Professional Documents
Culture Documents
Neom 10 Spine Infrastructure: 10-661120-1100001342-MAG-CIV-MST-000005 Rev.01 Page 1 of 18
Neom 10 Spine Infrastructure: 10-661120-1100001342-MAG-CIV-MST-000005 Rev.01 Page 1 of 18
NEOM ‐10 SPINE INFRASTRUCTURE
Work Order No. 003
Work Order Title RD 12
Contract No. 1100001342
Contract Title Masco Preparation Framework
Document Title WO 03‐Method Statement for Double Handling of Excavation
Materials‐RD12
Revision No. 01
Date 26 September 2021
Reason for Issue Approval
02
03
Originator internal Review and Approval
Originator Name Position Signature
Document approval
PREPARED BY:
TABLE OF CONTENTS
1. SCOPE OF WORK
2. MACHINERY AND EQUIPMENT
3. MATERIALS
4. WORK PROCEDURE
4.1 General
4.2 Work Execution
5. RESPONSIBILITIES.
6. HEALTH AND SAFETY.
7. QUALITY ASSURANCE.
8. RISK ASSESSMENT.
Excavation(Cut and Topsoil)
Satisfactory Unsatisfactory
materials materials
Disposal Disposal
Processing
Haulage
Double
Handling
Crushing Screening
Backfilling
/Embankment
1. SCOPE OF WORK
1.1. To ensure that all excavation and cutting are executed safely and in accordance
with the contract requirements and that all quality assurance / control activities
are conducted in a systematic manner, works are inspected and conformance is
verified and documented.
1.2. To ensure that disposal and haulage of materials and related activities are
executed safely and in accordance with the contract requirements and that all
quality assurance / control activities are conducted in a systematic manner,
works are inspected and conformance is verified and documented.
2. MACHINERY AND EQUIPMENT
The major equipment used for construction of Box Culvert, but are not limited to the
following: -
3. MATERIALS
The major materials used for Excavation, but are not limited to the following: -
- Warning Tapes
- Temporary Sign Boards
- Temporary Road Signs
- Safety Barriers
- Traffic Cones
- Grade Stakes
4. WORK PROCEDURE
4.1. General
4.2. Work Execution
4.2.2. Setting out- A survey team will take levels and set out the excavation area by
use of pegs to mark points on the ground.
4.2.3. Upon acceptance of the setting out by the Engineer, excavations will be started
after the acceptance of the Engineer.
4.2.4. During the progress of excavation, material taken from the cut and topsoil areas
shall be sectioned as following: -
4.2.4.1. Unsatisfactory Soils: -
- Soils outside the Limit of Work (Classification Groups GC, SC, CL, ML, OL, CH, MH,
OH, and PT according to ASTM D 2487 or Groups A-2-6, A-2-7, A-4, A-5, A-
6, and A-7 according to AASHTO M 145, or a combination of these groups) in
the opinion of the Engineer, are potentially unsatisfactory and liable to slide
or encroach into the Limit of Work.
- Dispose and collecting of Unsatisfactory Soils outside of the Excavation section. A
disposal plan shall be submitted to the Engineer.
- Haulage of Unsatisfactory Soils outside of the project. A Haulage plan, including
written permission from the owner(s) of the property used for material
Haulage and distance shall be submitted to the Engineer.
4.2.4.2. Satisfactory Soils: -
- Soils cut from the excavations and shall be used as Embankments, subgrade,
shoulders, slopes, bedding and backfill (Classification Groups GW, GP, GM,
SW, SP, and SM according to ASTM D 2487 or Groups A-1, A-2-4, A-2-5, and
A-3 according to AASHTO M 145, or a combination of these groups; free of
rock or gravel larger than 75 mm in any dimension, debris, waste, vegetation,
and other deleterious matter. Plasticity Index: <20%).
- Dispose of satisfactory Soils outside of the Excavation section to: -
* Processing area: If material suitable (According to Specs) to be used direct, material
shall be disposed and collected in stockpiles and mixed with water to be
Double handling as Embankment, subgrade, shoulders, slopes, bedding and
backfill.
