LOCATION
(1st Floor)
Floor : Conductive PVC Tile, Epoxy Paint, Floor Hardener
Wall : LGS gypsum board and ALC Wall
Ceiling : Gyptile with T-Bar System, GRC Board, Expose Ceiling
Interior
(2nd Floor)
Floor : No Finishing
Wall : ALC Wall with Plaster
ROAD: Heavy duty concrete road t:200mm & Heavy duty asphalt Pavement
External Work
DRAINAGE: Open Concrete Ditch & Concrete Pipe
Building Works
External Works
Mechanical Works
Electrical Works
Construction Manager PT. SIIX EMS INDONESIA
Masanobu ITOGAWA (OWNER)
0811 868 444
Drafter
Ghofur
0813 8081 9965
Project Site
Project Manager
Masaki ONO
0811 1988 691
Site Engineer
Parlin
0812 8100 2125
Safety and
Drafter Site Engineer
Mat. Control
Kuswanto Sodilin
Denny
0852 8239 1810 0815 9360 366
0813 4367 3284
Site Engineer Safety Officer
M. Arif Yoyok
0819 0721 0022 0821 3916 5529
SUBCONTRACTOR
PT. Hazama Ando Murinda – 12.08.2020
CONSTRUCTION MASTER SCHEDULE HAZAMA ANDO CORPORATION
ID Task Name 期間 開始日 終了日
2021年
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
1 PT. SIIX EMS INDONESIA FACTORY 395 days 金)20/08/07 ( 木)21/09/09 ( PT. SIIX EMS INDONESIA FACTORY EXPANSION PROJECT
EXPANSION PROJECT 08/07 09/09
2 QUATION AND CONTRACT 1 day 金)20/08/07 ( 金)20/08/07 ( QUATION AND CONTRACT
08/07 08/07
3 CONTRACT 1 day 金)20/08/07 ( 金)20/08/07 ( CONTRACT
08/07 08/07
4 DESIGN AND APPLICATION 111 days 金)20/08/07 ( 水)20/11/25 ( DESIGN AND APPLICATION
08/07 11/25
5 COSTRUCTION PERMIT APPLICATION 19 days 金)20/08/07 ( 火)20/08/25 (STRUCTION PERMIT APPLICATION DRAWING AND DOCUMENT
DRAWING AND DOCUMENT 08/07 08/25
6 SUBMIT APPLICATION (IBM) 2 days 水)20/08/26 ( 木)20/08/27 ( SUBMIT APPLICATION (IBM)
08/26 08/27
7 APPROVAL 90 days 金)20/08/28 ( 水)20/11/25 ( APPROVAL
08/28 11/25
8 COSTRUCTION WORK 382 days 木)20/08/20 ( 木)21/09/09 ( COSTRUCTION WORK
08/20 09/09
9 PREPARATION 40 days 木)20/08/20 ( 月)20/09/28 ( PREPARATION
08/20 09/28
10 SITE GRABBING AND SURVEY WORK 40 days 木)20/08/20 ( 月)20/09/28 ( SITE GRABBING AND SURVEY WORK
08/20 09/28
11 TEMPORARY FACILITY WORK 40 days 木)20/08/20 ( 月)20/09/28 ( TEMPORARY FACILITY WORK
08/20 09/28
12 TEMPORARY WORK 156 days 土)20/09/26 ( 日)21/02/28 ( TEMPORARY WORK
09/26 02/28
13 TOWER CRANE 156 days 土)20/09/26 ( 日)21/02/28 ( TOWER CRANE
09/26 02/28
