PROJECT FILE: SR 34-20

CONTENTS

SECTION 1

Job Summary

SECTION 2

Job Cost Estimate

SECTION 3

Construction Drawing

SECTION 4

Wayleave Clearance

SECTION 5

Correspondence
JOB SUMMARY

1. SCHEME NO : SR 34-20

2. AREA :NAIKABULA

3. DISTRICT : LAUTOKA

4. DESCRIPTION : NEW 11kV FEEDERS FROM NAIKABULA


SUBSTATION

SCOPE OF WORK

REFER TO CONSTRUCTION DRAWING A1//04//N53//269 FOR


CONSTRUCTION DETAILS.

LABOUR

Installation and Commissioning

LINES CONSTRUCTION TEAM – 23 DAYS

INSPECTION TEAM – 5 DAYS

O & M (OVERHEAD) – 12 DAYS

O &M (UNDERGROUND) – 50 DAYS

CABLE JOINTER TEAM – 16DAYS

SUBSTATION TEAM – 5DAYS