MONITORING PEKERJAAN REGULATING WEI

VOLUME RENCANA REALISASI


NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
I PEMASANGAN BERONJONG KIRI m3 190.50
II TIMBUNAN COFFERDAM STAGE 2 m3 21,094.28
III GALIAN COFFERDAM STAGE 2 m3 6,420.00
IV PENGECORAN STAGE 2
Block 10 - Block 12
Galian m3 570.40
Pengecoran m3 2,127.38
V PENGECORAN STAGE 2
Block 13 - Block 16
Galian m3 384.30
Pengecoran m3 819.05
VI TIMBUNAN STAGE 2 m3 25,119.74
VII PEMASANGAN BERONJONG KANAN m3 220.00
VII PEMBONGKARAN COFFERDAM STAGE 2 m3 17,976.00
VIII ROAD WORK m2
AN REGULATING WEIR

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
- 12/14/2020 12/28/2020 14
- 12/29/2020 2/27/2021 60
- 1/13/2021 1/27/2021 14
-
-
- 2/28/2021 3/14/2021 14
- 3/15/2021 5/14/2021 60
-
-
- 3/15/2021 3/25/2021 10
- 3/26/2021 5/10/2021 45
- 5/11/2021 7/10/2021 60
- 5/18/2021 6/8/2021 21
- 6/9/2021 7/2/2021 23
- 7/3/2021 8/2/2021 30
MONITORING PEKERJAAN RIVER CHANNEL IMPROV
VOLUME RENCANA REALISASI
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
I GALIAN
Earth Work Sta. 2+010 till Sta. 3+200 m3 40,462.44
II FOOTHPATH m 2400
III WASHING STEP unit 27
IV REPLACEMENT OF BRIDGE Ls 1
ER CHANNEL IMPROVEMENT

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
-
- 2/27/2021 5/28/2021 90
- 3/13/2021 5/27/2021 75
- 3/13/2021 8/10/2021 150
- 3/13/2021 8/10/2021 150
MONITORING PEKERJAAN NO.1 DIVERSION W
VOLUME RENCANA REALISASI
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
I CONCRETE STAGE 1
Crest Bridge unit
Right Concrete Wall m3
Left Wall (LW-1) m3
Intake Culvert m3
Concrete Block m3
II COFFERDAM STAGE 2
Timbunan Stage 2 m3 7,000.00
Galian Stage 2 m3 20,000.00
III CONCRETE STAGE 2
Galian m3 2,345.00
Pengecoran m3 3,630.53
IV BACKFILING m3 10,882.00
VI ROAD WORK m2
N NO.1 DIVERSION WEIR

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
-
-

-
-
-
-
- 12/31/1899 2/14/1900 45
- 2/15/1900 3/17/1900 30
-
- 3/18/1900 4/1/1900 14
- 4/2/1900 7/1/1900 90
- 7/2/1900 8/16/1900 45
- 8/17/1900 9/16/1900 30
MONITORING PEKERJAAN JEMBATAN ATASANG
VOLUME RENCANA REALISASI
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
I ACCESS ROAD m3 7,000.00
II ABUTMENT & PIER WORK
Galian m3 3,300.00
Pengecoran m3 319.74
IV SUPER STRUCTURE
Erection s/d Cor Slab ls 1.00
V RETAINING WALL
Pengecoran m3 442.00
VI EMBANKMENT WORK m3 20,214.00
VII GABION m3 265.00
VIII ROAD WORK m2
JEMBATAN ATASANGIN

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
- 12/8/2020 1/4/2021 27

- 1/5/2021 1/14/2021 9
- 1/15/2021 2/11/2021 27

- 2/12/2021 3/10/2021 26

- 3/11/2021 3/26/2021 15
- 3/11/2021 4/10/2021 30
- 4/11/2021 4/20/2021 9
- 4/21/2021 5/5/2021 14
MONITORING PEKERJAAN HEADPON
VOLUME RENCANA
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES
I GALIAN
A Headpond Wall and Slab M3 5,347.00
IV HEADPOND
A Wall HW 37, 38,39,40
PENGECORAN m3 266.59
B Slab ( HS 9, HS 16, HS 17, HS 8, HS 14, HS 15, HS 20)
PENGECORAN m3 427.00
Wall ( HW 17, HW 18, HW 19, HW 20, HW 21, HW 22,
C
HW 33, HW 34, HW 35, HW 36)
PENGECORAN m3 680.35
EKERJAAN HEADPOND
REALISASI TARGET PEKAN DURASI
DEVIASI DEPAN START FINISH
S/D 13 DES (HARI)
-
- 11/8/2020 12/2/2020 24
-
-
1,000.00 1,000.00 12/5/2020 1/13/2021 39
-
- 12/11/2020 12/25/2020 14
-
- 4/11/2021 5/26/2021 45
MONITORING PEKERJAAN INLET
VOLUME RENCANA REALISASI
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
I INLET BLOCK 1
PENGECORAN m3 750
II INLET BLOCK 2
PENGECORAN m3 3431
III INLET BLOCK 3
PENGECORAN m3 3073
IV INLET BLOCK 4
PENGECORAN m3 3804
V INLET BLOCK 5
PENGECORAN m3 674
KERJAAN INLET

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
-
2/2/2021 5/23/2021 110
-
- 1/5/2021 5/23/2021 138
-
- 12/12/2020 4/26/2021 135
-
- 1/5/2021 5/23/2021 138

2/2/2021 5/23/2021 110


MONITORING PEKERJAAN UPPER PENSTOCK
VOLUME RENCANA REALISASI
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
I GALIAN
A Upperpart Penstock m3 20625
II PENGECORAN
A Right Side Wall m3 1195.38
B Left Side Wall m3 1195.38
C Slab m3 227
D Saddle Pier m3 230
E Anchor Block 1 m3 367
F Anchor Block 2 m3 108
G PAGAR ls 462
AN UPPER PENSTOCK

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
-
- 0
- 0
- 1/6/2021 2/12/2021 37
- 1/6/2021 2/12/2021 37
- 12/23/2020 6/5/2021 164
- 12/18/2020 6/4/2021 168
- 1/15/2021 2/20/2021 36
- 3/30/2021 4/17/2021 18
- 1/19/2021 3/20/2021 60
MONITORING PEKERJAAN UPPE

NO ITEM PEKERJAAN SAT


I PEK. GALIAN TANAH
A Area Sebelum Culvert Bridge m3
B Area Setelah Culvert Bridge m3
II PEK. CULVERT BRIDGE
A GALIAN CULVERT BRIDGE m3
B PENGECORAN m3
LOKASI ANTARA ANCHOR BLOCK 2 - ANCHOR BLOCK 3
III PEK. LEFT RET. WALL ANTARA ANCHOR BLOCK 2 DAN ANCHOR BLOCK 3
A BLOK 5-BLOK 9
PENGECORAN m3
B BLOK 1-BLOK 4
PENGECORAN m3
IV PEK. RIGHT RET. WALL ANTARA ANCHOR BLOCK 2 DAN ANCHOR BLOCK 3
A BLOK 5-BLOK 9
PENGECORAN m3
B BLOK 1-BLOK 4
PENGECORAN m3
V PEK. SLAB DAN STAIR ANTARA ANCHOR BLOCK 2 DAN ANCHOR BLOCK 3
A SLAB 4 - SLAB 6
PENGECORAN m3
B SLAB 1 - SLAB 3
PENGECORAN m3
C STAIR ST 6 - STAIR ST 11
PENGECORAN m3
D STAIR ST 1 - STAIR ST 5
PENGECORAN m3
VI PEK. SADDLE PIER ANTARA ANCHOR BLOCK 2 DAN ANCHOR BLOCK 3
A SADDLE PIER SP 3 - SP 5
PENGECORAN m3
B SADDLE PIER SP 1 - SP 2
PENGECORAN m3
LOKASI ANTARA ANCHOR BLOCK3 - ANCHOR BLOCK 5
I GALIAN TANAH
A GALIAN ANCHOR BLOCK 5 m3
III.A PEK. LEFT RET. WALL ANTARA ANCHOR BLOCK 3 DAN ANCHOR BLOCK 5
A RTW BLOK 1
PENGECORAN m3
IV.A PEK. SLAB DAN STAIR ANTARA ANCHOR BLOCK 3 DAN ANCHOR BLOCK 5
SLAB 4 - SLAB 6
PENGECORAN m3
ADDITIONAL SLAB (T=15 CM)
PENGECORAN m3
V.A PEK. SADDLE PIER ANTARA ANCHOR BLOCK 3 DAN ANCHOR BLOCK 5
SADDLE PIER 6
PENGECORAN m3
V.A PEK. ANCHOR BLOCK 5 (INITIAL CONCRETE)
PENGECORAN m3
ORING PEKERJAAN UPPER PENSTOCK
VOLUME RENCANA REALISASI TARGET PEKAN DURASI
DEVIASI DEPAN START FINISH
TOTAL S/D 13 DES S/D 13 DES (HARI)
-
2,400.00 - 1/6/2021 1/17/2021 12
2,500.00 2/22/2021 3/5/2021 12
-
1,055.00 1,055.00 1,055.00 - - 12/2/2020 12/7/2020 6
218.87 - - - 39.41 12/8/2020 1/23/2021 47
-
-
-
256.23 - - - - 1/18/2021 3/14/2021 56
-
192.42 - - - - 3/15/2021 5/1/2021 48
-
-
256.23 - - - - 1/18/2021 3/14/2021 56
-
192.42 - - - - 3/15/2021 5/1/2021 48
-
-
66.28 - - - - 2/8/2021 2/25/2021 18
-
95.57 - - - - 3/6/2021 3/26/2021 21
-
24.55 - - - - 2/14/2021 3/14/2021 29
-
18.29 - - - - 3/15/2021 4/8/2021 25
-
-
116.28 - - - - 2/8/2020 3/14/2020 36
-
77.52 - - - - 3/15/2020 4/9/2020 26
-
-
1,200.00 - - - 1,200.00 12/14/2020 12/19/2020 6
-
-
51.56 - - - - 12/20/2020 1/22/2021 34
-
-
60.76 - - - - 12/23/2020 1/6/2021 15
-
31.41 - - - - 1/7/2021 1/26/2021 20
-
-
25.94 - - - 12.97 12/17/2020 12/22/2020 6
-
62.73 - - - - 1/23/2021 1/30/2021 8
MONITORING PEKERJAAN POWER HOU
VOLUME RENCANA
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES
I PEK. GALIAN TANAH
1 Elevasi 770.000-763.000 m3 3000.00 3,000.00
2 Elevasi 763.000-758.100 m3 2000.00 -
3 Elevasi 758.100-753.000 m3 5195.00 -
4 Elevasi 753.000-750.500 m3 311.00 -
II SHOTCRETE
1 Elevasi 770.000-763.000 m2 500.00 500.00
2 Elevasi 763.000-758.100 m2 1000.00 -
3 Elevasi 758.100-753.000 m2 750.00 -
4 Elevasi 753.000-750.500 m2 220.00 0
III Substructure Stage 1 (750.500-755.000) Zone 1
PEK. BETON m3 2400.00 0
IV Substructure Stage 2 (755.000-759.300) Zone 1
PEK. BETON m3 1400.00 0
V Substructure Zone 2
PEK. BETON m3 600.00 0
VI Superstructure Zona 1
PEK. BETON m3 1000.00 0
VII Superstructure Zona 2
PEK. BETON m3 1000.00 0
VIII Secondary Concrete for Sub structure Spiral Case 1
PEK. BETON m3 300.00 0
IX Secondary Concrete for Substructure Spiral Case 2
PEK. BETON m3 300.00 0
X Secondary Concrete for Substructure Area
PEK. BETON m3 4000.00 0
XI PEK. TIMBUNAN m3 12000.00 0
XII PEKERJAAN JALAN ls 1.00 0
KERJAAN POWER HOUSE
REALISASI TARGET PEKAN DURASI
DEVIASI DEPAN START FINISH
S/D 13 DES (HARI)
-
- (3,000.00) - 12/8/2020 12/11/2020 4
- - 2,000.00 12/15/2020 12/17/2020 3
- - - 12/24/2020 12/29/2020 6
- - - 12/27/2020 12/27/2020 1
-
- (500.00) - 12/9/2020 12/14/2020 6
- - 650.00 12/16/2020 12/23/2020 8
- - - 12/25/2020 12/30/2020 6
0 - - 12/28/2020 12/29/2020 2
-
0 - - 12/31/2020 2/17/2021 49
-
0 - - 2/18/2021 6/21/2021 124
-
0 - - 4/29/2021 6/27/2021 60
-
0 - - 6/22/2021 8/10/2021 50
-
0 - - 6/22/2021 8/20/2021 60
-
0 - - 10/22/2021 11/10/2021 20
-
0 - - 11/23/2021 12/12/2021 20
-
0 - - 12/13/2021 7/10/2022 210
0 - - 6/22/2021 10/19/2021 120
0 - - 10/20/2021 1/17/2022 90
MONITORING PEKERJAAN TAILRACE CONDUI