14 PILLING WORK(523p) 40 days 火)20/09/01 ( 土)20/10/10 ( PILLING WORK(523p)
09/01 10/10
15 STRUCTURE WORK 186 days 土)20/09/26 ( 火)21/03/30 ( STRUCTURE WORK
09/26 03/30
16 FOUNDATION WORK 60 days 土)20/09/26 ( 火)20/11/24 ( FOUNDATION WORK
09/26 11/24
17 AREA 1 Grid 9 to 13 123 days 金)20/10/16 ( 月)21/02/15 ( AREA 1 Grid 9 to 13
10/16 02/15
18 1ST FLOOR GRABBING AND LEAN 10 days 金)20/10/16 ( 日)20/10/25 ( 1ST FLOOR GRABBING AND LEAN CONCREAT
CONCREAT 10/16 10/25
19 1F RC COLUMN WORK (36p) 15 days 月)20/10/26 ( 月)20/11/09 ( 1F RC COLUMN WORK (36p)
10/26 11/09
20 2F SLAB WORK 40 days 火)20/11/10 ( 土)20/12/19 ( 2F SLAB WORK
11/10 12/19
21 2F RC COLUMN WORK 15 days 日)20/12/20 ( 日)21/01/03 ( 2F RC COLUMN WORK
12/20 01/03
22 RF BEAM 14 days 月)21/01/04 ( 日)21/01/17 ( RF BEAM
01/04 01/17
23 DISMANTLE SUPPORT FOR FORM 14 days 火)21/01/19 ( 月)21/02/01 ( DISMANTLE SUPPORT FOR FORM WORK
WORK 01/19 02/01
24 1F SLAB WORK 14 days 火)21/02/02 ( 月)21/02/15 ( 1F SLAB WORK
02/02 02/15
25 AREA2 Grid 13 to 17 146 days 木)20/11/05 ( 火)21/03/30 ( AREA2 Grid 13 to 17
11/05 03/30
26 1ST FLOOR GRABBING AND LEAN 10 days 木)20/11/05 ( 土)20/11/14 ( 1ST FLOOR GRABBING AND LEAN CONCREAT
CONCREAT 11/05 11/14
27 1F RC COLUMN WORK 15 days 日)20/11/15 ( 日)20/11/29 ( 1F RC COLUMN WORK
11/15 11/29
28 2F SLAB WORK 40 days 月)20/11/30 ( 金)21/01/08 ( 2F SLAB WORK
11/30 01/08
29 2F RC COLUMN WORK 15 days 土)21/01/09 ( 土)21/01/23 ( 2F RC COLUMN WORK
01/09 01/23
30 RF BEAM 14 days 日)21/01/24 ( 土)21/02/06 ( RF BEAM
01/24 02/06
31 DISMANTLE SUPPORT FOR FORM 14 days 月)21/02/08 ( 日)21/02/21 ( DISMANTLE SUPPORT FOR FORM WORK
WORK 02/08 02/21
32 1F SLAB WORK 14 days 月)21/02/22 ( 日)21/03/07 ( 1F SLAB WORK
02/22 03/07
33 STRUCTURE WORK OF AFTER TAKE OFF 30 days 月)21/03/01 ( 火)21/03/30 ( STRUCTURE WORK OF AFTER TAKE OFF TOWER CRANE
TOWER CRANE 03/01 03/30
34 AREA3 Grid 17 to 21(736m3) 123 days 水)20/11/25 ( 土)21/03/27 ( AREA3 Grid 17 to 21(736m3)
11/25 03/27
35 1ST FLOOR GRABBING AND LEAN 10 days 水)20/11/25 ( 金)20/12/04 ( 1ST FLOOR GRABBING AND LEAN CONCREAT
CONCREAT 11/25 12/04
36 1F RC COLUMN WORK 15 days 土)20/12/05 ( 土)20/12/19 ( 1F RC COLUMN WORK
12/05 12/19
37 2F SLAB WORK 40 days 日)20/12/20 ( 木)21/01/28 ( 2F SLAB WORK
12/20 01/28
38 2F RC COLUMN WORK 15 days 金)21/01/29 ( 金)21/02/12 ( 2F RC COLUMN WORK
01/29 02/12
