Professional Documents
Culture Documents
Method Statement For Excavation Works
Method Statement For Excavation Works
METHOD STATEMENT
Content Page No
1) Introduction 4
2) Scope 4
3) Responsibilities 4
4) Equipment 4
5) Procedure 4
6) Safety Measures 5
7) Risk Assessment 6
8) ITP 7
9) Risk Matrix 8
METHOD STATEMENT FOR
3. RESPONSIBILITIES
3.1. The contractor’s calculations for setting out from established points shall be
available for inspection by the Engineer.
3.3. The site Engineer shall check that the existing Ground levels as indicated on the
drawings are correct. Should there appear to be any discrepancies the contractor
shall agree the correct level with the Engineer.
3.4. The site Engineer shall be deemed to have satisfied himself as to the character of
the site and all the various materials, strata, ground water level etc. and all items
and things liable to affect or encountered in the excavation and earth works.
3.5. The Site Engineer shall be responsible for ensuring that all works are carried out
strictly in accordance with this Method Statement, the requirements of the client
and the overall contract documents.
3.6. The Site Engineer to ensure that all the works are carried out strictly in accordance
with safety norms.
5. PROCEDURE
5.1 The site to be excavated shall be cleared off all the trees, bushes etc. All
rubbish and grubbing matter shall be burned or disposed of site. (By
enabling subcontractor).
5.2 Excavation will be done by shovel, loader, hand shovel up to 3.0m from NGL
(By enabling subcontractor).
5.3 Necessary dewatering shall be done at site by an approved sub-contractor
and accomplish dewatering without damaging existing buildings adjacent to
the excavation.
5.4 Maintain water level in a minimum of 600mm below surface of excavation as
specified.
5.5 Loose soil, bad ground or cavities met within any part of the excavations for
foundations of structure shall be excavated to a solid formation and filled to
foundation level with hard core or other approved material properly
compacted to the Engineer’s approval
5.6 Extra quantities to be shifted outside the plot / approved dumping area.
5.7 Unauthorized / Over excavation shall be backfilled with approved filling
materials only.
5.8 In situ density test shall be done at site.
5.9 The contractor shall report to the Engineer when excavations are ready to
receive P.C.C / foundation concrete and shall obtain consent approval
before depositing concrete.
6. SAFETY MEASURES
1. Experienced persons will execute the driving operations.
2. Safety Officer, Site Engineer & Foreman will observe the works.
3. Safety measures will be as per safety manual.
7. RISK ASSESSMENT
DATE
1 Use of heavy Existing pipes & Failure to identify the Contamination of soil. 2 2 4 medium Verify utility service drawings and mark the services on the ground if any.
equipment buried cable being buried services and Sewer lines & electrical Identify and cordon the area in a safe method.
struck. marking it. lines’ disconnection of Immediate
Communicate method statement and Risk Assessment to workforce prior
Failure to follow the commercial links & to start the work.
safety rules and Damage to other
regulations underground services Ensure all equipment are certified by EIAC approved third party inspection
Electrocution, body.
Flooding of area, Heavy equipment should be operated by competent certified operator.
Personnel Injury, Record of pre-use inspection by competent person for all heavy equipment
Property damage. should be maintained. Ensure the equipment is fitted with reverse alarm
and flashing light.
Close supervision by a competent supervisor for all times for guiding the
activity.
Hand excavation in doubtful areas.
8. ITP
Preparation of relevant drawings and Project manager, Approved for construction All documents approved or Method Statement,
Review of documents DS
1.1 method statement, Inspection and QA/QC Eng. drawings/ approved as noted. drawings, HSE plan &
Test Plan, HSE procedure. HSE officer Project Specifications Comments – Incorporate and ITP approval
Proceed with works
9. RISK MATRIX