Method statement for concrete works.
Pages 1 of 10

METHOD STATEMENT FOR CONCRETE WORKS

PROJECT : (Replace with the project’s name, at location , city name)

CLIENT : (Replace with the client’s name)

MASTER DEVELOPER : (Replace with the master developer’s name)

PMC : (Replace with the PMC’s name)

LEAD CONSULTANT : (Replace with the lead consultant’s name)

SUB-CONSULTANT : (Replace with the sub-consultant’s name)

MAIN CONTRACTOR : (Replace with the main contractor’s name)

SUB-CONTRACTOR : (Replace with the sub-contractor’s name)


TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for concrete works.
Pages 2 of 10

TABLE OF CONTENTS
1. REVISION RECORD........................................................................................................................................3
2. SCOPE / OBJECTIVES....................................................................................................................................4
3. SEQUENCE OF RELATED ACTIVITIES..........................................................................................................4
4. DEFINITIONS / ABBREVIATIONS...................................................................................................................4
4.1. Definition.......................................................................................................................................................4
4.2. Abbreviations................................................................................................................................................4
5. REFERENCES..................................................................................................................................................4
6. RESPONSIBILITIES.........................................................................................................................................5
7. PROCEDURE...................................................................................................................................................5
7.1. Quality Requirements...................................................................................................................................5
7.2. Materials.......................................................................................................................................................5
7.3. Formwork......................................................................................................................................................6
7.4. Reinforcing Steel Work.................................................................................................................................6
7.5. Embedded Items...........................................................................................................................................6
7.6. Joints............................................................................................................................................................6
7.7. Preparation...................................................................................................................................................7
7.8. Concrete Requisition....................................................................................................................................7
7.9. Concrete Placement.....................................................................................................................................7
7.10. Placing of Concrete..................................................................................................................................8
7.11. Finishes....................................................................................................................................................8
7.12. Curing.......................................................................................................................................................8
7.13. Concrete Repair.......................................................................................................................................9
8. RESOURCE REQUIREMENTS........................................................................................................................9
8.1. Manpower.....................................................................................................................................................9
8.2. Material.........................................................................................................................................................9
8.3. Plant & Equipment........................................................................................................................................9
9. HEALTH, SAFETY, ENVIRONMENT (HSE).....................................................................................................9
10. ATTACHMENTS.........................................................................................................................................10
10.1. Inspection Checklists..............................................................................................................................10
10.2. Inspection Test Plan...............................................................................................................................10
10.3. Risk Assessment....................................................................................................................................10
10.4. Technical Data sheet (TDS)...................................................................................................................10
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for concrete works.
Pages 3 of 10

10.5. Material Safety Data Sheet (MSDS).......................................................................................................10

1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions are
hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions

0 First issue

Signature field

Revision
Revision
Number
Date
Prepared by Checked by

Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer ordinator Sub-contractor

Approved
By Project
Manager
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for concrete works.
Pages 4 of 10

2. SCOPE / OBJECTIVES
1. This Method Statement details general procedures to be followed for Concrete Works at Project.
2. This procedure applies to all concrete work of permanent structure except lean concrete to be used as a
structural fill and backfill.

3. SEQUENCE OF RELATED ACTIVITIES


1. Curing
2. Bituminous Protective Painting
3. Back Filling
4. Block Work
5. Finishes

4. DEFINITIONS / ABBREVIATIONS
4.1.Definition
1. Client -(Replace with clients name)
2. Developer -(Replace with developers name)
3. Consultant -(Replace with consultants name)
4. PMC -(Replace with PMC name)
5. Contractor -(Replace with contractors name)

4.2.Abbreviations
1. Engineer- Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MET - Method Statement
8. MIR - Material Inspection Request
9. MSDS - Material Safety Data Sheet
10. PPE -Personal Protective Equipment
11. PQP -Project Quality Plan
12. PTW -Permit To Work ( Working at Height or enclosed spaces)
13. RA -Hazard Identification and Risk Assessment
14. RFIA - Request for Inspection and Approval
15. TBM - Temporary Bench Mark

5. REFERENCES
1. Reference to Contract Documents
1. Specifications-Vol. II Book 1/2 – Division 3 -Concrete
2. Contract Drawings (Architectural and Structural as appropriate)
1. References to Internal Documents
1. Method Statements
2. Material / Mix approvals
3. Project Quality Plan
4. Project HSE Plan
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for concrete works.
Pages 5 of 10

