Schedule Deepwell

MONTH Dec-21 Jan-22 Feb-22 Mar-22


WEEK 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5
1. Preparation
- Survey Geolistrik
- Drilling Permitt ( SIP ) XX XX XX XX XX XX
- Mobilization of Drilling Equipment to the Project Site XX
- Setting & Placement of Drilling Machines at Drill Points XX
- Water & Electrical Preparation XX
2. Drilling Works
- Drilling XX XX XX XX XX XX
- logging test XX
- Reamer hole XX
- Cleaning hole XX
3. Deep Well Construction & Finishing
- Casing pipe installation XX XX
- Pump installation XX
- Pumping Test XX
-Test Lab Water XX
4. Utilization Permitt ( SIPA )
- Submitting an Application for a Groundwater Utilization Permit (SIPA) XX XX

55%
= Progress Actual

WORK PLAN ACTUAL % DEV Weeks Dev


Deepwell 55% 55% 0% 0