Risk Assessment -Bore well digging work

S.NO Activity Hazard Risk Counter Measure Resp


1-Basic PPE to be used while working. (Goggle ,Helmet ,Safety Gloves Anuj Sharma
,Safety Shoe, Gum Boot, ,Safety Mask for COVID-19 etc ) .
2-Site Area to be restricted and barricade for unauthorized person.
Barricading of working Human Injury,Manual
1 Human Injury 3-Temporary Light to be provided to ensure sufficient lux level at site if
area handling
required.
5- Contractor Supervisor will monitor the labors and will keep on talking
them to ensure their wellness.
1- Good condition of suction pump or Tanker will be used for removing GPSPL Team
Human Injury,Manual
2 Bore well digging Human Injury, Raw water from tank.
handling
2-Raw water will be shifted to Gutter directly to STP Plant.
GPSPL Team
1- Labor will go inside the under ground tank to collect the Mud /sand
Respiratory problem,
Removal of Mud/sand dust contamination, and will shift out side through bucket manually.
3 Eye Infection,
from bore well Manual Handling 2- Sand /Mud will be kept open area at out side the pump house
Human Injury
3-Labour will ensure all required PPE as mentioned above.

1- Basic PPE still to be used while working. GPSPL Team


Removing of barricading Eye Infection,
4 Manual Handling 2-Surrounding area must be cleaned from unwanted materials after
nearer to tank area . Human Injury
completion the Job.

NOTE:-
1.ALL THE REQUIRED PPE WILL BE USED WHILE WORKING.
2.JCBIL SHALL DEPUTE A SAFTEY OFFICER THROUGH OUT THE WORKING PROCESS.
3- Date and time to do work :-

Prepared by : Utility Deptt Reviewed by : Deptt Head Approved by :Safety Deptt