DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.

11

NEW RICE MILL PROJECT PT.PADI FLOUR NUSANTARA


MOJOKERTO – INDONESIA

WEEKLY REPORT
MAIN CONTRACT WORKS
NO. 011
20th May –26th May 2019

Disetujui oleh : Diperiksa oleh : Disiapkan oleh :


PT. Padi Flour Nusantara PT. TeamworX PT. SINAR GUNUNG SEJATI

Project Manager Construction Manager Project Manager Quantity Survey

CONTENTS
1|PT. SINAR GUNUNG SEJATI
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.11

1. Executive Summary ……………………………………………………………………………………3


2. Progress of This Week ………………………………………………………………………………..3
3. Area of Concern Engineering……………………………………………………………………….7
4. Summary of Construction & Tracking Performance Progress ……..……………...8
5. Two Week-Look a Head Schedule ………………………………………………………….22
6. Progress Photo ………………………………………………………………………………..24
7. 3D Progress Review ………………………………………………………………………………..28
8. Equipment Report & Weather Report………………………………………………………..29
9. Man Power Report …………………………………………………………………………………30
10. Summary of Material On-Site ………………………………………………………….31

1. Executive Summary
( Completed and on-going Major Critical Works )

2|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.11

A. Production Building
1) Completed Work :
 Casting Concrete Tie beam at Zone C As Grid 37A B1-E1
 Excavation Boiler area at As Grid N1-M1
 Excavation Foundation area F3, and F5 at Zone A
 Fabrication Rebar Boiler, F3, F5, F7, and F8
 Erection Main Frame ( Rafter R1, Rafter R2, Steel Column SC1, Steel Column
SC2A) at Zone B as grid P-J1
 Connecting Steel Beam (SB1) to Steel Column (SC1) Zone A without 100% of
torque at Zone B as grid P-J1

2) On-going :
 Excavation Wet Process area in
 Installation Rebar Boiler, F3, F5, F7, and F8
 Casting Concrete F3, F5, F7, and F8
 Erection Main Frame ( Rafter R1, Rafter R2, Steel Column SC1, Steel Column
SC2A) at Zone C as grid J1-B1 in
 Connecting Steel Beam (SB1) to Steel Column (SC1) Zone A without 100% of
torque at Zone B as grid P-J1 in
 Excavation F5 at grid Q1-P

3) On- Schedule :
 Back Filling with imported Material at Zone C as grid 32A-39A;B1-D1 30th
May 2019
 Disposal Pile Concrete to elevation ground Slab in 09th June 2019
 Back Filling with imported material at Zone A as grid 37A-39A;Q1-S1 09th
June 2019
 Casting Slab Pit Bottom Slab Daily Bin 22nd Mei 2019
 Install form work PC and F3 wet process area at Zone B 15 th June 2019
 Fabrication and installation rebar

B. Finish Good Warehouse


1) Completed Work
 Fabrication rebar footplate and pedestal
 Un-install Roof at Grid F14 – F23
 Painting Steel Rafter (Brushing, Cleaning, Coating ) at Grid F14 – F23
 Cleaning FAMSUN Area

2) On-going

3) On-schedule
 Casting Concrete Footplate and Foundation 27th May 2019

3|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.11

 Un-install Roof at Grid F1 – F14 depend of FAMSUN tools


 Installation Anchor Bolt 26th May 2019
 Re-install rear canopy 26th May 2019
 Chiping Slab Grid F13-F23 10TH June 2019

C. Intake Building
1) Completed Work :
 Excavation Main Pit Area at grid 28 A - 29 A
 Excavation Foundation

2) On-going
 Casting lean concrete at Pit area
 Fabrication Rebar Pit and Foundation
 Install Form work side of Wall Pit
 Disposal existing rigid concrete

3) On-Schedule
 Casting Slab 1 Bottom of Pit Intake 28th May 2019
 Excavation Foundation Grid 28A - 31 A 28th May 2019
 Excavation Dock Area 29th May 2019

D. Silo
1) Completed work :

2) On- going :
 Sundries Construction Join Inc. Filler

E. Office Building

1) Completed work :
 Rebar fabrication
 Installing bottom rebar Continues Footing and Footplate at grid 37A - 38 A
 Installing Tie Beam rebar at grid 37A – 38 A

