You are on page 1of 2

Change Order Request (03)

Project Title: PALM TILLS NEW CAIRO PHASE 1 CONSTRUCTION OF HARD SCAPE Request Date 14-11-2021
PHD Project Manager: ENG.AHMED SALEM Contract Ref.: CPD-CA-PHNC-129-12-2020
Contractor G.M: ENG.AHMED MAHER VO Scope (Civil-Arch-MEP): MEP

Reason of Variation:
Addition of new scope Addition of new items
Design change Contractor’s proposal
Change in Quantities Others (Specify)

Change Request Description:

FILTER OF GRAVITY WALL


price before (L.E)   price after (L.E)
  GW-01 GW-02 GW-03     GW-01 GW-02 GW-03
cementinous
composite filter 200 294 343   water proofing 138 188 225
(SIKA 107)
crushed stone 27 42 52   crushed stone 54 90 114
Geotextile (300 Geotextile (300
105 147 161   175 266 325
GM/M2 GM/M2
 
TOTAL 332 483 556 TOTAL 367 544 664
 

Cost Implication: (Yes / No )


Amount:
Time Schedule Implication: (Yes / No )
Description:
Time will be issued

Reference documents: (contract clause, letters, drawings, etc…)


Attachments:
*Price Comparison
*RFI ARCH Serial.33
*DS MECH. Serial.178
Initiated By
Contractor General Manager
Name: ENG.AHMED MAHER

Authorized
Signature:
Date: 14-11-2021