6. RESPONSIBILITIES
1. Project Manager has the overall responsibility for the implementation of this method statement and shall well
ensure that the approved Supplier for Ready Mix Concrete/Independent Testing Agency and Sub-
Contractors as well other team members are aware of the requirements of the Method Statement.
2. Project Manager is responsible to coordinate with the company PRO and the local bodies for obtaining
necessary and essential work permits – if any, for proceeding with the works.
3. Construction Manager/ Project Engineer will ensure that the Resources are available to carry out the works
as scheduled.
4. The Project Engineer/Site Engineer is responsible to carry out the works as per approved Shop Drawings,
Method Statements.
5. The Site Engineer/Supervisor is responsible to ensure that the work has been carried out as per
specifications & drawings and inspections are done as per contract.
6. The Surveyor/Site Engineer/Supervisor is responsible for Setting out the area and measuring, monitoring
and controlling the lines and levels.
7. The QA/QC Engineer/ QC inspector is responsible to ensure that the work performed is in compliance with
the approved method statement & other applicable requirements.
8. The Safety Officer is responsible to ensure that all safety precautions are in place and that the personnel on
site possess the necessary and essential PPE.
9. The Safety Officer is responsible to ensure that essential work permits are available prior to the
commencement of the work.

7. PROCEDURE
7.1.Quality Requirements

1. The works shall be performed as mentioned in this procedure and the quality assurance requirements shall
be consistent with the relevant sections of Quality System Procedure Manual of “Name of the contracting
company” as well with the Project Quality Plan.
2. Quality Control and Tests for concrete shall be as per contract specification.
3. Testing laboratory shall be approved by the Engineer.

7.2.Materials
1. The materials and material manufacturer (Ready Mix Concrete Supplier) covered by this procedure shall be
approved by Engineer prior to the commencement of concreting works in the project
2. Composition of concrete shall comply with that specified in the approved Mix Design. Batching, mixing and
delivering of concrete shall be performed in accordance with the trial mix approved by the Engineer for the
supply of Ready Mix Concrete.
3. Site Engineer/Supervisor has the responsibility of maintaining communication between the point of
placement, the concrete batch plant and with the approved Concrete Testing Laboratory.
4. Cement shall conform to that specified in Section 033000.
5. Aggregate grading shall conform to Section 03300 Part 2, clause 2.01 B of specification. Testing shall be
carried out as specified in clause 1.02 C section 03300 of specification.
6. Water shall conform to Section 03300 Part 2, clause 2.01 D of specification. Source of construction water to
be approved by the Engineer.
7. Concrete admixture for use in concrete shall be approved by the engineer and shall be as per the
requirements of project specifications Volume II- Book 1of2, section 03300 clause no.2.02.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for concrete works.
Pages 6 of 10

7.3.Formwork
(Refer Section 031000 of specification)
1. Form works shall be designed and constructed in accordance with applicable codes within the specified
tolerances to the shape, lines, and dimension required by the design drawings(s).
2. Forms shall be coated with approved mould oil or release agent
3. Form exposed corners to produce smooth, square, solid unbroken lines. Provide chamfers (20mm x 20mm) for
surfaces where indicated on drawings.
4. For slab work, Shore/ support shall be provided for floor directly under slab being placed so that loads from
construction above will safely transfer directly to these shores.
5. Formwork shall be struck without damaging, disturbing, or overloading the structure. The minimum periods for
striking formwork shall be as agreed with Engineer based on the compressive strength results on test cubes.
Calculations for formwork shall be submitted

7.4.Reinforcing Steel Work


(Refer Section 03200 of Specification)
1. Steel reinforcement bars to be used on site shall be from approved source only.
2. Cut and bend steel supplier shall be approved by the Engineer.
3. Re-bar work shall be performed in accordance with the relevant specifications, drawings and as per the bar
bending schedule.
4. Binding of rebar shall be done using annealed wire of 1.6mm dia. (16 gauge)
5. The concrete cover to the reinforcement shall be as per approved drawings.
6. Covers blocks shall be of concrete and of class same as that of the structure.
7. Fabric reinforcement shall be of approved type complying with BS 4483.
8. Welded wire fabric shall be lapped for a minimum length of 300mm including one full mesh for deformed wire
fabric and two full meshes with 50mm overlap for plain wire fabric .Offset end laps in adjacent widths to prevent
continuous laps.
9. The lap length of rebar shall be as per drawings/specifications.
10. Rebar and fabric reinforcement shall be stored under cover on timber or concrete blocks at a minimum height of
300mm above ground.
11. Reinforcement shall be securely fixed in position within a dimensional tolerance of 20mm in any direction parallel
to a concrete face and within a tolerance of 5mm at right angles to a face, provided that cover is not thereby
decreased below the minimum specified or otherwise as shown on drawings.
12. Copy of mill certificate of the consignment shall be attached to material delivery inspection report and submitted
to engineer for approval upon receipt of rebar at site.

7.5.Embedded Items
1. Anchor bolts, Pipe sleeves, Conduits for electrical works, drains, curb and trench angles, and other inserts as
shown on the design drawings shall be placed, secured, and protected during placement of concrete.
2. Engineers of relevant discipline from the Sub-contractor side shall check installation of embedment.

7.6.Joints
(Refer Section 03300 clause 3.07 of specification)
1. Construction joints shall be located as shown on the design drawings. If not shown on the design drawings,
construction joints shall be prepared in accordance with the design document requirements. Construction joint
schedule shall be approved prior to start of work.
2. Vertical Joints shall be formed by means of rigid, grout- tight side forms or stop ends designed to accommodate
projecting reinforcement & horizontal joints shall be level.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for concrete works.
Pages 7 of 10

3. The surfaces of the joints shall be thoroughly roughened, cleaned of all loose and foreign matter and
laitance, washed & saturated with water.
4. Before concreting, joints shall be treated with cement grout or sand and cement grout mixed in the same
proportions as that in concrete. Bonding agent (if instructed by the engineer) shall be applied as per
manufacturer recommendations.
5. The placing of concrete shall be carried out continuously from joint to joint. The face edges of all joints,
which are exposed to view, shall be carefully finished true to line and elevation.
6. Approved water stops shall be provided in construction joints in concrete designed to contain liquids and
where indicated on the drawings.
7. Isolation joints in slabs on grade at all points of contact between slabs on grade and interior column
pedestals and grade beams and elsewhere as indicated.
8. Control joints shall be formed in fresh concrete by either saw cutting or by forming. Depth of joint shall be ¼
slab thickness, unless indicated on drawings.
9. Sliding joints shall be provided, where indicated on drawings, with a preformed slip membrane to ensure
positive separation of concrete surfaces.

7.7.Preparation
1. Areas to be placed with concrete shall be maintained in clean condition, free from trash, debris, sand and other
foreign matters.
2. In hot weather conditions, area to be placed with concrete shall be suitably covered and protected by tarpaulin
sheet placed 20cm above the reinforcement. Water shall be sprayed on forms, reinforcement and base prior to
pouring the concrete.
3. Prior to placing, following items shall be checked by respective site supervisor:
1. Survey check review: deviation of line, grade, plumb and location of embedment.
2. Final clean up.
3. Joint preparation.
4. Dampness of surface to receive concrete
5. “Name of the contracting company” Site Engineer shall initiate Concrete pour record & Inspection
Request.

7.8.Concrete Requisition
1. After visual inspection by Engineer and approval of IR, Project Engineer/Site Engineer shall initiate requisition to
the Ready mix Concrete Supplier.

7.9.Concrete Placement
1. Field Checks
2. Upon arrival of transit mix truck at site the delivery note will be checked for the actual details like time of
batching, quantity, mix type, approved mix design, variation in weighing of materials, water cement ratio & slump
checked regularly to the satisfaction of the Engineer.
3. Concrete Temperature shall be measured using Thermometer and the maximum allowable temperature of
concrete shall be 32 degree centigrade.
4. One set of six (6) cubes for each 75 cum. Or fraction thereof of each concrete class placed in any one day or for
each 450 sq.mtr of surface area placed.
5. One specimen shall be tested at 7 days and 4 specimens shall be tested at 28 days. One specimen shall be
retained in reserve for later testing, if required. Two specimens tested at 28 days shall be field cured. All others
shall be laboratory cured.
6. Slump test shall be carried out for each concrete load at point of discharge and one for each set of compressive
strength test specimen.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for concrete works.
Pages 8 of 10

7. Air content test as per BS 1881 part 106, pressure method; shall be carried out one test for each set of
compressive strength test specimen.
8. Durability test for concrete shall be done as required in section 03300, table 2.08C as and when directed by the
engineer.
7.10. Placing of Concrete
No concrete shall be placed during sand storm or rain.
1. No water shall be added to the mixer truck after batching.
2. “Name of the contracting company” Site Engineer shall take immediate steps to notify the Engineer when a
cold joint is imminent and shall assure that the required method of correcting it is adopted as detailed on the
drawings.
3. Pump car, bucket and chute will be used as placing equipment as appropriate.
4. Chutes shall be used for drop of concrete greater than 1.0mtr in case of thin walls and 2 meter in other work.
In case of slab work it shall be 250-500mm.The slope of chutes should be constant and steep enough to
permit concrete to flow continuously down the chute without segregation(1:2 or 2.5 slope)
5. Concrete shall be deposited in horizontal layers to a compacted depth not exceeding 450mm and in a
manner to avoid inclined construction joints.
1. Procedure for compaction of concrete (Refer Clause 3.04 D section 03300 of specification)
1. Concrete shall be consolidated by mechanical vibrators. The vibrators shall be adequate in number of units
and power of each unit to properly consolidate all concrete.
2. In consolidating each layer of concrete, the vibrator shall be operated in a near vertical position, and the
vibrating head shall be allowed to penetrate under the action of its own weights. Vibrator shall be allowed to
remain inside the concrete for sufficient time to obtain proper consolidation of concrete.
3. The vibrator should penetrate rapidly to the bottom of the layer and at least 4 inch into the preceding layer.
4. Vibrators shall not be used to move or spread concrete.
5. Concrete shall be placed as soon as practicable after mixing and while sufficiently plastic for full compaction.
6. Concreting during hot weather (Temperature greater than 40 deg. Centigrade) shall be avoided as much as
possible to prevent the occurrence of severe thermal effects.
7. After concrete placing, “Name of the contracting company” Site engineer/Supervisor shall record relevant
details on the format ‘Concrete Pour Record’ in presence of Engineer.