2) On- going :
 Casting Concrete Continues Footing
 Casting Tiebeam Concrete
 Fabrication and Installation Column Rebar and Balk at Ground Flour
 Casting Column Rebar Ground Flour

4|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.11

3) On-Schedule :
 Installation Form work and Support Column and Balk
 Casting Concrete Column 1st Floor
 Casting Balk concrete 1st Floor
 Installation Rebar column 1st Floor
 Install Deck Slab GF

F. WWTP
1) Completed work :
 Excavation at Zone 1
 Excavation at Zone 3
 Excavation at Zone 2
 Anti-termite Zone 1

2) On- going :
 Anti-termite Zone 3
 Anti-termite Zone 2
 Back Filling to Elevation of Bottom Slab with imported material at Grid W1-
W3 ; WB-WG
 Compacted and CBR 80% at Zone 1-3 , Grid W1-W3 ; WB-WG
 Casting LC at Zone 1-3 Grid W1-W3 ; WB-WG
 Fabrication Bottom Rebar and Retaining Wall Zone 1&3

3) On-Schedule :
 Installation Rebar of Retaining Wall and Ground Slab
 Casting Slab Concrete ( Bottom of Pit ) at Zone 1&3
 Installation Retaining wall form work at Zone 1

5|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.11

2. Progress of This Week


Recapitulation Progress of This Week :

1. Bill 01 Preliminaries : d. Deviation : 1.65 %


a. Plan of This Week : 2.60 %
b. Actual Progress of This Week : 0.00%
c. Progress until This Week : 1.80 % 5. Bill 06 Silo :
d. Deviation : 0.45 % a. Plan of This Week : 6.66%
b. Actual Progress of This Week : 0.00 %
2. Bill 03 Production Building : c. Progress until This Week : 6.18 %
a. Plan of This Week : 27.43 % d. Deviation : -0.48 %
b. Actual Progress of This Week : 0.73 %
c. Progress until This Week : 19.80 %
d. Deviation : -7.63 % *Deviation Refer to Rev1 Master
3. Bill 04 Finished Good Ware House :
Schedule
a. Plan of This Week : 0.75 %
b. Actual Progress of This Week : 0.17 %
*Rekapitulasi Terlampir
c. Progress until This Week : 0.75 % *Office Building and WWTP on- Process
d. Deviation : -0.58 %
Maping

4. Bill 05 Intake Building :


a. Plan of This Week : 0.00 %
b. Actual Progress of This Week : 0.00 %
c. Progress until This Week : 1.65 %

6|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

3. Areas of Concern Engineering

1) Perubahan elevasi pada embedded plate akibat tingginya slab existing pada saat setelah
pengecoran, gambar permohonan elevasi embedded plate pada Shop drawing ( SGS – STR –
CL-1024-E, SGS – STR – CL-1024-F, SGS – STR – CL-1024-G, SGS – STR – CL-1024-H)
,perubahan berdasarkan Reverensi Shop Drawing ( SGS – STR – CL-1024) dan RFI no. RFI-
SGS-013
2) Adjustable elevasi pada pedestal diarea Production Building, berkaitan dengan posisi frame
Clading agar sejajar dengan frame lainnya (SGS – STR – BP – 1008 ,1003,1004,1005)
3) SI additional work ( WWTP, Office, Car Park, Motorcycle Park, PLN Substation, Pump Room,
Weight Bridge, Waste Storage ) berdasarkan S.I No : 3637/SGS/003
*lampiran 01
4) Permit Excavation Warehouse, Excavation WWTP, Excavation Intake Building, Excavation
Office area, Installation Rebar Office Still not Ready.

