This document provides progress summaries for multiple project areas of a construction project, including piping fabrication, piping erection, steel fabrication, steel erection, tie-in installation, piping hydro testing, equipment erection, painting, insulation, and an overall summary. It includes details on the quantity and man hours for each area, along with the weighting and percentage of progress completed for each. The overall progress across all disciplines for the project is reported as 91.3%.
This document provides progress summaries for multiple project areas of a construction project, including piping fabrication, piping erection, steel fabrication, steel erection, tie-in installation, piping hydro testing, equipment erection, painting, insulation, and an overall summary. It includes details on the quantity and man hours for each area, along with the weighting and percentage of progress completed for each. The overall progress across all disciplines for the project is reported as 91.3%.
This document provides progress summaries for multiple project areas of a construction project, including piping fabrication, piping erection, steel fabrication, steel erection, tie-in installation, piping hydro testing, equipment erection, painting, insulation, and an overall summary. It includes details on the quantity and man hours for each area, along with the weighting and percentage of progress completed for each. The overall progress across all disciplines for the project is reported as 91.3%.
Progress Summary by Project Area-Piping Fabrication
Project Quantity Progress Weighting Overall
Man hour Weighting Area (Dia-inch) by Area (Overall) Progress
A 1000 6000 0.43 100% 0.086957 8.7%
B 1500 8000 0.57 100% 0.115942 11.6% Total 2500 14000 1.00 Data from detail Progress Summary by Project Area-Piping Erection tracking sheet
Project Quantity Progress
Man hour Weighting Area (Dia-inch) by Area
A 300 4000 0.40 100% 0.057977 5.8%
B 450 6000 0.60 100% 0.086955 8.7% Total 750 10000 1.00
Progress Summary by Project Area-Steel Fabrication
Project Quantity Progress Man hour Weighting Area (Tonage) by Area A 100 4800 0.61 100% 0.069565 6.9% B 70 3100 0.39 100% 0.044928 4.5% Total 170 7900 1.00
Progress Summary by Project Area-Steel Erection
Project Quantity Progress Man hour Weighting Area (Tonage) by Area A 100 4800 0.61 100% 0.069565 6.9% B 70 3100 0.39 100% 0.044928 4.5% Total 170 7900 1.00 Progress Summary by Project Area-Tie-in Installation Project Progress Qty (Pcs) Man hour Weighting Area by Area A 10 1500 0.45 100% 0.021739 2.2% B 5 1800 0.55 100% 0.026087 2.6% Total 15 3300 1.00 Progress Summary by Project Area-Piping Hydro Testing Project Quantity Progress Man hour Weighting Area (Meter) by Area A 5000 2800 0.44 92% 0.04058 3.7% B 7000 3500 0.56 52% 0.050725 2.6% Total 12000 6300 1.00 Progress Summary by Project Area-Equipment Erection Project Quantity Progress Man hour Weighting Area (Tonage) by Area A 159 1600 0.44 80% 0.023188 1.8% B 168 2000 0.56 89% 0.02898 2.6% Total 327 3600 1.00 Progress Summary by Project Area-Painting Project Quantity Progress Man hour Weighting Area (Tonage) by Area A 300 2000 0.36 36% 0.02898 1.1% B 450 3500 0.64 57% 0.050731 2.9% Total 750 5500 1.00 Progress Summary by Project Area-Insulation Project Quantity Progress Man hour Weighting Area (Tonage) by Area A 2000 4500 0.43 100% 0.065217 6.5% B 3000 6000 0.57 87% 0.086957 7.6% Total 5000 10500 1.00 Progress Summary by Project Area-all disciplines Overall Project Man hour Weighting(Overall) Progress Area by Area A 32000 0.464 43.7% B 37000 0.536 47.6% Total 69000 1.000 91.3%
Developed by Toolbox4Planning Learn more at http://www.toolboxforplanning.com