39 RF BEAM 14 days 土)21/02/13 ( 金)21/02/26 ( RF BEAM
02/13 02/26
40 DISMANTLE SUPPORT FOR FORM 14 days 日)21/02/28 ( 土)21/03/13 ( DISMANTLE SUPPORT FOR FORM WORK
WORK 02/28 03/13
41 1F SLAB WORK 14 days 日)21/03/14 ( 土)21/03/27 ( 1F SLAB WORK
03/14 03/27
42 RF STEEL STRUCTURE TRUSS 60 days 月)21/01/18 ( 木)21/03/18 ( RF STEEL STRUCTURE TRUSS WORK
WORK 01/18 03/18
43 INTERIOR WORK 179 days 火)21/02/02 ( 火)21/08/03 ( INTERIOR WORK
02/02 08/03
44 1F INTERIOR WORK 130 days 火)21/03/16 ( 火)21/07/27 ( 1F INTERIOR WORK
03/16 07/27
45 INTERIOR WORKS(CEILING, WALL, 130 days 火)21/03/16 ( 火)21/07/27 ( INTERIOR WORKS(CEILING, WALL, JOINERY, FLOOR)
JOINERY, FLOOR) 03/16 07/27
46 2F INTERIOR WORK 107 days 木)21/04/08 ( 火)21/07/27 ( 2F INTERIOR WORK
04/08 07/27
47 INTERIOR WORKS(Modify Structure) 107 days 木)21/04/08 ( 火)21/07/27 ( INTERIOR WORKS(Modify Structure)
04/08 07/27
48 HAND OVER CLEANING 7 days 水)21/07/28 ( 火)21/08/03 ( HAND OVER CLEANING
07/28 08/03
49 EXTERIOR FINISHING WORK 131 days 火)21/02/02 ( 水)21/06/16 ( EXTERIOR FINISHING WORK
02/02 06/16
50 ROOF METAL SHEET WORK 50 days 火)21/03/09 ( 火)21/04/27 ( ROOF METAL SHEET WORK
03/09 04/27
51 EXTERIOR WALL FINISHING WORK 120 days 火)21/02/02 ( 土)21/06/05 ( EXTERIOR WALL FINISHING WORK
02/02 06/05
52 JOINERY WORK 50 days 火)21/04/13 ( 土)21/06/05 ( JOINERY WORK
04/13 06/05
53 DOWN SPOUT WORK 30 days 月)21/05/03 ( 土)21/06/05 ( DOWN SPOUT WORK
05/03 06/05
54 TAKE OFF SCAFFOLDING WORK 25 days 日)21/05/23 ( 水)21/06/16 ( TAKE OFF SCAFFOLDING WORK
05/23 06/16
55 EXTERNAL WORK 75 days 火)21/05/18 ( 土)21/07/31 ( EXTERNAL WORK
05/18 07/31
56 RAIN WATER DRAINAGE WORK 45 days 火)21/05/18 ( 木)21/07/01 ( RAIN WATER DRAINAGE WORK
05/18 07/01
57 ROAD WORK 50 days 土)21/06/12 ( 土)21/07/31 ( ROAD WORK
06/12 07/31
58 CAR PARK WORK 50 days 土)21/06/12 ( 土)21/07/31 ( CAR PARK WORK
06/12 07/31
59 ELECTRICAL WORK 265 木)20/11/05 ( 土)21/07/31 ( ELECTRICAL WORK
days 11/05 07/31
60 POWER ON 1 day 火)21/06/01 ( 火)21/06/01 ( POWER ON
06/01 06/01
61 PLUMBING WORK 265 days 木)20/11/05 ( 土)21/07/31 ( PLUMBING WORK
11/05 07/31
62 AIR AND VENTILATION WORK 134 days 火)21/03/16 ( 土)21/07/31 ( AIR AND VENTILATION WORK
03/16 07/31
63 INTERNAL INSPECTION / DEFECT 14 days 水)21/08/04 ( 火)21/08/17 ( INTERNAL INSPECTION / DEFECT REPAIR
REPAIR 08/04 08/17
