Saudi Aramco Test Report: LV Cablebus Torque Testing SATR-P-3239 3-Jul-18 Elect
Saudi Aramco Test Report: LV Cablebus Torque Testing SATR-P-3239 3-Jul-18 Elect
00 30-Apr-18
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Inspect the cable bus for proper installation and freedom from surface 16-SAMSS-520
A2
defects. Sec. 9.1
Schedule Q
A3 Check the torque wrench for the calibration validity.
Att. IV, Sec. 7.1
16-SAMSS-520
A4 Prepare a sketch of the cablebus and indicate the joint numbers.
Sec. 8.7.1
16-SAMSS-520
A5 Conductors shall not be spliced.
Sec. 8.2.1.3
Cablebus sections shall be bolted utilizing splice plates with a minimum of 16-SAMSS-520
A6
four (4) bolts (two for each bus section). Sec. 8.7.1
The lock washers shall be either dished (conical) spring washers or split 16-SAMSS-520
A7
lock-washers. Sec. 8.7.1
Check compression applied connectors for correct cable match and SAES-P-104
A9
identification. (NETA ATS, 2009 Sec. 7.3.2.1.4) Sec.3.2
SAES-P-104
A10 Check that the required informations are marked on the compression lugs.
Sec.6.1
Check the bolt and hole size of termination lugs for correctness. SAES-P-104
A11
(NFPA 70, NEC 110.14) Sec.3.2
The Vendor shall provide the recommended torque values for all fastening 16-SAMSS-520
A12
hardware. Sec. 8.7.1
Adjust the torque wrench setting according to the busduct manufacturer 16-SAMSS-520
A13
recommended torque values. Sec. 9.2
Tighten the bolt with the pre-adjusted torque wrench until click sound is 16-SAMSS-520
A14
heard. Sec. 9.2
16-SAMSS-520
A15 Record torque value.
Sec. 9.2
16-SAMSS-520
A16 Record the joint resistance value.
Sec. 9.2
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
3. Test equipment calibration cycle shall not exceed six (6) months.
Schedule Q, Att. lV, Sec. 7.1
C. TEST RESULTS
Retest
Joint # Size of Bolts & Grade Torque Value Resistance Pass Fail Remarks
Date
Note(s):
2. Values of resistance higher than 200 micro ohms and deviations greater than +-20 percent must be investigated before passing.
D. CONCLUSIONS
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Test results are acceptable and in accordance with Saudi Aramco Schedule Q
D1
Engineering Standards and contractual requirements. Sec 1.3
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
REMARKS:
REFERENCE DOCUMENTS:
1. Schedule G -- Material, Tools and Equipment (Pro Forma MP-IK-LS Contract), Contract Specific
2. Schedule Q -- Quality Requirements (Pro Forma Contract), Contract Specific
3. SAES-P-104 -- Wiring Methods and Materials, 01 January 2018
4. 16-SAMSS-520 -- Cablebus, 19 October 2008
5. NETA ATS -- Acceptance Testing Specifications for Electric Equipment and Systems, 2009
*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED