NOTICE TO PROCEED 002

PHASE III EXPANSION: METAL TECHNOLOGIES®

DESCRIPTION
This is a confirmation of the verbal approval given to VICSA on June 24th, 2022, during the terrain
preparations for Division I foundations. The trace, terrain humidity, level and compaction
complies with the specifications needed and are aceptable and inside the standars.
Proceed with the foundation template concrete pouring and rebar assembly collocation on
column line B axis 33 -38 and 40 as marked on the drawing below. (see Figure 1).

Figure 1. Foundation floor plan

Photograph 1. Rebar assembly, footing level and trace


Figure 2. Foundation template detail.
inspection.

JESÚS ALBERTO MARTÍNEZ C. MITRE ALDO IVÁN GARCÍA OCAÑA


GT-CONSULTING® GT-CONSULTING®
CIVIL ENGINEER AND PMO CONSULTANT PM & ASSET INSPECTOR
jmartinez@gtconsulting.mx aldogarcia@gtconsulting.mx

Notice to Ptoceed 002


Phase III Expansion | Metal Technologies®
General Contractor: Constructora Vidal S.A. de C.V.
Revisión 00
1 de 1