64 CLIENT INSPECTION 3 days 月)21/08/23 ( 水)21/08/25 ( CLIENT INSPECTION
08/23 08/25
65 DEFECT REPAIR 14 days 木)21/08/26 ( 水)21/09/08 ( DEFECT REPAIR
08/26 09/08
66 HANDOVER BUILDING 1 day 木)21/09/09 ( 木)21/09/09 (
Project: 東プレ概略工程表(21-10)1月末 Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Progress
Date: 20/08/28 (金) Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Deadline
Page 1
100
100%
97.8
90%
89.6
80%
78.8
70%
67.1
60%
57.4
50%
47.6
40%
38.3
schedule 31.7%
30%
actul 31.7%
25.9
20.6
20%
14.7
10%
7.9%
2.3% 0%
REVISION
NO. DESCRIPTION SIGN DATE
FABRICATION
OUTSIDE SCAFFOLDING
CIVIL
K
6000
M&E FOUNDATION
FL.+0.200
M&E FOUNDATION M&E FOUNDATION
FL.+0.200 FL.+0.200
STOCK AREA
M&E FOUNDATION
FL.+0.200
MATERIAL
APAR
8000 8000 8000 8000 8000 8000 8000 8000
APAR
I
00
24000
700
EXISTING SOIL DRAINAGE
H 2000 APAR m
NEW BRC FENCE
F
STEEL MATERIAL
& REMOVE
4000
STOCK AREA
24000
20
19
18
17
16
15
14
E
13
12
11
PILE MACHINE
10
09
08
07
06
05
04
R19349
03
02
01
D
OUTSIDE
16000
C SCAFFOLDING
8 40
R9
B
6000
M&E FOUNDATION
FL.+0.200
A SCAFFOLDING APAR
22033
CAR PARKING
M&E SAFETY MORNING AREA SITE OFFICE AREA
WASHING
-
BANNER FENCE PUBLIC ROAD
PT. HAZAMA ANDO MURINDA
12070 3850 WORKER BANNER FENCE MIDPLAZA 1 BUILDING 16th FLOOR
TRAINING SUBCON IN EXISTING BRC FENCE TEMPORARY FENCE Jl. Jendral Sudirman Kav. 10-11 Jakarta 10220, INDONESIA
Tel :(021) 5735 774 (Hunting) Fax :(021) 5735 737
OFFICE
PROJECT
20000 17500 5500 9000 25050 3000 10500 2500 26000 11550 PHASE-1 = 80000 19500
3000 PT. SIIX EMS INDONESIA
58104 10000 90600 EXISTING SUB STATION
1 EXPANSION FACTORY PROJECT
3 EXISTING SECURITY POS TEMPORARY GATE ACCESS
SAFETY CONE 19 9
DRAWING TITLE
SCALE 1:1000
LEGEND :
SIGNATORIES
TAMPORARY BANNER FENCE WORKER TOILET OUT SIDE SCAFFOLDING TEMPORARY DRAINAGE
RAINY SEASON DESCRIPTION SIGNATURE DATE
TAMPORARY METAL FENCE
HANDRAIL TEMPORARY ROAD FABRICATION AREA WATER SUPPLY POINT APPROVED BY Mr. Itogawa
500MM THK. LIME STONE
STEEL PLATE BRIDGE CHECKED BY Mr. Ono
TEMPORARY PARKING TEMPORARY LIGHTING
100MM THK. BASE COURSE MATERIAL STOCK
CHECKED BY Parlin
SITE OFFICE TEMPORARY WALK WAY TEMPORARY ELECTRICAL LINE
NEW WORKER TRAINING & LOAD PANEL CAD BY Kuswanto 07 OKT 20
WIDTH 1m
NO HELMET WALK WAY HANDWASHING
5 APAR LOCATION
PROJECT CODE DRAWING NO. SHT. NO.
