PROJECT MANAGER’S INSTRUCTION (PMI)

(NOTIFICATION / COMMUNICATION )

Project Scope: ARCHITECTURAL WORKS PMI No.:


231004-107
Contractor: GREENHOME

Subject: GENSET PAD LOCATION Date Requested:


2023-10-04
Pls tick as appropriate :

Instruction Notification Communication

You are hereby instructed (notified/sent communication) to:


Commence the parts of the works Deal with an object of value or interest

Change the Works Information Implement a change decision

Change a key date Others, specify:

Stop Work SUBMIT QUOTATION

Not start work

Cost Implication

Additive Cost Deductive No Cost Implication

Structure / Area
GENSET
As detailed below:

See attached plans for reference

Issued to: GREENHOME


Authorized Representative to Receive: ENGR. MAX

Contractor Sub-Contractor PIC File Others: ______________________

Attachments:

Drawings Specification/detail Cost Evaluation Billing Others: PHOTOS

Prepared By: Endorsed By:

GMG FMK3 – AR. CHITO


Date: 2023-10-04 Date:
Recommended By: Approved By:

JML Phoebe Sy / Charry Sy


Date: Date:
Received By:

GREENHOME – Engr. MAX

P a g e 1|1
0.705

2.46
1.05
T P AD
S E
GEN 2.435m)
1.30 m x
(1.05

2.435
0.705