Professional Documents
Culture Documents
650
98 DT.20.09.2014 .
EXG.GL 98.980
5000 6. FOR LEVELLING COURSE - M-10, PLAIN CONCRETE WORKS - M-20 AND RCC WORKS - M-25 OF WEIGH
200
200
5825
5825
97 AX)
0(M
IN 2
4500 E1 BATCHING OF CONTROLLED CONCRETE SHOULD BE USED.
SLO S LOP
96 PE 1
7175
950
AX)
500
500
CROSS SECTION OF EMBANKMENT 8. EXCEPT FOR ROCK A SAND GRAVEL MIXTURE LAYER OF 200mm TO BE SPREAD AND WELL CONSOLIDATED
94 103.96m 6m 18.580m 6m 117.14m
(NOT TO SCALE)
250 4500 BELOW THE RCC BASE SLAB.
PRO. ROAD LEVEL 94.105 93
1350
650
9. A GAP OF 20mm TO BE PROVIDED IN BETWEEN TWO BOXES. AFTER ERECTION OF BOXES IN ALIGNMENT
100.010
100.000
120 99.960
100 99.800
99.600
-120 99.320
-100 99.250
99.200
99.180
99.270
99.950
99.930
99.810
99.510
99.390
99.520
99.670
EXG.RL
250
AND AFTER ALLOWING INITIAL SETTLEMENT OF BOXES THE GAP BETWEEN THE BOX JOINTS ARE TO BE
6500 DISTANCE(m)
-80
-60
-40
-20
PRESSURE GROUTED WITH CEMENT / EPOXY SUITABLY.
20
40
60
80
-4
4
250 TH CC PRE-CAST RCC BASE
200 TH. COARSE TO MEDIUM SAND WITH
SLAB IN M.25 GRADE
GRAVEL MIXTURE TO BE WELL COMPACTED 10. SUITABLE BED SLOPE IN THE BARREL LENGTH OF THE BOX TO BE GIVEN IN THE WEARING COURSE.
BEFORE PLACING THE BASE SLAB UNITS.
LONGITUDINAL SECTION OF ROAD
11. NO CONSTRUCTION JOINTS SHALL BE NORMALLY ALLOWED IN CONCRETE WORKS WITHOUT SPECIAL
HALF ELEVATION AND HALF SECTION
KAR
LHS SITE PLAN PRECAUTIONS AS PER RELEVANT BRIDGE CODE AND SUITABLE PROTECTIVE PAINTING OF APPROVED MAKE
UV
[NOT TO SCALE]
SHOULD BE USED TO PAINT THE UNDERSIDE OF CONCRETE.
ELA
B
20550
HEIGHT
MPA
C.L.OF LUS GAUGE
20000
12. SUITABLE HEIGHT GAUGES TO BE PROVIDED AT THE BEGINNING OF THE APPROACHES AND LUS ON EITHER
TTI
IOC Building SIDES.
C
L OF PRO. SUBWAY
HEIGHT GAUGE 13. NECESSARY GUARD RAILS TO BE PROVIDED AT THE LUS LOCATION.
HEIGHT GAUGE
10000
Ty.SHORING 14. THE ENGINEER-IN-CHARGE WILL PROVIDE ADEQUATE FOUNDS TO SUIT THE SBC OF SOIL.
6000
SLOPE
TY.C.C.CRIB AS PER PLACING OF PRE-CAST BOX UNITS BY CRANE OR ANY OTHER MEANS FOR THEIR CAPACITY BEFORE
PRO. PRE-CAST RCC. BOX
m
CULTIVATION FIELD
1000
117.14
DRAIN 1x4500x4500 AS PER CASTING THE RCC BOX UNITS / BEFORE PLACING THE BOX UNITS IN FINAL POSITION.
ALT - 2
1 IN 2
DRG.NO.CBE/TP/258/2012-Sh-2
16. THIS WORK WILL BE CARRIED OUT BY CUT AND CONNECTION AND OPEN EXCAVATION METHOD UNDER
RCC RETAINING WALL
0
SIMILAR TO DRG.NO. LINE / POWER BLOCK OF REQUIRED DURATION WITHOUT ANY TEMPORARY ARRANGEMENTS FOR TRACK
RAILWAY BOUNDARY
1 IN 20
SLOPE
4200
MDU END
18.580m
CL OF BG TRACK VPT END L
C OF BG TRACK MODUS OPERANDI:-
20
PRO. DOUBLING
6m
17.50m PRELIMINARY:-
RAILWAY BOUNDARY
1 IN
RAILWAY BOUNDARY KEEP READY THE PRE-CAST BASE SLABS AND PRE-CAST BOX UNITS NEAR THE SITE. IMPOSE
SLOPE 1 IN 20
KM 506/000 KM 506/100
103.96m
NON-STOP AND TEMPORARY SPEED RESTRICTION OF 20 Kmph WITH NECESSARY TEMPORARY
18580
3400
ENGINEERING INDICATORS AT THE APPROACHES.