SIIX-2020 T-01 -
D:\00. PT. HAZAMA ANDO MURINDA\29. PT. SIIX EMS INDONESIA\PT. SIIX INDONESIA\TEMPORARY WORK\T-01 - TEMPORARY OFFICE - R6 - 07-10-2020.dwg
REVISION
NO. DESCRIPTION SIGN DATE
0m
20600
20.6 m
TOWER CRANE
22 m
25 m
27 m
30 m
32 m
35 m
40 m
42 m
45 m
47 m
50 m
52 m
55 m
57 m
60 m
62 m
65 m
67 m
70 m
DISTANCE LOAD
70000 RADIUS
9.53 t
8.67 t
6.24 t
5.64 t
4.93 t
4.58 t
4.37 t
4.07 t
3.89 t
3.65 t
3.17 t
11.1 t
6000
7.6 t
5.2 t
3.3 t
3.5 t
12 t
STANDARD LOAD
6 t
3 t
7 t
2400
9.6 t
8.9 t
7.6 t
6.9 t
6.1 t
5.6 t
5t
4.8 t
4.5 t
4.2 t
3.9 t
3.7 t
3.5 t
3.3 t
3.1 t
2.92 t
2.8 t
2.64 t
2.54 t
2.4 t
HAZAMA LOAD
3350
8800
FL.+11.665
CLEAR H=23000
FL.+10.705
FL.+10.065
C1
11655
INSIDE FACTORY FL.+5.000
10470
FENCE
FENCE PUBLIC
FENCE INSIDE FACTORY ROAD
FL.±0.000
BOUNDARY LINE
FL.-0.350
BOUNDARY LINE
6000 8000 8000 8000 8000 8000 8000 8000 8000 6000
5359 9475 76000 16834
-
107668
PT. HAZAMA ANDO MURINDA
MIDPLAZA 1 BUILDING 16th FLOOR
J J I H G F E D C B A Jl. Jendral Sudirman Kav. 10-11 Jakarta 10220, INDONESIA
Tel :(021) 5735 774 (Hunting) Fax :(021) 5735 737
PROJECT
TOWER CRANE LOAD DIAGRAM -
SCALE 1 : 425 - PT. SIIX EMS INDONESIA
EXPANSION FACTORY PROJECT
DRAWING TITLE
SIGNATORIES
DESCRIPTION SIGNATURE DATE
CHECKED BY Parlin
SIIX-2020 T-16 -
D:\00. PT. HAZAMA ANDO MURINDA\29. PT. SIIX EMS INDONESIA\PT. SIIX INDONESIA\TEMPORARY WORK\T-13 - TEMPORARY TOWER CRANE FOUNDATION.dwg
REVISION
10000 10000 10000 10000 9257 10743 10000 10000 10000 10000 10000 7500 2500 10000 10000
4000 16000 10000 10000 9670 2830 7500 24000 2700 13300
INSIDE STAIR-6
II III B TO 2ND FLOOR
EMERGENCY STAIR-2 (STEEL STAIR)
COOLING
K TOWER FL.+0.300 FL.+0.300 FL.+0.300
6000
M&E FOUNDATION M&E FOUNDATION
I
FL.+0.200 FL.+0.200
M F 2.0 ton/m2
STORAGE-1 FL±0,00
10000 FLOOR FINISH: CONDUCTIVE PVC TILE
I 1500 NO CEILING
CARGO LIFT (FUTURE) 2750 LOAD: 1.0 ton/m2
24000
140
ANTE 4000
SS-1
20000
RM
8000
G FUTURE RM
HSS-1 FL±0,00
FL±0,00
20
19
FLOOR FINISH:
18
FL±0.000
17
16
FLOOR FINISH:
15
14
13
12
11
PROJECT
8000
C
5 DRAWING TITLE
8000
ELECTRICAL RM-1
FL.+0.200
6000
6000
AHU-1 M F
7000
FUTURE WALL 8000 4000 8000 12500 10000 7500 8000 15500 4000 10000 FUTURE WALL APPROVED BY Mr. Ono
INSIDE STEEL STAIR-4
INSIDE STEEL STAIR-3 II STAIR-1 A TO 2ND FLOOR III STAIR-2 CHECKED BY Parlin
TO 2ND FLOOR FLOOR FINISHING:
INSIDE STAIR-5 CHECKED BY
120000 FLOOR HARDENER
TO 2ND FLOOR
PHASE-2 CAD BY Kuswanto 16-NOV-20
CONDUCTIVE PVC TILE
EXPANSION FACTORY PLAN (1st FLOOR PLAN) - CONDUCTIVE EPOXY PAINT
PROJECT CODE DRAWING NO. SHT. NO.