VOLUME RENCANA REALISASI


NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
I PEK. GALIAN TANAH
Area BL 1-3 m3 1,500.00 - -
II TAILRACE CONDUIT BL 1 - BL 3
Pengecoran m3 2,109.74 - -
III RETAINING WALL BL 4 - BL 6
Pengecoran m3 717.96 - -
IV PEK. TIMBUNAN m3 4,200.00 - -
VI PEK. STONE PITCHING m2 735.00 - -
VIII PEK. PAGAR m3 110.00 - -
VII PEK. JALAN (GRAVEL SURFACING) m3 118.00 - -

Note:
Pekerjaan Tailrace Conduit bergantung pada pekerjaan galian Powerhouse
N TAILRACE CONDUIT

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
-
1,200.00 12/14/2020 12/23/2020 10
12/24/2020 3/30/2021 97
- - 12/24/2020 3/30/2021 97
3/31/2021 4/29/2021 30
- - 3/31/2021 4/29/2021 30
- - 5/13/2021 5/20/2021 8
- - 12/27/2020 3/26/2021 90
- - 2/10/2021 3/26/2021 45
- - 5/21/2021 5/27/2021 7
MONITORING PEKERJAAN TAILRACE OUTLET
VOLUME RENCANA REALISASI
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
I RIVERSIDE PROTECTION BL 1-3
A PENGECORAN m3 130.89 32.78 32.78
II PEK. GABION m3 59.10 - -
III PEK. PONDASI GABION UJUNG
A PONDASI m3 16.50 - -
B GABION UJUNG m3 80.00 - -
IV PEK. TANGGA kg 2000.00 - -
V PEK. HANDRAIL m 105.00 - -
AN TAILRACE OUTLET

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
- 93
- 12.04 11/14/2020 1/28/2021 75
- 1/29/2021 2/8/2021 10
-
- - 2/9/2021 2/15/2021 6
- - 2/13/2021 2/23/2021 10
- - 12/20/2020 1/19/2021 30
- - 1/20/2021 2/19/2021 30
MONITORING NO.2 SWITCHYARD
VOLUME RENCANA REALISASI
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
I GALIAN
Foundation and Drain Pit m3 6.854
II TIMBUNAN
Foundation and Drain Pit m3 6
III PENGECORAN
Foundation and Drain Pit m3 30
IV PAGAR ls 354
.2 SWITCHYARD

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
-
- 12/12/2020 1/24/2021 43
-
- 12/23/2020 1/28/2021 36
-
- 12/13/2020 1/26/2021 44
- 11/20/2020 1/19/2021 60
MONITORING PEKERJAAN ARSITEK
VOLUME RENCANA REALISASI
NO ITEM PEKERJAAN SAT
TOTAL S/D 13 DES S/D 13 DES
1 Regulating Weir Control House m3 155.00
2 No.1 Diversion Weir Control House m3 155.00
3 No.1 Powerhouse m3 7.00
4 Control Building m3 1,860.00
5 No.1 Switchyard Service House m3 230.00
6 No.1 Switchyard Warehouse m3 94.00
7 No.1 Switchyard Guard House m3 68.00
8 No.2 Diversion Weir Control House m3 155.00
9 No.2 Powerhouse m3 114.00
10 No.2 Powerhouse Warehouse m3 94.00
11 No.2 Switchyard Control House m3 1,130.00
12 No.2 Switchyard Service House m3 140.00
13 No.2 Powerhouse Guard House m3 68.00
14 Right Mooring Warehouses m3 91.00
15 Left Mooring Warehouses m3 91.00
16 Public Lavatories m3 380.00
ERJAAN ARSITEK

TARGET PEKAN DURASI


DEVIASI DEPAN START FINISH
(HARI)
- 12/1/2020 4/29/2021 150
- 6/23/2021 11/19/2021 150
1/2/2022 7/15/2022 195
- 12/14/2020 6/20/2021 189
- 3/7/2021 8/13/2021 160
- 12/7/2020 3/6/2021 90
- 2/1/2021 3/17/2021 45
- 9/1/2020 2/9/2021 162
- 7/22/2021 7/6/2022 350
- 7/22/2021 11/18/2021 120
- 10/1/2020 3/30/2021 181
- 1/3/2021 6/10/2021 159
- 7/22/2021 10/19/2021 90
- 11/21/2020 2/18/2021 90
- 12/25/2020 3/24/2021 90
8/1/2021 4/16/2022 259