You are on page 1of 1

Chapter 6

CEMENT CONCRETE PAVEMENT


Reference to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Specifications
6.6 1500 Rectangular Concrete Block Pavement
Manufacturing, laying of cement concrete blocks of size 0.450 m x 0.300 
Unit = sqm
Taking output = 112.5 sqm
Concrete M30 grade for block, 400 x (0.450 x 0.300 x 0.150) cum 8.10
Concrete M30 for edge block, 2 x 50 x (0.300 x 0.300 x 0.150) cum 1.35
TOTAL cum 9.45
a) Labour
Labour for Manufacturing the Cement Concrete Block :
(i) Mate day 1.70 410.00 697.00
(ii) Mazdoor (Unskilled) day 41.00 410.00 16,810.00
(iii) Mason (2nd class) day 6.00 410.00 2,460.00
(iv) Bhisti day 1.40 390.00 546.00
b) Machinery
Concrete mixer 0.28 / 0.4 cum  hour 6.00 100.00 600.00
Plate vibrator hour 12.00 100.00 1,200.00
Water tanker  6 kl capacity hour 2.00 200.00 400.00
c) Material
(i) Coarse aggregates (9.450 x 0.84) cum 8.50 980.00 8,330.00
(ii) Sand (9.450 x 0.42) cum 4.25 750.00 3,187.50
(iii) Cement t 3.80 6,500.00 24,700.00
(iv) Sand as per Table 1500.5 cum 1.725 300.00 517.50
Bed = 60*0.025 = 1.5 cum
Joints = 1.5*0.15 = 0.225 cum
(v) Cost of water kl 6.00 100.00 600.00
d) Formwork @ 3% of (a+b+c) 1,801.44
e) contengency @ 3% on (a+b+c+d) 1,855.48
f) Contractor’s profit @ 10% on (a+b+c+d+e) 6,370.49
Cost for 112.5  sqm = a+b+c+d+e+f 70,075.42
Rate per sqm = (a+b+c+d+e+f)/112.5 622.89
Note: i. In case curing compound is used in places where there is scarcity
ii. Carriage of C.C. block to site of is payable seperately as per