You are on page 1of 4

EPIC FOR FIRE STATIONS AT MIC - 143/18

SITE WORKS SCHEDUEL MEETING - 17/10/2020


S.No Area Work Describtion Start Date End Date Work Status
MAIN FIRE STATION BUILDING
1 MFS - Zone 2 Back side Blockwork 24-Oct-20 4-Nov-20 Scaffolding work in progress
2 Copin Beam 5-Nov-20 11-Nov-20 conflict with paint, roof, gutter forecasted
3 Plastering - External 15-Nov-20 19-Nov-20 conflict with paint, roof, gutter forecasted
4 Plastering Internal 20-Nov-20 25-Nov-20 conflict with paint, roof, gutter forecasted
MFS - Zone 1 - GF Wet Area Water Proofing(Toilet) completed
5 Wet Area Water Proofing(Laundry) 19-Oct-20 22-Oct-20
6 Ramp level difference rectification-Beam 21-Oct-20 Waiting for the TQ approval
7 Ramp slope rectification-Slab - Zone - 2 27-Oct-20 After Grade beam concrete
8 Tiling Pantry & Dining Room 21-Oct-20 Setting out approved. Work in progress
9 Tiling Ablution Room 30-Oct-20 Waiting for HVAC duct complection
10 Tiling work - laundry Room 23-Oct-20 27-Oct-20
11 G.F Tiling works -corridor 1-Nov-20
12 Wooden Door installation work 25-Oct-20
13 Substation Trench Cover done
14 Ceiling - Bulkhead
15 Training Room done
16 Ready Room - Bulkhead done
17 Locker Room 20-Oct-20 22-Oct-20
Corridor Ceiling 24-Oct-20
18 Training Wall Primer 19-Oct-20 20-Oct-20
First floor Partition gypsum work temporarily going to hold the Partition work
surface Preparation inspection on day after tomorrow
19 Toilet plasering work 18-Oct-20 21-Oct-20 (19-10-20)
20 Floor tiling works (5 Offices - Right ) done
21 Ceiling @ Rooms in FF 25-Oct-20 2-Nov-20
Zone -3 Metal Door installation 1-Nov-20 carpenters are busy with ceiling
22 Scread Waterproofing roof , Zone 3 10-Dec-20 inspection on 19-10-20
MAIN FIRE STATION - EXTERNAL WORKS
23 Culvert - concrete works 23-Oct-20 27-Oct-20
24 Wing Wall 28-Oct-20 5-Nov-20
25 Road Construction
26 Land Development - Substation Extention done
27 Road Connection- developmet work done
28 Sewage / Storm Manholes 1 pending
29 Fire Chambers - 5 Excavation done, awaiting rebar info
30 Silt Chambers - 4 Nos 2 done precase. One erection tomorrow
31 JRC - 8 Nos
32 Electrical Chamber
33 Kerbstone for New Layout - Substation done
34 Road Kerbstone Pending kerb: around 1300 M
35 Electrical Chamber - handhole 29 Pending handhole:
36 Traffic Chamber - quantity : 8
37 Fire Alarm Chamber - handhole 13
38 Modular Soak away - 4 Nos (For One) 20-Oct-20
39 Light Pole (12m) - 37 Nos started mockup. Date after approval
40 Light Pole (4m) - 15 Nos started mockup. Date after approval
41 Gully - 26 16 Completed
EPIC FOR FIRE STATIONS AT MIC - 143/18
SITE WORKS SCHEDUEL MEETING - 17/10/2020
S.No Area Work Describtion Start Date End Date Work Status
MAIN FIRE STATION - INFRASTRUCTURE
42 Infrastructure(HV Works)
43 Excavation at Entry -1
44 Aggregate Filling
45 precast Slab 28-Oct-20
46 Back Filling up to sun grade level
47 Pipe Protection
48 Excavation -Entry 2 20-Oct-20
49 Aggregate Filling 21-Oct-20
50 Precast Slab 28-Oct-20
51 Backfilling up to subgrade
52 traffic foundation excavation Awaiting for MIC letter
53 road kerb works
SATELLITE FIRE STATION BUILDING
EXTERNAL WORKS
1 Substation - Door Fixing 19-Oct-20 done
2 External Plastering Completed
3 Roof Plastering Completed
4 Substation Scread Completed
5 Tiling works - Dinning Room Completed
6 Tiling works - Battery Room Completed
7 Tiling - Locker Room 17-Oct-20 26-Oct-20 set out over
8 Structural Steel - Intumscent coating 30-Oct-20 2 layer over as of 19 oct
9 Pump Room Block Work Completed
10 Pump Room Plastering - Internal 2-Nov-20
11 Pump Room Plastering - External 10-Nov-20
12 Pump Room - Grade Slab 26-Oct-20
13 Pump Room - Plinth 27-Oct-20
14 Stome / Foul - Manholes (19 Nos) (5 Nos) 23-Oct-20
15 Kerbstone - East - 2nd Side over
16 Pump room parapet Block works over
17 Fence Foundation (21 Nos)
18 Ramp Level Rectification
19 Lagoon Earth Work 20-Oct-20
20 Lagoon Lining Work 26-Oct-20
INFRASTRUCTURE
1 Trial Pit revise route Completed
2 Crossing Matrix Submitted
3 Trench Excavation (Sector vise)
4 S1 - SFS to Qafac Signal (400M)
5 S2 - Landscape to New Street (34491-13119) (170M)
6 S3 - Qatalum Silos to New Street (34491-2375) (115M)
7 Traffic Foundation Permits Awaiting for MIC Letter
8 HDD work permit
Sl No Location
MFS
Description Detail Start Date End Date Remarks
Tiling Dining
Laundry

You might also like