You are on page 1of 28

‫ راپور تفتیش ساحوی‬/‫راپور تخنیکی‬

Sayed Mir Agha Manawi


Senior Lecturer
manawi@pu.edu.af
Table of content ‫فهرست‬

Title ‫موضوع‬
Introduction ‫تشریح باز دید از ساحه‬
Finding/Observation ‫مشاهدات‬
1- Tools and equipment’s (bulldozer, shovel, ‫وسایل و ماشنری در ساحه‬
2- Construction material and its condition:
3- Quality assurance check: ‫چک نمودن کیفیت کار و مواد‬
- % of work is done / what is operation / no operational/ ‫فیصدی کار انجام شده‬
- % of remaining work/ fault in progress work ( concrete mix design, shuttering, plaster, mosaic, tiles, ………….,
trees, landscape slope, top view , other views, ‫فیصدی کار باقی مانده‬
Recommendation (Reward/ warning) ‫نتیجه و هدایات‬

Conclusion: (focus on the alarming issue put your recommendation any) ‫نتیجه نهایی‬
‫‪Technical/site inspection reports are used for controlling, checking construction process of a project or‬‬
‫‪inspecting the condition of a construction site/ landscape of what is being done so far. Technical report‬‬
‫‪is also evaluating the percentage of project items being completed.‬‬

‫راپور تخنیکی انجنیری یا راپور باز دید از ساحه پروژه ساختمانی عبارت از راپور است که در آن کنترول‪ ،‬چک نمودن پروسه‬
‫ساخت و ساز و یا تفتیش و بازدید از حالت پروژه ساختمانی ویا هر ساحه محیط زیستی باشد که تا فعال کدام کار در آن انجام داده‬
‫شده‪ .‬راپور تخنیکی انجنیری برای ارزیابی فیصدی کار انجام شده پروژه ساختمانی نیز استفاده میشود‪.‬‬
Finding/Observation ‫ موندنی‬/ ‫ یافته ها‬/ ‫باز دید از ساحه یا مشاهدات‬

Observing the existing work (completed, Continued and Not started yet) ‫مشاهدات در ساحه‬
1- Check the bill of quantity (BoQ) of the project ‫بل ارقام و مواد را چک کردن‬
2- Based on site take not of what item is completed ‫کدام کارها انجام شده مطابق بل کارهای پروژه‬
3- Do some small tests ( Test of breaks, Steel, plaster, slump test etc) ‫یگان تست های ساده ساحوی را برای چک مواد انجام دهید‬
4- Check the material on site! Are they on a good/usable condition) for example cement must be protected with plastic
sheets and must be positioned above the ground, steel must be clean with no corroded spots or dirt,
‫مواد های موجوده در ساحه ساختمانی باید چک شود که و باید در بهترین وضعیت مکانی و محیطی قرار داشته باشد‬
5- Check the technology of pouring concrete as check the portion of water in concrete ‫چک کردن مواد کانکریت کا باید شکل‬
.‫خمیر باشد یعنی کار آیی کانکریت چک شود‬
6- Take photos ‫تصاویر هر قسمت از کار پروژه را بگیرید‬
Item Actual Quantity
Description Of item Unit Quantity in BoQ
No Previous Payable To date
Mobilization at site is for the cost of establishing plant equipment facilities and
0.1 personnel upon the site. Lump sum 1.00 1.000 - 1.00

Demobilization from site is shall be compensation in full for the costs of removing
0.4 plant, equipment, facilities and personnel from the site . Lump sum 1.00 0.000 1.000 1.00

Environmental and Social Mitigation Measures shall be made as per actual


0.8 Pro. Sum 1.00 0.000 - -
expenditures against the measures proposed in the ESMP. The activities covered
under the sum
Excavation of are provideof
foundation with detailed
building break
in soil down
type in the ESMP
3 including attached
transpotion oftoextra
the
2.3 Cum 1,975.00 1,924.280 50.72 1,975.00
materials based on the design and specification with all required activities.
Back filling of building with compaction based on the design and specification with
2.3 all required activities. Cum 466.00 463.554 2.45 466.00

