S.No Area Work Describtion Start Date End Date Work Status MAIN FIRE STATION BUILDING 1 MFS - Zone 2 Back side Blockwork 24-Oct-20 4-Nov-20 Scaffolding work in progress 2 Copin Beam 5-Nov-20 11-Nov-20 conflict with paint, roof, gutter forecasted 3 Plastering - External 15-Nov-20 19-Nov-20 conflict with paint, roof, gutter forecasted 4 Plastering Internal 20-Nov-20 25-Nov-20 conflict with paint, roof, gutter forecasted MFS - Zone 1 - GF Wet Area Water Proofing(Toilet) completed 5 Wet Area Water Proofing(Laundry) 19-Oct-20 22-Oct-20 6 Ramp level difference rectification-Beam 21-Oct-20 Waiting for the TQ approval 7 Ramp slope rectification-Slab - Zone - 2 27-Oct-20 After Grade beam concrete 8 Tiling Pantry & Dining Room 21-Oct-20 Setting out approved. Work in progress 9 Tiling Ablution Room 30-Oct-20 Waiting for HVAC duct complection 10 Tiling work - laundry Room 23-Oct-20 27-Oct-20 11 G.F Tiling works -corridor 1-Nov-20 12 Wooden Door installation work 25-Oct-20 13 Substation Trench Cover done 14 Ceiling - Bulkhead 15 Training Room done 16 Ready Room - Bulkhead done 17 Locker Room 20-Oct-20 22-Oct-20 Corridor Ceiling 24-Oct-20 18 Training Wall Primer 19-Oct-20 20-Oct-20 First floor Partition gypsum work temporarily going to hold the Partition work surface Preparation inspection on day after tomorrow 19 Toilet plasering work 18-Oct-20 21-Oct-20 (19-10-20) 20 Floor tiling works (5 Offices - Right ) done 21 Ceiling @ Rooms in FF 25-Oct-20 2-Nov-20 Zone -3 Metal Door installation 1-Nov-20 carpenters are busy with ceiling 22 Scread Waterproofing roof , Zone 3 10-Dec-20 inspection on 19-10-20 MAIN FIRE STATION - EXTERNAL WORKS 23 Culvert - concrete works 23-Oct-20 27-Oct-20 24 Wing Wall 28-Oct-20 5-Nov-20 25 Road Construction 26 Land Development - Substation Extention done 27 Road Connection- developmet work done 28 Sewage / Storm Manholes 1 pending 29 Fire Chambers - 5 Excavation done, awaiting rebar info 30 Silt Chambers - 4 Nos 2 done precase. One erection tomorrow 31 JRC - 8 Nos 32 Electrical Chamber 33 Kerbstone for New Layout - Substation done 34 Road Kerbstone Pending kerb: around 1300 M 35 Electrical Chamber - handhole 29 Pending handhole: 36 Traffic Chamber - quantity : 8 37 Fire Alarm Chamber - handhole 13 38 Modular Soak away - 4 Nos (For One) 20-Oct-20 39 Light Pole (12m) - 37 Nos started mockup. Date after approval 40 Light Pole (4m) - 15 Nos started mockup. Date after approval 41 Gully - 26 16 Completed EPIC FOR FIRE STATIONS AT MIC - 143/18 SITE WORKS SCHEDUEL MEETING - 17/10/2020 S.No Area Work Describtion Start Date End Date Work Status MAIN FIRE STATION - INFRASTRUCTURE 42 Infrastructure(HV Works) 43 Excavation at Entry -1 44 Aggregate Filling 45 precast Slab 28-Oct-20 46 Back Filling up to sun grade level 47 Pipe Protection 48 Excavation -Entry 2 20-Oct-20 49 Aggregate Filling 21-Oct-20 50 Precast Slab 28-Oct-20 51 Backfilling up to subgrade 52 traffic foundation excavation Awaiting for MIC letter 53 road kerb works SATELLITE FIRE STATION BUILDING EXTERNAL WORKS 1 Substation - Door Fixing 19-Oct-20 done 2 External Plastering Completed 3 Roof Plastering Completed 4 Substation Scread Completed 5 Tiling works - Dinning Room Completed 6 Tiling works - Battery Room Completed 7 Tiling - Locker Room 17-Oct-20 26-Oct-20 set out over 8 Structural Steel - Intumscent coating 30-Oct-20 2 layer over as of 19 oct 9 Pump Room Block Work Completed 10 Pump Room Plastering - Internal 2-Nov-20 11 Pump Room Plastering - External 10-Nov-20 12 Pump Room - Grade Slab 26-Oct-20 13 Pump Room - Plinth 27-Oct-20 14 Stome / Foul - Manholes (19 Nos) (5 Nos) 23-Oct-20 15 Kerbstone - East - 2nd Side over 16 Pump room parapet Block works over 17 Fence Foundation (21 Nos) 18 Ramp Level Rectification 19 Lagoon Earth Work 20-Oct-20 20 Lagoon Lining Work 26-Oct-20 INFRASTRUCTURE 1 Trial Pit revise route Completed 2 Crossing Matrix Submitted 3 Trench Excavation (Sector vise) 4 S1 - SFS to Qafac Signal (400M) 5 S2 - Landscape to New Street (34491-13119) (170M) 6 S3 - Qatalum Silos to New Street (34491-2375) (115M) 7 Traffic Foundation Permits Awaiting for MIC Letter 8 HDD work permit Sl No Location MFS Description Detail Start Date End Date Remarks Tiling Dining Laundry