1. Contractor : PT. OKTAVIARY BINTAN FAMILI 2. Period of Work : 1 (SATU) HARI 3. Manpower : VERY ARGANA SAPUTRA 1 (SATU) ORANG 4. Crane/Equipment : MOBILE CRANE 5. Lifting Gears : SLING, SHACKLE 6. Work Description : ERECTION AND STRINGING PIPE SPOOL USING CRANE 45 T ( INCLUDE LOADING UNLOADING 7. Time : 09.00 WIB To 12.00 WIB 8. Name of Supervisor in-charge : MR. AHMAD DJUMARI 9. Name of Safety in-charge : MR. EDI WARSONO
B Attachment Remarks
1 Is the rigging procedure available? √ Yes No
2 Are the rigging plan & drawing available? √ Yes No 3 Is the load calculation available? √ Yes No 4 Is the JSA/RA available? √ Yes No 5 Is the equipment checklist available? √ Yes No 6 Are the lifting gears documents available? √ Yes No
C Precautions Remarks
1 Is the PPE as required available? √ Yes No
2 Are the warning / caution signs displayed? √ Yes No 3 Does the road need to be blocked? √ Yes No 4 Are there any obstructions to the lifting operation? Yes √ No 5 Are there any potential of falling object? Yes √ No 6 Has the JSA/RA been briefied to all involved? √ Yes No 7 Has the crane been checked? √ Yes No 8 Are communication devices available? √ Yes No
Operating MPI/NDT Confirmed Acknowledged by Client(if Applicable)