SCALE 1 : 500 -
NO FLOOR FINISH
SIIX EMS-2020 A-GA-02 -
D:\00. PT. HAZAMA ANDO MURINDA\29. PT. SIIX EMS INDONESIA\PT. SIIX INDONESIA\SHOP DRAWING\00. GA\A-GA-00 - ARCHITECTURE\A-GA-01~03 PLAN.dwg
REVISION
EXPANSION FACTORY EXISTING FACTORY NO. DESCRIPTION SIGN DATE
10000 10000 10000 10000 10000 10000 10000 10000 10000 10000 10000 7500 2500 10000 10000
6000
I II III 1.0 ton/m2 1.0 ton/m2 M F 1.0 ton/m2
2500
J C4
3625 3675
DOWN TO 1F UP TO ROOF DOWN TO 1F
8000
CANOPY ROOF
10000
I 1
C4
H C4
20000
8000
G C4
C4
3 PHASE-1
PHASE-2
64000
FL.+5.000
26 DN
25
24
24000
23
22
8000
21
NO FINISHING FLOOR
20
EMERGENCY
19
18
17
16
15
STAIR-1 NO CEILING
14
13
E C4
8000
D C4
SHOP DRAWING
8000
V V CANTILEVER Tel :(021) 5735 774 (Hunting) Fax :(021) 5735 737
8000
SLAB PROJECT
INSIDE STAIR INSIDE STAIR
TO 1ST FLOOR SS-2 TO 1ST FLOOR 1 SS-2 PT. SIIX EMS INDONESIA
w.5000xh.3000 w.5000xh.3000
B DN
C4
EXPANSION FACTORY PROJECT
DN
CHILLER M F ELECTRICAL RM AHU
6000
6000
6000
I AHU AHU 1.0 ton/m2 1.0 ton/m2
1.0 ton/m2 1.0 ton/m2 DRAWING TITLE
1.0 ton/m2
A DN EXPANSION FACTORY PLAN
(2nd FLOOR PLAN)
II III
CANTILEVER 1 INSIDE STAIR
STAIR-2
STAIR-1 SLAB TO 1ST FLOOR SCALE : 1:500
180
30000 8000 4000 8000 12500 10000 7500 8000 15500 4000 10000 2500 SIGNATORIES
120000
OUT SIDE IN SIDE DESCRIPTION SIGNATURE DATE
PHASE-2
LINTLE COLUMN SHUTTER DOOR APPROVED BY Mr. Ono
FLOOR FINISHING: 200 STEEL ANGLE
EXPANSION FACTORY PLAN (2nd FLOOR PLAN) - FL.+5.000 CHECKED BY Parlin
SCALE 1 : 500 - SLOPE
NO FINISHING CHECKED BY
10
CAD BY Kuswanto 19-SEP-20
2 CONCRETE BEAM
SECTION-V - 265 135 PROJECT CODE DRAWING NO. SHT. NO.
SCALE 1 : 20 -
A SIIX EMS-2020 A-GA-03 -
Z:\KIIC AREA\PT. SIIX INDONESIA\SHOP DRAWING\00. GA\A-GA-00 - ARCHITECTURE\200919\A-GA-01~03 PLAN.dwg
REVISION
NO. DESCRIPTION SIGN DATE
0 1ST ISSUED 07AUG20
1 REVISION - 1 12SEP20
I II III B
9'
21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
200000
120000
30000 90000 80000
10000 10000 10000 10000 10000 10000 10000 10000 10000 10000 10000 7500 10000 10000 10000 10000 10000 10000 10000 10000
ROOF: CORRUGATED METAL SHEET
w/ GLASS WOOL INSULATION 2500
SLOPE 1/25 (4%)
20000 4000 16000
K 1 1
6000
CT
2500
J DN
8000
CANOPY
I
24000
8000
1
H
20000
8000
C
G
8000
64000
F 10000
24000
8000
PHASE-2 PHASE-1
E
EMERGENCY
8000
STAIR-1
D SHOP DRAWING
PT. HAZAMA ANDO MURINDA
8000
16000
C
MIDPLAZA 1 BUILDING 16th FLOOR
Jl. Jendral Sudirman Kav. 10-11 Jakarta 10220, INDONESIA
Tel :(021) 5735 774 (Hunting) Fax :(021) 5735 737
8000
PROJECT
B PT. SIIX EMS INDONESIA
6000
960
FL.+9.825 1 REVISION - 1 12SEP20
2160
C1
1200
C1
960
TOC.+9.505 FL.+9.505
TOC.+8.865 TOC.+8.865 TOC.+9.065 DOWN
4505
4505
3865
PIPE
11665
FL.+5.000 FL.+5.000 FL.+5.000
CH.+3.000
PARTITION
1
5000
5000
PARTITION PARTITION PARTITION PARTITION PARTITION WALL
WALL WALL WALL WALL WALL
