You are on page 1of 3

Egyptian Drilling Company

QM-HSSE Dept.

SAFE JOB ANALYSIS (SJA)

Procedure Reference: Remove & Install mud tank agitator SJA No.: M-45 RIG: 53

Potential Person Responsible for


Hazards: Potential hazard or threat Controls: List controls/safe guards that are
Task: The steps involved in doing the job. that is associated with each step e.g. Consequence: List in place to prevent reduce or mitigate potential Controls: List the Responsible
DROPS, . potential consequences if risk/threat. person(s)/position(s) responsible for
control is not in place the control measure.

1-Preparing for the job.


* Misunderstanding 1. PTW and IC using locks and
* Using incorrect tool tags.
* Using defect tools 2. Confined Space enter check list
3. Stop agitators.
4. Pre-Job Safety Meeting. Senior mechanic
5. Check Gases by competent
person.
6. Wear Proper PPE.
7. Ensure that the confined space
rescue kit is on the mud system
2- Open drain valve handle Depended on the volume of the 1. Use Proper PPE
mud inside the tanks reference to 2. Use proper tools
how fare to open the valve. 3. Wear safety goggles.
Personal Injury 4. Never stand in front of the Senior mechanic
gate.
5. Worker standing at a safe
distance.
3-Open tank hatch. 1- Fall into Open Hatch. 1. Wear rubber gloves.
2- Tripping hazard. 2. Install rescue in
Personal Injury confined spaces kit on Senior mechanic
tank hatch.

SJA Form
Rev. 06/AUG16
Egyptian Drilling Company
QM-HSSE Dept.

4-Workers enter the tank. 1-Worker slipping off ladder. Personal Injury 1- Appointed watch man.
2-Worker slipping on the tank 2- Max time for the man inside the
floor. tank should be one hr.
3-Workers inhale gasses. 3- Washing of ladder before entering.
4--Tripping Hazard. 4- Wear rubber boots and rubber
Senior mechanic
gloves.
5- Wear safety harness.
6- Apply LOTOTO system.
7- Watch steps during descending.
8- Use good condition foot wear.
5-Remove bolts of main shaft flange & bolts of 1-Worker slipping on the tank Personal Injury -Max time for man inside the tank
agitator base. floor. should be one hour.
2-Worker inhale gasses. 2-Wear safety harness.
3-Tank environment measured & Senior mechanic
monitored.
4-Use Proper PPE
5-Use proper tools
6-Remove the agitator by using crane. 1-Agitator damaged. Personal Injury 1-Worker inside tank goes out the
2-Agitator hit workers. Material damage tank before start loading the agitator.
2-Use tag line. Senior mechanic

7-Install agitator in the tank (install bolts of


1-Worker slipping on the tank
Personal Injury 1-Worker inside tank goes out the tank
main shaft flange & bolts of agitator base. before start loading the agitator.
floor.
2-Worker inhale gasses.
2-Use tag line. Senior mechanic
3- assign banks ma
4- competent person
8-Worker goes outside tank Personal Injury 1- Maintain good housekeeping.
2- Ascending the ladder slowly.
. 3- Watch steps during ascending.
1-Tripping Hazard. 4- Follow 3 points rule during
2-Worker slipping off ladder. ascending the stairs. Senior mechanic
3-Worker slipping on the tank 5- WGS & SL to check the working
floor. area before signing off the PTW.
6-Remove all equipment from work
area.

SJA Form
Rev. 06/AUG16
Egyptian Drilling Company
QM-HSSE Dept.

Comments and Conclusions: Inadequate procedure/Deviation from standing procedure to be highlighted and additional recommendations listed

Task Team Leader shall answer the below questions before approving the SJA:

This SJA is a new or a revised SJA? Have changes been made to the original
New  Revised  YES  NO 
SJA?
In case of a revised SJA: Have all the significant hazards, controls
Are there any changes in the conditions or job steps? YES  NO  and responsibilities involved with the work YES  NO 
been identified by the preparation team?
Are there any modifications that require MOC?
YES  NO 
If yes please attach a copy of the MOC

SJA Team Members preparing/reviewing SJA

Name Position Signature Date


Sr.Mech

N.Mech

HSE

Reviewed By: Team Leader (Work Group Supervisor/PA) Approved By: PIC

Name: Name:

Position: Sr.Mech Position: STP

Signature Signature

Date: Date:

SJA Form
Rev. 06/AUG16