7.2 Dolok Penggaron Drainage Design, Feasibility Study, DHV, October 1992
In order to solve problem of floods in the Penggaron and Dolok River Systems, the Study by DHV in 1992 proposed
the followings (source: Semarang Flood Control Project, Consolidated Preparation Study, under IBRD Loan,
November 1999):
Source: Semarang Flood Control Project, Consolidated Preparation Study, under IBRD Loan, November
1999 by SMEC and Associated Indonesian Consultants
Figure 7.2.1 Proposed Design Discharge of the DHV Study, 1992
1) Design flood:
KBT: 100-year return period of flood
Babon River together with Dombo-Sayung River: 50-year return period of flood
2) Closing the inlet gate of the KBT
3) Diverting the floodwater of the Penggaron River by the Babon River with the new
Dombo-Sayung River
The proposed design discharges by the JICA Study is shown in Figure 7.3 .2.
Unit:m3/s
Proposed by Jratunseluna Project
Penggaron River
(630)
New Hydraulic Structure
630
(120)
120
0 230
(430) (660)
(780)
350
Pucang Gading Weir
(200)
420
East Floodway
Babon River
Sea Sea
Source: The Master Plan on Water Resources Development and Feasibility Study for Urgent Flood Control
and Urban Drainage in Semarang City and Suburbs, Japan International Cooperation Agency (JICA),
November 1993
Figure 7.3.2 Proposed Design Discharge of the JICA Master Plan and Feasibility Study,
1993
Stage 1:
1) Design flood:
KBT: 25-year return period
Babon River together with Dombo-Sayung River: 25-year return period
Dolok River: 25-year return period
2) Closing the inlet gate of the KBT
3) Discharging the floodwater of the Penggaron River into the Babon River and the
new Dombo-Sayung River
4) Diverting the excess floodwater of 160m 3/s from the Penggaron River into the Dolok
River through the Kebon Batur Floodway (reverse flow direction of the current
Kebon Batur Channel)
Stage 2:
1) Design flood:
KBT: 50-year return period
Babon River together with Dombo-Sayung River: 50-year return period
Dolok River: 50-year return period (Stage 1 + Dolok Dam)
2) Closing the inlet gate of the KBT
3) Discharge the floodwater of the Penggaron River by the Babon River with the new
Dombo-Sayung River
4) Diverting the excess floodwater of 230m 3/s from the Penggaron River to the Dolok
River through the Kebon Batur Floodway (reverse flow direction of the current
Kebon Batur Channel)
Design discharges of the Stage 1 and Stage 2 are shown in Figure 7.4 .3.
Stage 1 Stage 2
Source: Semarang Flood Control Project, Consolidated Preparation Study, under IBRD Loan, November 1999 by
SMEC and Associated Indonesian Consultants
Figure 7.4.3 Proposed Design Discharge of the IBRB_SMEC Study, 1999
7.5 Detail Desain Sistem Sungai Dolok Penggaron (Kanal Banjir Timur
– Dombo Sayung), PT.Jasapatria Gunatama, November 2009
The “Detail Desain Sistem Sungai Dolok Penggaron (Kanal Banjir Timur – Dombo Sayung), PT.Jasapatria
Gunatama, November 2009” (hereinafter called as the DD Study) proposed the flood control plan for the KBT,
Babon, Dombo-Sayung Rivers as follows:
1) Design flood: 50-year return period for the KBT, Babon and Dombo-Sayung rivers
2) Improvement of KBT to discharge 124m 3/s (from the inlet gate) to 423m 3/s in the
downstream reach
3) Improvement of the Babon River to discharge 246m 3/s (from the Pucanggading
Weir) to 350m3/s in the downstream reach
4) Improvement of the Dombo-Sayung River to discharge 210m 3/s
5) Enlargement of the discharge capacity of the Pucanggading Weir of the Babon River
to discharge 246m3/s
6) Enlargement of the discharge capacity of the Gergaji Weir of the Dombo-Sayung
River at Pucanggading to discharge 210m3/s
The proposed design discharges by the DD Study is shown in Figure 7.5 .4.
Source: Detail Desain Sistem Sungai Dolok Penggaron (Kanal Banjir Timur – Donbo Sayung),
PT.Jasapatria Gunatama, November 2009
Figure 7.5.4 Proposed Design Discharge of the DD Study, 2009
内容
エラー! 文書が自己参照を行っています。 1
Chapter 7. REVIEW OF THE EXISTING FLOOD CONTROL PLANS 7-1
7.1 Previous Flood Control Studies and Plans 7-1
7.2 Dolok Penggaron Drainage Design, Feasibility Study, DHV, October 1992 7-1
7.3 JICA Master Plan and Feasibility Study in 1993 7-2
7.4 Semarang Flood Control Project, Consolidated Preparation Study, under IBRD Loan, November
1999 by SMEC and Associated Indonesian Consultants 7-4
7.5 Detail Desain Sistem Sungai Dolok Penggaron (Banjir Kanal Timur – Donbo Sayung),
PT.Jasapatria Gunatama, November 2009 7-5