and electrical pre- Refer to the respective SATIPs for Electrical &
4.5
commissioning Instrumentation
Piping Re-instatement/Hook-up Power SAIC-F-2030
4.1 SAIC-F-2030 H S
piping to Plant piping-Final Inspection SATR-A-2011
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust
1 the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
###
###