FL.±0.000 FL.±0.000 FL.±0.000
5000 3000
DRAINAGE 6000 8000 8000 8000 8000 8000 8000 8000 8000
70000 8000
DRAINAGE
A B C D E F G H I J
SECTION III - III -
SCALE 1 : 300 - FL.+11.665 ROOF: CORRUGATED SLOPE
4% 4%
- SLOPE 1 METAL SHEET 1
FL.+10.065 25 25 FL.+10.705
960
FL.+9.825
2160
1200
960
TOC.+9.505 FL.+9.505
TOC.+8.865 TOC.+8.865 TOC.+9.065
4505
4505
3865
CONC. PARTITION
STAIR
11665
FL.+5.000 FL.+5.000 WALL FL.+5.000
28
1200
25
21 CH.+3.000
FL.+5.000 17
5000
3800
11
WALL WALL WALL WALL WALL WALL WALL
3000
7
FL.±0.000 3 FL.±0.000 FL.±0.000
6000 8000 8000 8000 8000 8000 8000 8000 8000 DRAINAGE
DRAINAGE
70000 8000
TOILET WALL SHOP DRAWING
A B C D E F G H I J
PT. HAZAMA ANDO MURINDA
SECTION II - II - 4% FL.+11.665 ROOF: CORRUGATED SLOPE MIDPLAZA 1 BUILDING 16th FLOOR
SCALE 1 : 300 - SLOPE 1 METAL SHEET 1 4% Jl. Jendral Sudirman Kav. 10-11 Jakarta 10220, INDONESIA
Tel :(021) 5735 774 (Hunting) Fax :(021) 5735 737
25 25 FL.+10.705
960
1013
PROJECT
FL.+10.065
1000
PT. SIIX EMS INDONESIA
1000
1000
C4
FL.+9.705 EXPANSION FACTORY PROJECT
FL.+9.065
4705
4065
DRAWING TITLE
10652
9705
11665
FL.+5.000 FL.+5.000 FL.+5.000 SECTION I, II, & III
10065
9705
9065
5000
3500
STORAGE-2 SIGNATORIES
FL.±0.000 FL.±0.000 FL.±0.000 DESCRIPTION SIGNATURE DATE
B C D E F G H I J
PROJECT CODE DRAWING NO. SHT. NO.
SECTION I - I -
SCALE 1 : 300 SIIX EMS-2020 A-GA-05 -
Z:\KIIC AREA\PT. SIIX INDONESIA\SHOP DRAWING\00. GA\A-GA-00 - ARCHITECTURE\200919\A-GA-05 SECTION.dwg
REVISION
ROOF: CORRUGATED METAL SHEET
SLOPE 4% 1 1 SLOPE 4% ALC WALL NO. DESCRIPTION SIGN DATE
T.O.C 25 25 T.O.C 0 1st ISSUED 07AUG20
FL+10,705 FL+10,065
1000
1 REVISED-1 12SEP20
1000
2nd FL 2 2nd FL
5000 4705
5000 4065
FL+5,000 FL+5,000
10705
10065
1st FL 1st FL
6000
ROAD ROAD
FL±0,00 FL-0.300 2 FL-0.300 FL±0,00
1000
2nd FL
5000 4065
2 2 2 2 2 FL+5,000
1200 10065
6000
ROAD 1st FL
2 2 2 2 2 FL-0.300 FL±0,00
15500 12000
2500 4000
27500
10000 10000 10000 10000 10000 10000 10000 10000 7500 10000 10000 10000 10000 10000 10000 10000 10000 10000 10000 10000
80000 90000 30000
200000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
ELEVATION - B 9'
SCALE 1 : 750
EXPANSION FACTORY EXISTING FACTORY SHOP DRAWING
ROOF: CORRUGATED METAL SHEET
ALC WALL PT. HAZAMA ANDO MURINDA
T.O.C 10000 MidPlaza 1 Building 16th Floor,
FL+10,065 Jl. Jendral Sudirman Kav.10-11 Jakarta 10220, INDONESIA
760
FL+5,000 2 2 2 2 2
9825
1st FL ROAD
FL±0,00 FL-0.300 2 2 2 1 2 2 EXPANSION FACTORY PROJECT
CANTILEVER SLAB CANTILEVER SLAB
12000 15500 DRAWING TITLE
2500
27500 ELEVATION - A, B & C
10000 10000 10000 10000 10000 10000 10000 10000 10000 10000 10000 7500 10000 10000 10000 10000 10000 10000 10000 10000
30000 90000 80000 SCALE 1 : 750
200000
SIGNATORIES
DESCRIPTION SIGNATURE DATE
21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 APPROVED BY Mr. Itogawa .
