SEPCOII DATE: 11 January 2018

JOB SAFETY ANALYSIS (J S A)


II (DAY&NIGHT)
JSA No .05 Rev:01
YNABU-PHASEIII
POWER PROJECT
PROJECT: Yanbu Power & Desalination Project Phase 3
CONTRACTOR NAME: GSSE

LOCATION: ADDRESS: Yanbu KSA


CONTRACT NO: SA005-SS-001-00

JOB DESCRIPTION : Scaffold Erection & Work at Heights


EMERGENCY ACTION PLAN:
One team member with first aid qualifications.
Mobile communication in area at all times -
Access into area for emergency vehicle to be kept clear.-YES
PLANNED HIGH RISK CONSTRUCTION ACTIVITY
Radio Graph
MANUAL EXCAVATION Confined Space Entry Hazardous Substance use Work in/over water
Test
Critical/Heavy
HOT WORK Tilt up/precast use Structural Alterations Scaffold Erection lift/Non-Engineered
Lift
Demolition
Work at Heights Magnetic Particle Test Flammable/contaminated atmosphere
work
REVIEWED BY: HSE MANAGER:(FOR SUBCON) APPROVED BY: CONSTRUCTION MNGR: (FOR SUBCON)
N
No. Name Position Signature Date o. Name Position Signature Date
Bilal Mustafa HSE Project
1 Manager 1 Musawar Jamil Manager
Rana
REVIEWED BY: SEPCO-III DISCIPLINE MANAGER:
Name Position Signature
Date

REVIEWED BY: SEPCO-III HSE MANAGER:


Name Position Signature Date
JSA No.05 Rev:01
JOB SAFETY ANALYSIS ( JSA)
Scaffold Erection & Work At Heights

Approved By SEPCOIII Construction Manager


Name Position Signature Date

P.P.E REQUIREMENTS PLANT, EQUIPMENT & TOOLS TAGGING & SIGNS PERMITS/INSTRUCTION
“Check ” FOR JOB “Check ” “Check ”
“Check ”
Persons
Air Purifying Excavat
Safety Harness Ladder Working MSDS’s
Respirator or
Above
Confined
Static Line Space Hand Tools Winch Barrier Mesh Instruction Manual
Harness
Tinted Safety Extensio
Gloves – PVC Shovel Flagging HV Access
Glasses n Leads
Clear Safety Coated fabric Welding Personal Floor/Roof
Backhoe
Glasses Gloves Machine Locks Opening
Gloves - Power Personal
Goggles Compactor Hot Work
Leather Source Danger Tags
Out of
Face Shield Dust mask Drill Crane Lockout/ Tag out
Service Tags
Information
Sun Screen Grinder EWP Excavation
Tags
Hearing
Scaffold Fans Signage Confined Space
Protection
Fire
Scissor High Pressure /
SCBA Extinguish Barricades
Lift Abrasive Blasting
er
Fire Suspended
Airline Man lift
Blanket Personnel Platform
Skills/Competencies/Authorisations
“Check ”
EWP boom > 11m Excavator Rigger II Asbestos removalist
JSA No.05 Rev:01
JOB SAFETY ANALYSIS ( JSA)
Scaffold Erection & Work At Heights

LIKLIHOOD CLASSIFICATIONS Front End


Scissor Lift
LEVEL Rigger III Light Vehicle
Loader
Consequence unheard of:/not known to have occurred; very unlikely to occur under LIKELIHOOD
Unlikely
Concretenormal
Placing Boom
conditions. Backhoe Dogger Heavy Rigid
Consequence know to have occurred in construction industry; unlikely to occur in normal
Rare Forklift Type and
conditions. Unlikely Rare Possible Likely Very Likely
Personnel Hoist has occurred within
Consequence Capacity: 3 may occur under normal
the company; Grader operating Scaffolder I Articulated
Possible
conditions. Tonnes
Consequence occur several times per year within the company; very likely to occur at CONSIQUENCE 1 2 3 4 5
Material Hoist
Likely Loader Scaffolder II Modular Transporter
sometime under normal operating conditions.
VerySkid
Consequence occurs several times per year at similar projects/locations; can be
likely Steer Scraper Scaffolder III 5
reasonably expected to occur under normal operating conditions. Catastrophic 5Boat 10 15 20 25

4
Major 4 8 12 16 20

CONSIQUENCE CLASSIFICATION 3
Serious 3 6 9 12 15
SEVERIT SAFETY AND HEALTH ENVIRONEMENT REPUTATION PORPERTY
Y LEVEL FINANCIAL 2
Company/client Medium 2 4 6 8 10
First aid or minor Insignificant impact, fully / local
Minor loss
Minor injury/illness no medical contained on site (Env. community 1
treatment Level 3) concern, no
( $10 K) Minor 1 2 3 4 5
media attention
Medical
Negligible short-term Community
treatment/restricted
impact confined on site. concern with Medium loss
Medium- work day case,
No regulatory local media ($10<$100K)
temporary health
exceedance (Env. Level 3) attention
effect.
State or
Lost time injury/illness Moderate to significant
provincial Risk Acceptance Thresholds
or moderate (<30% of impact confined on site,
concern with Serious loss
Serious body) permanent regulatory exceedance or
regional ($100<$1M) Low Risk: (1-6)Risk is considered broadly acceptable. No further risk reduction is
disability to one or any off site impact Env.
media/commun required. Risk is managed as part of the ESH general project procedures and
more people Level 2
ity attention
periodically confirmed that the risk continues to remain low. Further risk reduction is
Single fatality or severe
Serious impact on or off at management discretion
(>30% of National
site or potential Major
Major body)permanent media/commun Medium Risk: (7-14) Risk is acceptable if reasonable safeguards and controls are in
enforcement action Env. loss($1M<$10M)
disability to one or ity attention place to reduce the hazard to ALARP. Responsibility is to be assigned for proactive
Level 2
more people
management with active monitoring defined as part of the ESH general project
Multiple fatalities or Very serious impact, long
permanent disability/ term liability, or procedures.
Catastrop International Catastrophic loss
significant irreversible irreversible damage, High Risk: (15-25) Intolerable risk that must be eliminated or reduced by controls to
hic media attention (>$10M)
health impact of 3 or enforcement action. Env. ALARP immediately. Where the risk remains at this level following the identification
more people Level 1
of all practical controls a formal plan is to be developed that assigns responsibility
for the implementation of controls and a means of proactive monitoring
JSA No.05 Rev:01
JOB SAFETY ANALYSIS ( JSA)
Scaffold Erection & Work At Heights
JSA No.05 Rev:01
JOB SAFETY ANALYSIS ( JSA)
Scaffold Erection & Work At Heights

