REQUIREMENTS / RESOURCES
07/03/2022 2
MANPOWER REQUIREMENTS
Required Existing Variance
Position Remarks
Expat Local Expat Local Expat Local
A. MANAGEMENT STAFF:
Director 1 (1) To be hired
Mine Manager 1 (1) To be hired
Utility Manager 1 (1) To be hired
Planning & Design
1 (1) To be hired
Manager
Mine Planner &
1 1 Existing
Designer
Sub-total 3 2 1 (2) (2)
B. MINE OPERATION:
Dev't & Prod's
4 3 (1) 3 existing, 1 to be hired
Supervisor
16 expats to be hired, 6 locals
MS Operator 16 8 2 (16) (6)
to be promoted from JSMO.
JMS Operator 16 17 1 6 to be promoted to MSO.
07/03/2022 SUMMARY 3
MANPOWER REQUIREMENTS
Required Existing Variance
Position Remarks
Expat Local Expat Local Expat Local
C. SUPPORT SERVICES:
Sakaro
UR-06 TWIN JUMBO DRILL 1 1 Accident
Compound
Sakaro
UR-09 TWIN JUMBO DRILL 1 1 Operational
Compound
Sakaro
UR-10 TWIN JUMBO DRILL 1 1 Operational
Compound
Total 4 4 3
07/03/2022 7
EQUIPMENT REQUIREMENTS
Equipment and
UNIT/ REMARKS
machineries
CODE TYPE Location Req’d Act Var (as of
availability at any
No. August 2020)
given time
Total 4 4 3
07/03/2022 8
EQUIPMENT REQUIREMENTS
Equipment and
UNIT/ REMARKS
machineries
CODE TYPE Location Req’d Act Var (as of
availability at
No. August 2020)
any given time
Canopy
Sakaro malfunction,
UC-06 CHARGER 1 1
Compound abnormal
revolution.
Total 2 2 2
07/03/2022 10
EQUIPMENT REQUIREMENTS
Equipment and
UNIT/ REMARKS
machineries
CODE TYPE Location Req’d Act Var (as of
availability at any
No. August 2020)
given time
V. SCALING MACHINE:
Sakaro Battery problem,
US-03 SCALER 1 1
Compound overheating.
Total 2 2 2
VI. UTILITY MACHINE:
Fuel injection
Sakaro
UC-04 CHARGER/ UTILITY 1 1 problem as per
Compound March 2018 report.
Total 1 1 1
07/03/2022 11
EQUIPMENT REQUIREMENTS
Equipment and
UNIT/ REMARKS
machineries
CODE TYPE Location Req’d Act Var (as of
availability at
No. August 2020)
any given time
VII. DOZER:
Mech’l & elect’l
LD-83 KOMATSU DOZER Sakaro Compound 1 1
problem
Total 1 1 1
Total 1 1 1
07/03/2022 12
MACHINERIES
07/03/2022 13
MACHINERIES REQUIREMENTS
Equipment and
UNIT/ REMARKS
machineries
CODE TYPE Location Req’d Act Var (as of
availability at
No. August 2020)
any given time
Electrical
20 GenSet Sakaro Compound 1 1
problem.
Total 3 3 2
07/03/2022 14
MACHINERIES REQUIREMENTS
Equipment and
REMARKS
UNIT/ machineries
TYPE Location Req’d Act Var (as of
CODE No. availability at any
August 2020)
given time
II. TRANSFORMERS:
Compact Transformer, Surface, 2nd
1 1 Operational.
1250 KVA Portal
Operational for
Portable Air Compressor Sakaro
1 1 bit grinding
(Engine Driven) Compound
machine.
Sakaro HD
Portable Air Compressor
Maintenance 1 1 Operational.
(Electric Driven)
Shop
Total 3 3 2
07/03/2022 16
MACHINERIES REQUIREMENTS
Equipment and
UNIT/ REMARKS
machineries
CODE TYPE Location Req’d Act Var (as of
availability at any
No. August 2020)
given time
IV. BIT GRINDING MACHINE:
Sakaro Lamp &
Bit Grinding Machine
Bit Grinding 2 2 Operational.
(Electric Driven)
Machine Room
Total 4 4 1
V. FANS:
Electric Fan Starter, 380V 1820L VIS To be
1 1
Dual 55 KW Motor Opening reconditioned.
