1. ASH has mention in beginning of project that there is no access to side elevation due to
AC Pipe should be concealed to not affect the elevation. As attached photo
2. No access to start working at side elevation as mentioned on our progress meeting
dated 30th March 2021
3. Main contractor has refused starting work till approved the variation.
4. Client Representative requesting ASH to issue Work order to contractor to start work.
5. ASH has issue work order dated 30TH March 2021.
6. Main contractor has started dated 3rd April 2021. As attached photo
7. Work will be handed over to ASH dated 8th April 2021.
8. ASH Will resuming to work for side elevation on 10 th April 2021
We understand that access will be increase for the next [ 29] days as mentioned on below
schedule, to help in your planning, we provide to you this further update. Although we are
certain that you are working diligently to solve this access problem, we thought that you would
appreciate knowing that the project schedule, showing the Delay Analysis for the impeded tasks
Planed Planed
Execution Work
Apply Enhancement Elevation hood 16- Feb -2021 10- Mar -2021 11- April -2021 29
deep galvanized treated CNC panels as
1 mentioned on approved design.
3 Apply Aluminum decorative strip panels 11- Mar -2021 14- Mar -2021 15- April -2021 29
with indirect light.
3 Supply and apply all electrical work i.e. 15- Mar -2021 19- Mar -2021 19- April -2021 29
strip light, indirect light for light under
the decorative.
4 Supply and installation Acrylic Lighting 19- Mar -2021 21- Mar -2021 20- April -2021 29
Logo, client will confirm the design.
Accordingly, we request an extension of time , We assure you that we will do everything we can
to minimize those time extension and handing over the project.
Your cooperation will be appreciated.