Filling of foundation of building by boulder thickness 20cm based on the design and
2.1 specification with all required activities: Cum 159.00 159.000 58.000 217.00

Filling by compacted Gravel as per drawing based on design and Specification with
2.3 Cum 197.00 195.000 2.000 197.00
all required activities
Sand for filling around the pit based on the design and specification with all required
2.7 Cum 8.00 0.000 - -
activities.
Stone masonry in foundation and above foundation, with morter 1:4 (cement-sand)
3.6 based on the design and specification with all required activities. Cum 370.00 355.260 14.740 370.00

Construction of Blinding Concrete of the, Required Strength in Foundations is 28


3.0 days cylinder crushing strength is minimum 10Mpa based on the design and Cum 120.00 113.530 6.470 120.00
specification of
Construction with all required
Reinforced activities.
Cement Concrete ( RCC) M 200 including shuttering and
3.0 steel cost based on the design and specification with all required activities. Cum 472.00 470.000 42.200 512.20

Construction of Reinforced Cement Concrete ( RCC) M 150 including shuttering and


3.0 Cum 29.00 20.000 29.560 49.56
steel cost based on the design and specification with all required activities:
Burnt Brick masonry with M1:4 based on the design and specification with all
3.5 required activities. Cum 402.00 382.080 19.92 402.00

Supply and installation of wooden doors and windows with steel grille and ironware
3.9 Sqm 24.00 0.000 64.220 64.22
Based on the design and specification with all required activities.
Pointing with morter 1:3(cement-sand) Based on the design and specification with all
3.6 required activities. Sqm 490.00 484.760 (484.76) -

Supply and installation of 4mm mesh according to drawing and specification with all
3.8 Sqm 56.00 56.000 - 56.00
required activities.
Supply and installation of stair from 18mm dia steel bar as per drawing and
3.8 specification with all required activities. No 1.00 0.000 - -

Dry Stone masonry in foundation based on the design and specification with all
3.6 required activities. Cum 11.00 0.000 - -
‫لست احجام کاری پروژه‬

‫‪ -1‬انتقال مواد به ساحه‬


‫‪ -2‬کندن کاری‬
‫‪ -3‬کار تهداب‬
‫‪ -4‬چک مواد چون سنگ‪ ،‬خشت‪ ،‬ریگ‪ ،‬جغل‪ ،‬سمنت‪ ،‬آب و تمامی مواد الزمی که در امور انجام پروژه استفاده میشود‪.‬‬
‫‪ -5‬سنگ کاری‬
‫‪ -6‬خشت کاری‬
‫‪ -7‬قالب بندی و سیخبندی و لین های سیستم برق‬
‫‪ -8‬پالستر‪ ،‬موزاییک‪ ،‬کاشی‬
‫‪ -9‬رنگ‬
‫‪.‬‬
‫‪.‬‬
‫‪.‬‬
Steel test ( Rebar, bar
‫چک کردن از ریخت و حالت کانکریت‬
‫‪Slump Test on site‬‬
‫تست کارایی کانکریت‬
‫تست ساحوی خشت از لحاظ محکمیت ‪Field Brick test ,‬‬

‫برای تست ساحوی خشت میتوانید یک خشت را بشکل افقی و یک خشت را در زیر آن بشکل‬
‫عمودی قرار دهید و به زمین از فاصله یک متری رها کنید و این کار را باالی سه جوره خشت‬
‫جداگانه که از قسمت های مختلف انبار خشت گرفته ایید انجام دهید‪ .‬در سه بار انجام این کار باید‬
‫دو تست جواب مثب بدهد یعنی خشت ها میده نشود و اگر از یک بار زیاد میده میشد بداند که‬
‫کیفیت خشت مشکل دارد اینکه‬
‫شاید خشت از قسمت های سر کوره خشتی بوده که بخار خشت های دیگر آنرا ضعیف الکیفیت‬
‫کرده‪.‬‬
‫ساحه کشی موجوده وسایل لکه ماشنری او نوری وسایل ) ‪1- Tools and equipment’s (bulldozer, shovel,‬‬