JOB STEP
DESCRIPTION POTENTIAL HAZARD
STEP HAZARD CONTROL METHOD Likeli Sever Risk RESPONSIBLE
List the potential hazards that
List the control measures required to eliminate
NO. List the steps required to could cause injury/damage when
or minimise the risk of injury
hood ity (SxP)=R PERSON
perform the task in the the task step is performed (L) (S)
sequence they are
carried out

 Ensure all people authorized to


work at site, JSA communication
TOOL BOX meeting should be
completed in respect to task & area
proper supervision. Tool box Site Engineer, Site
Preparation for the Slip trip falling and cut meeting attendance/JSA and Supervisor, Work
1 task injuries Permit must be available at working 2 2 4
Crew, PTW Co-
location. Ordinator
 Permit required.
 Checklist for Work at Heights has
been signed by the Area
Supervisor and the Area HSE
Officer.
2 Transportation Slip trip and falling hazards  While transporting materials must 4 Site Engineer, Site
2 2
Risk of accidents on the be tired properly. Supervisor, Work Crew
way of transportation  Loading trucks must be position
under controlling of flagman, and
flagman must be maintaining 20mtr
rule at site. He is always standing
JSA No.05 Rev:01
JOB SAFETY ANALYSIS ( JSA)
Scaffold Erection & Work At Heights

JOB STEP
DESCRIPTION POTENTIAL HAZARD
STEP HAZARD CONTROL METHOD Likeli Sever Risk RESPONSIBLE
List the potential hazards that
List the control measures required to eliminate
NO. List the steps required to could cause injury/damage when
or minimise the risk of injury
hood ity (SxP)=R PERSON
perform the task in the the task step is performed (L) (S)
sequence they are
carried out
with the eye contact of driver. The
truck parking area must be
compacted.
 Provide escort and flagman for the
vehicles. Red flag or light should be
reflected on the extended part of
the structure from the vehicle.

Unloading of  Only trained and authorized


EQUIPMENT personnel can allow doing the job.
 Trained flagman shall be giving the
signals for positioning the vehicle in
unloads area the Vehicle parking
area must be compacted and
Pinch points,
inspected. Unloading area must be
Material collapse,
barricaded and unauthorised Site Engineer, Site
3 hit, 2 3 6
personnel cannot allow entering the Supervisor, Work Crew
personnel injury &struck
material handling area. Crane
positioned area must be compacted
and use correct rated pads. After
un loading the materials provide the
proper barricading along with sign
boards.

4
Falling Objects, Heat  Scaffold Erection must be carried 6 Site Engineer, Site
Scaffolds Erection & 2 3
Stress, Electrical Hazard, out by TUV Certified erectors. Full Supervisor, Work Crew
Work At Heights
Body Injury body harness with double lanyard
is mandatory. Tools must be
JSA No.05 Rev:01
JOB SAFETY ANALYSIS ( JSA)
Scaffold Erection & Work At Heights

JOB STEP
DESCRIPTION POTENTIAL HAZARD
STEP HAZARD CONTROL METHOD Likeli Sever Risk RESPONSIBLE
List the potential hazards that
List the control measures required to eliminate
NO. List the steps required to could cause injury/damage when
or minimise the risk of injury
hood ity (SxP)=R PERSON
perform the task in the the task step is performed (L) (S)
sequence they are
carried out
secured with the tagline. Electrical
lines must be kept away from the
scaffolds to avoid any
electrocution for the safety of
erectors Drink plenty of water to
avoid de-hydration. Use proper
and safe manual handling
techniques.
 Always make sure the Life-Line is
installed and properly inspected.
 Always instruct the Scaffold
Erector to anchor the Lanyards of
his Safety Harness properly.

5
Collapse Hazard  After erection of scaffolds, make
Scaffold Inspections
Personnel injury sure the inspection by the
Asset Damage qualified scaffolding inspector.
Proper tags must be fixed with the
Site Engineer, Site
signatures and contact details of 2 3 6
Supervisor, Work Crew
the Inspector. DONOT use the
scaffold without SCAFFTAG
installed on it or if it is RED
TAGGED.
Falling and Tripping  Proper housekeeping must be
Site Engineer, Site
6 House Keeping Hazard carried out before and after the job 2 3 6
Supervisor, Work Crew
and it must be maintained.
JSA No.05 Rev:01
JOB SAFETY ANALYSIS ( JSA)
Scaffold Erection & Work At Heights