Electric Fan Starter, 380V To be
1820L Exhaust 1 1
Dual 55 KW Motor reconditioned.
Electric Fan Starter, 380V 1755L V2 AR To be
1 1
Dual 55 KW Motor Opening reconditioned.
Electric Fan Starter, 380V 2nd Decline
2 2 Operational.
Dual 55 KW Motor Portal
Electric Fan Starter, 380V 1910L RB To be
1 1
Dual 55 KW Motor Opening reconditioned.
Total 6 6 6
07/03/2022 17
MACHINERIES REQUIREMENTS
Equipment and
UNIT/ REMARKS
machineries
CODE TYPE Location Req’d Act Var (as of
availability at any
No. August 2020)
given time
XIV. WATER PUMPS:
To be
Cafeteria Reservoir 1 1 1
reconditioned.
Stalker Electric
Niche-6, Main Decline 1 1 1 Operational.
Pump, 90KW with
Motor & Base Niche-10, Main Decline 1 1 1 Operational.
Main Store 1 1 1
Niche-2 Main Decline 1 1 1 Operational.
Niche-11, 1820L 1 1 1 Operational.
Grindex Electric Assembling of unit
1 1 1
Pump, 41KW is on-going.
PR initiated for
2 -2 2 dewatering of
1755L and spare.
07/03/2022 18
MACHINERIES REQUIREMENTS
Equipment and
UNIT/ REMARKS
machineries
CODE TYPE Location Req’d Act Var (as of
availability at any
No. August 2020)
given time
Assembling of unit
Niche-1, 1820L 1 1 1
is on-going.
Grindex Electric
Pump, 10.2 KW
PR to be initiated
2 -2 2
for face pump
Total 12 8 -4 12
07/03/2022 19
SERVICE VEHICLES REQUIREMENTS
ITEM DESCRIPTION REQUIRED ACTUAL VARIANCE STATUS / REMARKS
Sub-total 10 8 (2)
07/03/2022 20
SAFETY
REQUIREMENTS
07/03/2022 21
SAFETY REQUIREMENTS
I.Personal Protective Equipment (PPE)
Hard Hat
Cap Lamp (light with battery)
Hearing Protector
Safety Goggles
Snug Coverall (with reflection tape)
Self-Rescuer
Ankle Strap
Steel-toed Boots
Drinking Water
Dust Mask
Safety Gloves
07/03/2022 22
SAFETY REQUIREMENTS
II. Communication
Telephone
Radio
III. First Aid Facility
Refuge Chamber
Portable Toilet
IV. Underground Mobile
Service Vehicle (back-up when ambulance is not available)
Ambulance
07/03/2022 23
SAFETY REQUIREMENTS
V. First Aid Training - All underground
personnel are required to undergo first
aid training.
VI. Fire Fighter - Required a team for fire
fighter.
VII. Provide medical kit of all active headings
that are far from the refuge chamber..
07/03/2022 24
07/03/2022 25
COMMUNICATIONS
RADIO TELEPHONE
07/03/2022 26
REFUGE CHAMBER STATION AND SCAPE ROUTE LOCATION
07/03/2022 2D VIEW 27
REFUGE CHAMBER STATION AND SCAPE ROUTE LOCATION
07/03/2022 3D VIEW 28
REFUGE CHAMBER
07/03/2022 29
STEEL LADDER 1.00 m.
STAIRWELL
FOR SCAPE
1.00 m.
TOP VIEW
TOP VIEW
MANWAY
RAISE
FRONT VIEW
1.00 m.
FRONT VIEW
SIDE VIEW
1.00 m.