SIIX-2020 A-GA-06 06
FEB2020
136250 9150
6834
BOD D-1
FL-1.308 400 DESIGN W=600
300
BOD 0,3% P-1 P-1 P-1 P-1
PVC PIPE
0.3% 0,3% 0,3% 0,3% NO CONNECT
6000
20834
BOD BOD
∅250
FL-1.233 EX. W=300
PVC PIPE
FL-1.053 FL-0.900
FL-0.730
∅250
2000
PVC PIPE
PVC PIPE
16000
∅250
∅250
FL-0.750
0.2%
R50
00 PVC PIPE P-1 BOM (MH-2) FL-0.700
I ∅250 FL-0.750
FL-0.700
1 1
0.2%
8000
'A'
16000 13000
H
8000
BOD
FL-1.388
G
8000
0.2%
PHASE-2
42716
64000
20
STORAGE
19
18
17
16
15
14
13
FL±0,00
12
11
10
09
E
08
07
06
05
04
03
02
01
8000
BOD
FL-1.436
D
0.2%
'B'
SHOP DRAWING
8000
0 FL-0.700
BOD R500 BOM (MH-1) BOM (MH-1) BOM (MH-1) BOD
FL-1.470 FL-0.750 FL-0.750 FL-0.750 PT. SIIX EMS INDONESIA
FL-0.600
B EXPANSION FACTORY PROJECT
BOM (MH-2) P-1 BOM (MH-2) BOM (MH-2)
6000 1000 6000
PVC PIPE
FL-0.750 FL-0.750
16000
FL-0.750
0,2%
PVC PIPE
BOD BOD
∅250
BOD
22000
300
BOD
2934
FL-1.502
3799 3424 SIGNATORIES
BOD
BOD 0,3% 0,3% 0,3% FL-1.119 0,3% 0,3% DESCRIPTION SIGNATURE DATE
D-1
9000
BOD 1
9073
FL-1.512 1
D-1
6552
FL-1.283
12618
BOD APPROVED BY Mr. Ono
FL-1.733 Parlin
CHECKED BY
BOD BOD BOD
3424
3537
1 FL-1.830 FL-2.148 1 CHECKED BY Ghofur
45°
FL-2.038
CAD BY Syamsul 16SEP20
BOD BOD
FL-2.330 DRAINAGE PLAN FL-2.648 PROJECT CODE DRAWING NO. SHT. NO.
SCALE 1:500
SIIX EMS-2020 SD-EX-DR-01 -
PT. HAZAMA ANDO MURINDA
PT. SIIX EMS INDONESIA - EXPANSION FACTORY PROJECT
Overall Site Progress Photo
for Augustus 2020
PT. HAZAMA ANDO MURINDA
PT. SIIX EMS INDONESIA - EXPANSION FACTORY PROJECT
Overall Site Progress Photo
for September 2020
PT. HAZAMA ANDO MURINDA
PT. SIIX EMS INDONESIA - EXPANSION FACTORY PROJECT
Overall Site Progress Photo
for October 2020
PT. HAZAMA ANDO MURINDA
PT. SIIX EMS INDONESIA - EXPANSION FACTORY PROJECT
Overall Site Progress Photo
for November 2020
PT. HAZAMA ANDO MURINDA
PT. SIIX EMS INDONESIA - EXPANSION FACTORY PROJECT
Overall Site Progress Photo
for December 2020
PT. HAZAMA ANDO MURINDA
PT. SIIX EMS INDONESIA - EXPANSION FACTORY PROJECT
Overall Site Progress Photo
for January 2021