7.11. Finishes
1. Concrete finishes shall be as required in specification volume II-book 1of2 section 03300, clause 3.05 and
3.06 and shall be free from voids, honey combing or any other defects.
2. All concrete shall be power floated to produce smooth even finish unless otherwise specified. Hand
trowelling shall be carried out to surfaces of footings, beams etc.

7.12. Curing
(Refer Section 03300 Clause 3.08 of specification)
1. During and after placement, concrete and the exposed surface of fresh concrete shall be protected from
wind, high temperature and rain. Curing shall start as soon as free water has disappeared from the concrete
surface after placing and finishing. Concrete surface shall be initially covered by only polythene sheet. Then
after required hardening, place the wet hessian cloth and cover with polythene sheet.
2. Concrete shall be cured for a minimum of 7 days. Curing compound, if used, shall be approved by the
Engineer.

7.13. Concrete Repair


1. Repair method of defective concrete shall be determined or selected by Consulting Engineer or in
accordance with the disposition of issued Non Conformance Report.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for concrete works.
Pages 9 of 10

2. Repair shall not be carried out without written instruction/ approval of Engineer.

8. RESOURCE REQUIREMENTS
8.1.Manpower
1. - Site Engineer 2. - Carpenters
3. - Supervisor 4. - Steel Fixer
5. - QA/QC Engineer 6. - Helpers (skilled, semi-skilled)
7. - Masons

8.2.Material
1. - Formwork material (ply board, soft wood, nails, Tie Rods, Clamps)
2. - Mould Release Oil
3. - Rebar / Spacers /Binding Wire
4. - Polythene Sheet / Hessian Cloth
5. - Concrete as per specifications
6. - Concrete Repair materials
8.3.Plant & Equipment
1. - Transit Mixers 2. - Slump Cone, Air Meter
3. - Concrete Pump 4. - Thermometer
5. - Water Tanks 6. - Measuring Jar
7. - Air Compressor 8. - Crane & Skip
9. - Mechanical Vibrator 10. - Theodolite/Total station
11. - Masonry tools (trowels & hand tools) 12. - Dumpy Level
13. - Wheel Barrows 14. - Water Level
15. - Cube Moulds 16. - Spirit Level, Right Angle, Plumb Bob
17. - Tamping Rod 18. - Hammer
9. HEALTH, SAFETY, ENVIRONMENT (HSE)
1. The entire works will be carried out as per the guidelines established in the Project Specific HSE Plan.
2. Utmost importance shall be given to safety of personnel and protection of existing above /underground services.
It will be ensured that the personnel involved are thoroughly aware of the “Name of the contracting company”/
Employer Safety regulations. To achieve the above the following shall also be ensured:
3. Tool Box Meetings will be conducted before starting the works.
4. All personnel will be provided with suitable Personal Protective Equipment.
5. Required permits will be obtained from the Engineer/ authorities concerned before starting the works.
6. Plant & Equipment’s shall be fully tested & certified by an independent testing agency. Copies of certificates shall
be submitted to Engineer
7. All pneumatic / lifting equipment’s including booms, slings; chain blocks etc. shall be fully tested & certified by an
independent testing agency. Copies of certificates should be available.
8. The following checks will be done as required:
9. Rigidity of connections in case of booms of the pneumatic pumps
10. Check if the grease applied to the wearing parts is adequate.
11. Check against slippage/breakage of the concrete pumps boom from the sleeves/connections while working.
12. Check whether the end of the hose has become loose or has slipped from connecting clamps
13. Check for loose strands of wear, deformation, corrosion and Breakage of parts of the pump.
14. Check all forms, shuttering’s and bracings are adequate to support the concrete loads and as per the approved
design.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for concrete works.
Pages 10 of 10

10. ATTACHMENTS
10.1. Inspection Checklists
10.2. Inspection Test Plan
10.3. Risk Assessment
10.4. Technical Data sheet (TDS)
10.5. Material Safety Data Sheet (MSDS)