SIDE VIEW
07/03/2022 30
SCAPE ROUTE / MANWAY RAISE
07/03/2022 31
PORTABLE TOILET FOR UNDERGROUND
07/03/2022 32
PRODUCTION
REPORT
YEAR 2018
07/03/2022 33
BUDGET VS. MILL REPORT COMPARISON
YEAR 2018
TOTAL
MONTH JAN FEB MAR APR
DAYS 31 29 31 30 121
PLAN
Ore t 15,288 13,808 15,288 14,795
59,178
Gold
g/t 3.00 3.00 3.00 3.00 3.00
Grade
Gold Kg 45.86 41.42 45.86 44.38 178
ACTUAL
Ore t 15,323 13,598 14,746 11,967 55,634
Gold
g/t 2.39 3.06 3.91 1.84 2.84
Grade
Gold Kg 35.49 40.37 56.36 21.09 153
VARIANCE
Ore t 35 (210) (542) (2,828) (3,544)
Gold
g/t (0.61) 0.06 0.91 (1.16) (0.16)
Grade
Gold Kg (10.37) (1.05) 10.50 (23.29) (24)
07/03/2022 34
BUDGET VS. MILL REPORT COMPARISON
20,000
10,000
ORE , TONS
(10,000)
(20,000)
JAN FEB MAR APR
07/03/2022
2018 35
BUDGET VS. MILL REPORT COMPARISON
10.00
8.00
6.00
4.00
GOLD GRADE, g/t
2.00
0.00
(2.00)
(4.00)
(6.00)
(8.00)
(10.00)
JAN FEB MAR APR
07/03/2022
2018 36
BUDGET VS. MILL REPORT COMPARISON
100.00
75.00
50.00
25.00
GOLD , kg
0.00
(25.00)
(50.00)
(75.00)
(100.00)
JAN FEB MAR APR
07/03/2022
2018 37
DEVELOPMENT AND
STOPE STATUS
07/03/2022 38
STOPE STATUS OF VEIN-2 (1960EL-1755L)
AND DEVELOPMENT STATUS OF VEIN-1 (1820L & 1755L)
V2
1755L
V1 1820L
V1a
MINED-OUT
(1820 L-1960 EL
1820L
1820 L
REMNANTS
1755L (1755 L-
1800 L)
V1 V1 V2
a
07/03/2022 41
DRILLING PATTERN
07/03/2022
4M. X 4M. LD 42
07/03/2022
LONGITUDINAL SECTION 43
4.00
0.70 – 0.80
07/03/2022
TYPICAL CROSS SECTION 44
MINING CYCLE
07/03/2022 45
SAKARO UNDERGROUND DEVELOPMENT
MINING CYCLE
ITEM ACTIVITIES DURATION (Hrs.)
1 Blast hole drilling (66-70 holes for 5.0m x 5.5m) 4
2 Charging & Blasting 2
3 Smoke Dissipation 3
4 Water Down Muck (WDM) / Spray water on blasted portion 0.5
5 Hand Scaling / Barring down 1
6 Initial Muck Removal (IMR) & Hauling (45 mins./ cycle) 3
7 Smoke Dissipation at mid of Initial Muck Removal (IMR) 1
8 Resume Initial Muck Removal & Hauling (45 mins./ cycle) 3
9 Smoke Dissipation 1
10 Mechanical Scaling 2
11 Final Muck Removal (FMR) & Hauling (45 mins./ cycle) 1
12 Smoke Dissipation 1
Marking of survey controls (Center line, grade line & stations)/ Geology
13 1.5
evaluation
TOTAL 24
The total time spent during smoke dissipation in one (1) round of blast is six (6) hours. This should be
reduced by boring exhaust holes to improve ventilation.
07/03/2022 46
1-YEAR
MINE PLAN
07/03/2022 47
SAKARO UNDERGROUND DEVELOPMENT AND PRODUCTION PROGRAM
Continue development and stope preparation from 1755L to 1910EL (phase-1) utilizing two (2) expat crews and concurrent activities with stoping to be
manned by two (2) local crews of the remaining slices / cuts at 1765el to 1780el of veins-2 , 21 and continue sill drifting of vein-1 at 1755L and resume
stoping at 1820L as shown on the attached drawing on phase-1. While raise boring activity is dependent on the availability of stations / chambers to be
done by development crews.
1. Expat crew #1 to start at vein-1, 1820L development and stope preparation:
Drive attack ramp at midway of existing vein-1 perpendicular towards footwall side or eastside of the vein to connect at proposed production ramp
and prepare raise bore station of 1820 level development.
2. Expat crew #2 to start driving of 1st and 2nd decline connecting ramp and transformer station to relocate the existing at niche-6 along 2 nd decline
due moisture content of the station. From 2nd decline, drive raise bore station access to prepare RB station at 1910L.
Next activities, the crew will concentrate at vein-1, 1755L development and stope preparation:
Drive attack ramp at midway of existing vein-1 perpendicular towards footwall side or eastside of the vein to connect at proposed production ramp and prepare
raise bore station of 1755 level development.
