4 Clarification from Customer for Incomplete Info Mail Reference 1. Mail Communication Reference for any further clarifications for Project or Product
7 Receipt of LOI from Customer Mail Reference 1. Mail Communication Reference for LOI from Customer
Evaluation of Regulatory/Statutory requirements, 1. CFT Signed off Team Feasibility Commitment Report
8 # 1.5
Environmental Health & Safety Issues (with Name, Department and Signature)
9 Preparation of Timing Chart # 1.2 1. Overall Project Timeline Chart For Project
Evaluation of Regulatory / Statutory requirements, 1. CFT Signed off Team Feasibility Commitment Report
17 # 1.5
Environmental, Health & Safety Concerns / Issues (with Name, Department and Signature)
1. PFMEA
18 Process FMEA AAP/CORP/16
(ensure for PFMEA for complete assembly part)
1. Control Plan
21 Control Plan (Proto-Type) AAP/CORP/QA/11
(ensure for CP for complete assembly part)
1. CFT Signed off MOM
22 Phase 1 Completion Review / Phase 1 Gate Review # 1.7
(with Name, Department and Signature)
1. Management Signed off MOM or Presentations (PPT)
23 Management, CFT & Plant Head Review # 1.8
(with Name, Department and Signature)
Mail Reference 1. Mail Communication Reference from Feedback for any Corrections
49 Feedback Analysis & Corrective Action
& 8D Reports 2. 8D Reports for Non-confirmation found during Validation or Trials
1. Control Plan
50 Production Control Plan # 4.7
(ensure for CP for complete assembly part)
1. PPAP Approval / PSW Mail Reference from Customer
51 Production Source Approval # 4.8
51 Production Source Approval # 4.8
2. Signed off PSW (b/w Aditya & Customer)
1. CFT Signed off MOM
52 Phase 4 Completion Review / Phase 4 Gate Review # 4.11
(with Name, Department and Signature)
1. Management Signed off MOM or Presentations (PPT)
53 Management, CFT & Plant Head Review # 4.12
(with Name, Department and Signature)
Sl No. Phase - 5: Launch, Customer Feedback, Assessment, Analysis, CI’s & Corrective Action
1. PPAP (PFMEA, SPC, MSA, CP, PFD, PSW)
(ensure for any Changeovers are addressed or not during each of the Phases i.e. ECN or
All Documents Review (PPAP & Project related other
54 # 5.1 PCN's, if any)
Documents)
2. Ensure on Closure of any Open Points are Closed or not in each of the Phases, i.e.
Check whether are there any Open Points
1. Ensure for all kinds of Reports against each of the Phases have been made and
55 Inspection Reports & Samples # 5.2
maintained or not
56 Output of each Phase # 5.3 1. Ensure on all Gate Reviews, i.e. Signed off MOM's