7|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

4. Summary of Construction Tracking Performance Progress


4.1 Sumarry Progress & Critical Works ( Production Building )

a. Production Building

COMPLETE

ON-GOING

ON-SCHEDULE

8|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

b. Warehouse

COMPLETE

ON-GOING

ON-SCHEDULE

c. Silo

COMPLETE

ON-GOING

9|PT. SINAR GUNUNG SEJATI


DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

d. Intake

COMPLETE

ON-GOING

ON-SCHEDULE

e. WWTP

COMPLETE

ON-GOING

ON-SCHEDULE

10 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

f. Office

COMPLETE

ON-GOING

ON-SCHEDULE

11 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

3.1 Production Building


A. Tie Beam, and Foundation ( Footplate, and Pilecap )

COMPLETE

ON-GOING

ON-SCHEDULE

*All schedules refer to Executive Summary

12 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

B. Steel Beam Erection ( Production Building )

C. Steel Column Erection ( Production Building )

COMPLETE

ON-GOING

ON-SCHEDULE

*All schedules refer to Executive Summary

13 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

D. Steel Beam Erection ( Production Building )

COMPLETE

ON-GOING

ON-SCHEDULE

14 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

3.2 Ware House

A. Un-Install Roof and Wall Clading ( Warehouse )

COMPLETE

ON-SCHEDULE

UJ

15 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

COMPLETE

ON-GOING

ON-SCHEDULE

3.3 SILO

A. CASTING CONCRETE SLAB WITH FC’ 30MPA

EEE3
ZONA A
COMPLETED
SLAB ZONE A COMPLETE

ON-GOING

ZONA B COMPLETED ON-SCHEDULE

SLAB ZONE B

ZONA C1
FINNISH SLAB
ZONE C1

ZONA C2
FINNISH SLAB
ZONE C2

16 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

B. INSTAL EMBEDED PLATE

ON-GOING

*On-going install Embedded Plate with Chemical –

Anchor, Planning Finish work in 17th May 2019.

17 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

3.4 OFFICE

A.Rebar Continues Footplate Installation ( Office Building )

COMPLETE

ON-GOING
B. Excavation and LC ( Office Building )
ON-SCHEDULE

18 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

3.5 WWTP

A. Excavation WWTP

COMPLETE

ON-GOING

ON-SCHEDULE

B. Filling With Imported Material

COMPLETE

ON-GOING

ON-SCHEDULE

19 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO

4. PROGRESS PERFORMANCE
3.6 INTAKE BUILDING

20 | P T . S I N A R G U N U N G S E J A T I
D0P3A2neviati.69rgslctu
o%
WEEKLY PROGRESS REPORT NO.10

COMPLETE

ON-GOING

ON-SCHEDULE
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

21 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

5. Two Week Look A Head Schedules


Work for the next two weeks are follows :
Silo Area :
Any work at Silo Building has been completed
Production Building :

 Fabrication Rebar of Pit Rice Cleaning


 Casting Concrete Slab of Pit and Retaining Wall
 Back filling under Ground slab with Imported Material at Zone A,B, and C
 Casting LC under Slab
 Casting Concrete Slab
 Continues excavation Pit Rice Cleaning area
 Verticality check of any steel column has installed
 Grouting bottom of plate
 Fabrication component rice cleaning, wet process,and dry process steel structure

Warehouse Area :

 Un-install roof, rear and side canopy


 Excavation foundation area
 Excavation slab area
 Casting slab concrete
 Disposal side wall to elevation plan

Office Area :

 Casting Column and Balk concrete


 Casting concrete Slab 1st floor
 Install rebar of Slab at GF and 1st Floor
 Fabrication form work for column and balk
Intake Building :

 Finishing Excavation at main pit area


 Fabrication rebar for foundation and Retaining wall
 Fabrication form work pit area, footplate, and pedestal column
 Casting retaining wall Concrete
 Casting Concrete of Bottom Slab Pit

22 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

WWTP area :

 Filling with imported material on the top ground with 500mm layer, compacted CBR
min 80% at Zone 2
 Start Casting concrete LC with fc 15 Mpa
 Preparation Casting concrete for Backwall with fc 30 Mpa’ (incl. Integral)
 Fabrication rebar for foundation and Water Wall
 Fabrication formwork pit area, footplate, and pedestal column

23 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

6. Progress Photo

6.1. Production Building

24 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

6.3 WWTP

25 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

6.4 Intake Building

6.4 Office Building

26 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

6.5 FG Warehouse

27 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

7. 3D PROGRESS VIEW

COMPLETE

ON-GOING

ON-SCHEDULE

COMPLETE

ON-GOING

ON-SCHEDULE

28 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

8. Equipment Report & Weather Report

29 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

9. Man-Power Report (terlampir)

30 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10

10.Summary of Material On-Site

31 | P T . S I N A R G U N U N G S E J A T I