NOTICE TO PROCEED 003

PHASE III EXPANSION: METAL TECHNOLOGIES®

DESCRIPTION
This is a confirmation of the verbal approval given to VICSA on June 29th, 2022, during the
foundations preparations inspection. The rebar assembly, rebar and formwork levels complies
with drawing specifications and measurements. Proceed with the concrete pouring on
foundations Z-01 of column line B axis 33 -38 and 40 as marked on the drawing below.

¡Error! No se encuentra el origen de la referencia.. Foundation floor plan.

Photograph 1. Rebar assembly, footing level and trace


Figure 1. Foundation template detail.
inspection.

EDUARDO VELARDE LOBATÓN ALDO IVÁN GARCÍA OCAÑA


GT-CONSULTING® GT-CONSULTING®
PROJECT SUPERVISOR PM & ASSET INSPECTOR
evelarde@gtconsulting.mx aldogarcia@gtconsulting.mx

Notice to Ptoceed 003


Phase III Expansion | Metal Technologies®
General Contractor: Constructora Vidal S.A. de C.V.
Revisión 00
1 de 1