07/03/2022 48
SAKARO UNDERGROUND DEVELOPMENT AND PRODUCTION
PROGRAM
Resume Bench Stoping of V1S (back el. 1830-1840 el.) with remaining height of 20 meters according to geology but
WAI projection was until 1910 elevation. This should be reviewed and decided at once and may be needs
confirmation drilling above 1820L.
5. This approach is composed of the following criteria to be considered in developing and preparing the stopes of veins-1
and 2.
Assumed 2 meters per day advance of development in every crew which equivalent to 4 meters per day advance,
120 meters per month and 1,440 meters per year.
Production Plan is 180,000 tonnes yearly target or 15,000 tonnes monthly target or 500 tpd @ 3g/t-Au.
For expat manpower requirements, it requires 16 men including rest day replacement and vacation leave in 2-
long shift basis. While local manpower requires 24 men including rest day replacement and absenteeism in 3-shift
system basis.
07/03/2022 49
SAKARO UNDERGROUND DEVELOPMENT AND PRODUCTION
PROGRAM
Expat support services manpower requirements are 1 expat Electrician, 1 expat Mechanic and 2 Raise bore
Operators.
Local support services manpower requirements on pumping, pipe fitting, fan set-up and vent ducting, power line lay-
out extension and roadway maintenance.
07/03/2022 50
SAKARO UNDERGROUND DEVELOPMENT AND PRODUCTION
PROGRAM
7. Water supply for surface and underground use and potable water shall be available.
8. Power supply from EEPCo shall be available and GENSETS will serve as back-up or spare during emergency cases.
9. Explosive supplies shall be available in every shift.
10. Rock bolt support shall be available as required.
11. Service lines (vent duct, water supply & power supply) accessories shall be available as required.
12. Refuge Chamber will be decided.
13. Required equipment and machineries shall be available at any given time:
Two Boomer Jumbo Drill - 3 units
Scoop Tram - 3 units
Dump Truck - 5 units
Charger - 2 units
Scaler - 2 units
07/03/2022 51
SAKARO UNDERGROUND DEVELOPMENT DESIGN BY PHASE
Portal1, el. 2075
SCAPE ROUTE
(1st Decl., MD)
V1a 1635L
1635L
1600L
v2
v1
V1a
V2
V1
V1a
07/03/2022 55
GANTT CHART
SAKARO UNDERGROUND DEVELOPMENT METERAGE
2021
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
31 29 31 30 31 30 31 31 30 31 30 31 366
Access 57 33 48 16 44 13 210
Reamer Station 13 3 10 25
Total Development
186 174 186 140 124 120 124 124 120 124 120 124 1,666
Meterage
07/03/2022 SUMMARY 56
SAKARO UNDERGROUND DEVELOPMENT TONNAGE
2021
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
31 29 31 30 31 30 31 31 30 31 30 31
Total Dev't Ore Tonnage
2265 2119 2265 731 7,381
Generated
Total Dev't Waste
7128 6669 7128 6340 6263 6061 6263 6263 6061 6263 6061 6263 76,760
Tonnage Generated
Combined Total Tonnage
9394 8788 9394 7071 6263 6061 6263 6263 6061 6263 6061 6263 84,141
Generated
07/03/2022 SUMMARY 57
1-YEAR SAKARO UNDERGROUND RAISEBORING SCHEDULE
(PHASE-1)
07/03/2022 58
07/03/2022 59
07/03/2022 60
1-YEAR SAKARO MINE PRODUCTION PLAN
Month
Total
Description UOM Budget
Jan Feb March April May June July Aug Sept Oct Nov Dec 2021
31 28 31 30 31 30 31 31 30 31 30 31
Production &
Dev't Ore
Tonnage tons 15,288 13,808 15,288 14,795 15,288 14,795 15,288 15,288 14,795 15,288 14,795 15,288 180,000
Gold Grade g/t-Au 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
Metal
Content 46 41 46 44 46 44 46 46 44 46 44 46 540
07/03/2022 SUMMARY 61
REVENUE
The 2021mine production plan is 180,000
tons at 3.00 g/t-Au mill grade, 540 kg. or
19,048 ounces of gold will be produced
which will generate a revenue of 36.86
million US dollars or 1.32 billion birr with
assumed gold price of USD 1,935/0unce.
Combined ore tonnage will be generated
from the exploration/ development drives
and stoping grounds.
07/03/2022 SUMMARY 62
THE
<<<END>>>
07/03/2022 63
THANK YOU !!!