SUMMARY FOR TECHNICAL PROPOSAL

OKI ROAD LINK - OWNER REQUIREMENT


23-Mar-21
No Scope of Work Unit Owner Requirement
A. Site Observation Work
Observation work by visiting the site which
1 use while providing the technical and cost
proposal

B. Preliminary Work
Mobilization and demobilization for the
1
scope of work

C. Survey Work

1 Total length of road (sta 5.2 to sta 61.27) m'

Distance cross section to cross section along


2 m' maximum 25m
the length of road

a.) Minimum width is 50 m


b.) Minimum reading is following
3 Total area of survey work m2 record:
- 1 point of centre
- 3 point of each side

4 Permanent Benchmark
To use existing benchmark from OKI (to be
a.)
issued to bidder)

- Consultant shall install


permanent benchmark 9 nos (at
Any benchmark created by Consultant, to
every communication tower) for
b.) be verified by OKI team and preserved by Nos
handover to OKI
Consultant team
- Temporary benchmark as per
the need from Consultant

5 Survey equipment
- Total station Nos
- Theodolite Nos - Total time period for
- GPS Nos topography survey is one month
- To use minimum 2 nos of GPS
- Hand GPS Nos geodetic and 4 nos of total
- Fotogrametri Package station
- Precise level / Automatic level Nos
- DGPS drone Nos

D. Soil Investigation

1 Dynamic Cone Penetration Test (Sondir) Nos The minimum is every 1 km

(subject to discussed on tech


2 Site CBR Test (Dynamic Cone Penetrometer) Nos
clarification)
The minimum is every 1 km
3 CPTu Nos (subject to discussed on tech
clarification)
(subject to discussed on tech
4 Bore Hole Work
clarification)
a.) Bore Hole Work by machine
- Number of Bore Hole Nos 60
- Depth of Bore Hole per point m' 15 - 30
- Number of sample per point Nos 1-2
- Number of SPT per point Nos 10 - 20
b.) Bore Hole Work by manual
- Number of Bore Hole Nos -
- Depth of Bore Hole per point m' -
- Number of sample per point Nos -
4 Equipment plan
- Number of bore hole machine to be
Nos
mobilized

- Number of DCPT (sondir) to be mobilized Nos

- Number of CPTu to be mobilized Nos - Total time period for soil


investigation (including final
- Number of site CBR Test (Dynamic Cone report) is 2.5 months
Penetrometer) to be mobilized Nos

5 Lab Test
- The quarry location is 3 area
- Index properties Nos which will be informed by Owner
- Engineering properties Nos
6 Quarry
- Material location will be informed by
Client
- Laboratory test Nos

E. Hydrology work lumpsum


1 Hydrology analysis
The hydrological data shall be
- Rainfall intensity collected by Consultant and to
- Drainage analysis be reported on final design
- Temperature (day and night) report, specifying data source to
be written in the report
- Humidity
- Flooding

F. Data Provided by Client


Road train (Single and Double Trailer)
1
(current and future)
Total traffic per day (forestry data) (current
2
and future) Have been given to Consultant
3 Sample photos for road condition except for point F.5
Existing soil investigation at warehouse area
4
and mill site area
5 Quarry location (being used currently)
except for point F.5

6 Existing road cross section data

G. Design Concept
1 Geometric design
- Long section
- Cross section
2 Pavement design
3 Road foundation design
4 Road stability analysis
- Consolidation settlement analysis
- Side sliding analysis
5 Hydrology analysis
- Rainfall intensity analysis based on certain
period
The Consultant design must
6 Design of drainage system ensure the adequate drainage
system
The relevant national and
7 Design code and standard
international standard code
(subject to discussed on tech
8 Design lifetime years
clarification)
9 Document
- Design report
- Construction drawings
- Technical specification
- Blank BOQ and cost estimation All the deliverable should be
- Construction schedule included

- Preparation for bidding document


including to assist the Client in tender stage

- Maintenance recommendation

The Consultant must present the


10 Meeting on site during design phase progress during past week
during weekly progress review.

H. Construction Method
The concept of construction not to stop the
1
operation
The design to adopt the availability of
2
material construction in the market

I. Design and Supervision Schedule


a. Design Schedule (Total)
1 Survey days or months
2 Soil Investigation days or months 16 weeks. Subject to discuss
- Soil investigation during technical clarification
meeting
16 weeks. Subject to discuss
during technical clarification
- Lab Test meeting
- Reporting
3 Design days or months
b. Construction Suprevision Schedule The construction supervision to
1 Construction Supervision days or months be put as an option

J. Experience for similar issue

1 CV for expertise including the certification

2 Project experience for similar project

(subject to discussed on tech


K. Manpower
clarification)
1 Manpower for survey
- Lead Survey engineer Person
- Survey engineer Person
- Draftsman Person
- Assistant surveyor Person
2 Manpower for soil investigation
- Geotechnical engineer Person
- Bore master Person
- Technician Person
3 Manpower for design
- Project coordinator / Team Leader Person
- Co Team Leader Person
- Road engineer / Highway engineer Person
- Geotechnical engineer Person
- Hydrology and drainage engineer Person
- Draftsman Person
- Document control Person

4 Manpower for construction supervision

- Engineers Person
5 Any other recommended engineer
- Estimator Person
To be proposed the HSE
- HSE engineer Person Supervisor

General Notes :
1.) The Consultant to ensure the safety during the execution of field work without disturbing the operation
2.) The Consultant to include the Covid protocol in the commercial proposal

…….......... , …...........................
PT XXXX
(Name)
(Position)
100 m/nos RALAT: "Dynamic" ini menyatakan DCP. Klo Sondir namanya "Dutch"

12 nos
250 m/nos RALAT: bukan CPTu TAPI: CPT/Sondir 2.5 ton capacity

1000 m/nos

TIDAK DIPERHITUNGKAN PEKERJAAN HAND BORING (BORE BY MANUAL)


sturbing the operation