‫دست کش ندارد‬
‫مواد ساختمانی و حالت شان ‪2- Construction material and its condition:‬‬

‫مواد های موجوده در ساحه ساختمانی باید چک شود و باید در بهترین وضعیت مکانی و محیطی قرار داشته باشد از‬
‫قبیل ریگ‪ ،‬جغل‪ ،‬سمنت‪ ،‬سنگ‪ ،‬سیخ‪ ،‬خشت و تمامی مواد ساختمانی‬
‫‪Site Engineer of the project‬‬
‫?‬

‫منک یا پیمانه که حجم آن معادل حجم یک بوجی سمنت می باشد‬


Example
Oct-21-2020
THIS REPORT SHOWS THE REMAIING WORK OF NRAP BUIDLING/SOUTH REHION

1- Electricity

Electric sockets and air conditioners not installed yet


2- Plumbing

Fixtures for bath room and kitchen are not completely done!
3- Hand railing for Stairs

Not installed yet


4- Paint
First floor putten/filling is done but
second floor and basement + exterior
paint is pending
5- Installation of widows glass PVC partition between two
frame + doors not installed bathrooms are not done
6- Bar meshing for septic well
walls is not installed
7- Side walks are not poured yet
8- Internet Issue
‫)‪Recommendation (Reward/ warning‬‬ ‫هدایات او توصیه‬

‫‪1- Construction work slow, stopped, on planed so the work must be started as soon as possible‬‬
‫کار ساختمانی به شکل بطی روان است‪ /‬یا کار مطلقا توقف است و باید کارها در اسرع وقت شروع شود‬
‫)‪2- The ratio of the concrete was not correct so that ratio of concerted for mark 200M must be ( 1:1.4:2‬‬
‫نسبت مواد ریگ جغل و سمنت درست نبود فلهذا برای مارک ‪ 200‬باید نسبت مواد جغل ریگ و سمنت ‪ 1:1.5:2‬باشد‬
‫‪3- Gravel has dirt , so it must be washed before use in concrete‬‬
‫ریگ در بین خود الی و خاک داشت فلهذا باید ریگ و جغل قبل از استفاده خوب شتسته شود و بعد استفاده‬
‫آب موجود آب سیالب بود که قابل استفاده نمی باشد‬
‫خشت کاری به شکل منظم انجام شده بود ‪4- Break‬‬
‫سنگ کاری در بعضی قسمت ها مواد کانکریت اصال استفاده نشده بود که باید سنگ کاری تخریب شده و دوباره از سر با مواد که نسبت ‪5- Stone‬‬
‫های آن دیزاین شده اجرا شود‬
‫رنگ در قرارداد نوع برایتو است لیکن در ساحه از رنگ های گینت و محلی استفاده شده فلهذا باید رنگ از نوع برایتو استفاده شود ‪6- Paint‬‬
To conclude

1- Construction work of this project going smoothly, fairly, very good , not bad, in a best condition, bad,
so bad, on satisfactory.
This company should be given appreciation award or execute their payment as best implementer

2- Based on low quality and less technical education and the existing evidence, this company must be
fined/ introduced to responsibility authorities to take its construction working permit and should be
blacklisted.

‫نتیجه‬

‫ غیر مسلکی) جیریان داشت که باید این‬، ‫ بد‬،‫ قابل قبول‬، ‫ مناسب‬، ‫در آخر کار ساخت و ساز این پروژه به شکل (خوب‬
‫کمپنی به شکل عالی تمجید شود و مستحق تصدیق نامه ( این کمپنی نظر به بی کیفایتی و غیر مسلکی مطابق به این اسناد‬
) ‫موجود به ثارنوالی معرفی شود و کمنی مذکور را در لست سیاه پشنهاد میکنم‬

You might also like