DAILY ACTIVITIES ACCOMPLISHMENT FEBRUARY 24 – MARCH 01, 2020

MONDAY: EXCAVATION AT BLOCK C

TUESDAY: FABRICATION AND PIPELAYING AT BLOCK C


WEDNESDAY: FABRICATION OF PIPE FOR BLOCK C

THURSDAY: FABRICATION OF PIPE


FRIDAY: EXCAVATION AND FABRICATION AT BLOCK C
SATURDAY: FABRICATION AND TAPPING AT BLOCK C

SUNDAY: FABRICATION AND TAPPING AT BLOCK C