* Processing area: If material contain rock or gravel larger than 75 mm in any
dimension, material shall be disposed to be screened with Mesh “70 X 70 mm”
and collected the passing material into stockpiles, mixed with water to be
Double handling as Embankment, subgrade, shoulders, slopes, bedding and
6. HEALTH AND SAFETY
6.1. Prior to the commencement of any activities, the workforce will receive an induction
talk on the project Safety Manager. This induction talk will include both activity safety
issues, as well as general safety requirements.
6.2. Where possible hazards may arise from placing of select fill material activities, the
necessary safety measures will be taken to prevent accident or injury at all times.
This may include barriers, warning tape/ net, signage, flagman, and proper lighting.
6.3. Safety Officer will enforce that Personal Protective Equipment be worn by site
personnel at all times during construction activities.
6.4. Heat Stress Training will be provided.
6.5. Provisions of adequate cool drinking water, shade, and salt water tablets will be in
place.
6.6. Equipment will be provided back‐up alarms, lights, and all other applicable safety
devices.
6.7. Permit Requirement
6.7.1. Prior commencing the construction activities, information about all existing
underground services such as gas, water, telephone lines, sewage lines,
electrical cables, etc. shall be obtained from concerned agencies.
6.7.2. Work permit will be as per the Engineer Program procedure.
7. QUALITY ASSURANCE
7.1. All checking, inspecting and testing shall comply with applicable standards specified and
as indicated in specification and drawings.
7.2. The quality control procedures shall satisfy all technical requirements providing the
same degree of quality test and other quality control procedure specified.
7.3. All records and reports shall be arranged and maintained to ensure traceability between
material and test reports.
7.4. All testing equipment shall comply with applied standards and shall be available on the
project site in complete calibrated condition.
8. RISK ASSESSMENT
RISK ASSESSMENT MATRIX
CONSEQUENCE
RISK MATRIX 5 4 3 2 1
Catastrophic High Medium Low Insignificant
LIKELIHOOD
5 H H S M M
ALMOST CERTAIN
25 20 15 10 5
4 H H M M L
LIKELY
20 16 12 8 4
3 S
POSSIBLE M M M L
15
12 9 6 3
2
UNLIKELY M M M L L
10 8 6 4 2
1
M L L L L
RARE
5 4 3 2 1
RISK MATRIX CATEGORY DEFINITIONS (COLOR CODE)
HIGH/UNACCEPTABLE
Stop work immediately, secure area and report hazard to the superior for
rectification and control.
Any existing Method Statement must be reviewed and authorized before the work
commences.
If NO Method Statement exists, secure and provide MS in conjunction with JSEA for
SA approval before work commence.
SIGNIFICANT
MODERATE
Record and report new hazards and control actions are already taken prior
commences work.
LOW / ACCEPTABLE
Record and report new hazards and control actions are already taken prior
commences work.
CONSEQUENCE OF HAZARD
02 Obtain work permit from All the utility services should be marked
MASCO before starting the work.
Ensure inspection has been conducted
Damage to property on the whole are.
4 4 16 2 2 4
The manhole should protect by steel
plates if any equipment has to work on
that otherwise barricade should be
around the manholes.
No unauthorized entry.
Trainings like induction, toolbox talks
should be provided before starting the
work.
Physical or serious Injuries to workers 3 5 15 All the utility services should be marked 1 3 3
before starting the work.
Ensure inspection has been conducted
on the whole are.
COMMUNICATION FORM
I, THE UNDERSIGNED HEREBY ACKNOWLEDGE THAT THIS JOB SAFETY ENVIRONMENTAL ANALYSIS HAS BEEN DISCUSSED WITH ME AND THAT I UNDERSTAND
THE CONTENTS AND THE RISKS INVOLVED IN THE TASK TO BE PERFORMED. I HAVE ALSO BEEN INSTRUCTED ON THE SAFE METHODS TO PERFORM THIS TASK.
1
2
3
4
5
6
7
8
9
10