GROUP 3

MANPOWER SCHEDULE
DESCRIPTION Day 1-20 Day 21-40 Day 41-60 Day 61-80

REMOVAL OF EXISTING ASPHALT PAVEMENT


Construction Foreman 1
Skilled Laborer Backhoe 1
Skilled Laborer Dumptruck 1
Laborer 2
REMOVAL OF EXISTING BASE COURSE (100mm)
Construction Foreman 1
Skilled Laborer Backhoe 1
Skilled Laborer Dumptruck 1
Laborer 2
Crushed Aggregates Base Course
Construction Foreman 1
Skilled Laborer 1
Laborer 3
PCCP(Plain) Conventional Method 254mm thnk
Construction Foreman 1
Skilled Laborer 5
Laborer 12
Concrete Curb and Gutter 1
Construction Foreman 1
Skilled Laborer 3
Laborer
SIDEWALK
Construction Foreman 1
Skilled Laborer 2
Laborer 6
Structural Excavation (common soil)
Construction Foreman 1
Laborer 12
Drainage System (covered)
Construction Foreman 1
Skilled Laborer 6
Laborer 12
Recondtioning Drainage System (Manhole)
Construction Foreman 1
Skilled Laborer 1
Laborer 2
Project Sign Board
Construction Foreman 1
Skilled Laborer 1
Laborer 1
Traffic Control and Management
Traffic Men 2
Construction Safety And Health
Safety Practitioner 1