P Q UNDER LINE BLOCK:-
CULTIVATION FIELD CULTIVATION FIELD
6000
DISCONNECT THE TRACK TO THE REQUIRED LENGTH. CUT OPEN THE FORMATION TO THE REQUIRED
6000
SPEED BREAKER
6m LENGTH AND DEPTH ACCORDING TO SITE CONDITION.
10m HEIGHT GAUGE
FILL UP SAND GRAVEL MIXTURE FOR 200 THICK AND RAM IT WELL. LAY THE PRE-CAST BASE SLABS
500
AND PRE-CAST RCC BOX UNITS IN POSITION BY USING CRANE. FILL THE SIDES UP TO FORMATION
EXG.WIDTH 6.00 m
PRO.PRE-CAST RCC BOX
675 LENGTH OF
500
SPEED INDICATOR
(20 kmph) @ 506.010
T
20
PRO.ROAD LEVEL 94.105
12 NOS OF 1530 LONG RCC BOXES WITH
20
INDICATOR @ STAGE I:
LONGITUDINAL SECTION
KM 507.260 PRELIMINARY:-
LENGTH OF
4500 TERMINATION INDICATOR
LONGEST GOODS 30 m
PLAN OF TY.GIRDER ARRANGEMENT 1. IMPOSE SPEED RESTRICTION OF NON-STOP 20 KMPH DULY PROVIDING ENGINEERING
@ KM 505.363
5000 TRAIN [677 m] 1200 INDICATORS AS SHOWN. KEEP READY ONE SET OF TY.GIRDER. ALSO SUFFICIENT NO OF
4500
20
6990
2. DISCONNECT THE TRACK TO THE REQUIRED LENGTH. CUT OPEN THE FORMATION TO THE
650
TEMPORARY SIGNALLING ARRANGEMENTS REQUIRED LENGTH AND DEPTH ACCORDING TO SITE CONDITION AND ERECT SLEEPER
BASE SLAB IN M.25 GRADE
250 TH CC PRE-CAST RCC
(NOT TO SCALE)
CRIBS "P & Q" AS SHOWN.
3. INSTALL TY.GIRDERS OVER THE CRIBS "P & Q" LINK THE P-WAY AND ALLOW THE TRAFFIC.
LEVEL
18580
DUTY CRANE OF 120 T CAPACITY (MIN) CRAWLER TYPE) ALONG WITH STANDBY CRANE OF
675
RDSO/B-1484/5 ALT - 2
EXG.GL 98.980 TY.C.C.CRIB AS PER DRG.NO. SAME CAPACITY.
256
650
RDSO/B-1484/5 ALT-2 5. FOR GAD REFER DRG NO. LUS/13/16 ALT-1 SHEET 1 OF 2
508
9. FILL THE SIDES UP TO FORMATION LEVEL AND CONSOLIDATE FULLY.
5000 10. LINK THE TRACK AND ALLOW TRAFFIC AT RESTRICTED SPEED.
600
600
6. THIS WORK WILL BE CARRIED OUT BY CUT AND CONNECTION AND OPEN EXCAVATION METHOD
500
650
200
200
BETWEEN TRAINS:
254
254
500
6500 1800x3600 300 1800x3600 UNDER LINE / POWER BLOCK OF REQUIRED DURATION WITH TEMPORARY GIRDER ARRANGEMENTS 11. COMPLETE ALL OTHER WORKS INCLUDING CONSTRUCTION OF PARAPET WALLS AND
4500
W 3400 X 4200
6000
300
O LAYING OF WEARING COURSE.
6000
3400x4200
7175
P
FORMATION LEVEL 99.255
600x600x600
SUPERVISION OF ENGINEER IN CHARGE
4682
00mm
IPE 2
RCC P
RAIL LEVEL 99.930
250
4500
00°
45.
20
Ty.SHORING
650
1 IN
250
234
4448
200
300
RAILWAY BOUNDARY
103.96m
6500
1 IN 20
RCC RETAINING WALL ELEVATION OF TY.GIRDER ARRANGEMENT SOUTHERN RAILWAY वववववव ववववव
MADURAI DIVISION ववववव वववव
CC ROAD
DEN /SOUTH
DRN BY
वववववव [A.THIRUMAL]
ववववव
1000
DRAIN
[V.MURUGAN]
MADURAI - VIRUDUNAGAR (BG) SECTION Sr.DEN / Co.or.
RAIL PEGS @ 600 THIS LC WILL BE CLOSED PERMANENTLY AFTER COMPLETION OF
SPEED 6000 600 C/C
LIMITED USE SUBWAY VIDE DISTRICT COLLECTOR CHD BY
BETWEEN TIRUPPARANKUNDRAM AND TIRUMANGALAM ववववववव
/व [D.SARANGAPANI]
BREAKER 2000
10000 ----------------- LR NO : ---------------- DT -------------- वववव STATIONS
ADRM
वववववववव
234235
[P.V.MURALI KRISHNA.]
PRO. CONSTRUCTION OF A DRM
BOTTOM OF FOUNDATION
A
NEW LUS NO. 1519A (1 x 4.50mX 4.50m) RCC BOX [SUNIL KUMAR GARG.]