You are on page 1of 6

Type - 1

General
Length = 6 m
Width = 6 m
Area = 36 m²

Pedestal size a = 500 mm


b = 600 mm

Foundation SIze A = 1750 mm


B = 2000 mm
Thickness of Foundation C = 500 mm

FGL to HPP = 300 mm


Bottom of Foundation = 1500 mm
No. of Pedestal / Foundation = 4 Nos

Loads
Member spaced = 1.5 m
DL (Gratings) = 0.35 kN/m²
Mid Span = 0.53 kN/m
End Span = 0.26 kN/m

RCC Qty
Foundation Qty = 7 m³
Pedestal Qty = 1.56 m³
Bliding Concrete = 1.716 m³
Reinforcement = 1.0272 MT

Steel Qty
Grating Qty = 36 m²
Structural Steel = 2.8 MT

Support Reaction
Node L/C Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm
Max Fx 3 101 DL + L 10.523 48.165 0 0 0 -13.295
Min Fx 4 105 DL + L -13.073 49.089 0 0 0 18.323
Max Fy 4 105 DL + L -13.073 49.089 0 0 0 18.323
Min Fy 1 102 DL + W -1.859 2.241 0 0 0 4.155
Max Fz 1 101 DL + L 10.523 48.165 0 0 0 -13.295
Min Fz 1 103 DL + W 0.691 3.165 -3.45 -11.4 0.043 -0.873
Max Mx 1 101 DL + L 10.523 48.165 0 0 0 -13.295
Min Mx 1 103 DL + W 0.691 3.165 -3.45 -11.4 0.043 -0.873
Max My 1 103 DL + W 0.691 3.165 -3.45 -11.4 0.043 -0.873
Min My 2 103 DL + W -0.691 3.165 -3.45 -11.4 -0.043 0.873
Max Mz 4 105 DL + L -13.073 49.089 0 0 0 18.323
Min Mz 3 101 DL + L 10.523 48.165 0 0 0 -13.295
Type - 2
General
Length = 6 m
Width = 6 m
Area = 36 m²

Pedestal size a = 500 mm


b = 650 mm

Foundation SIze A = 1750 mm


B = 2000 mm
Thickness of Foundation C = 500 mm

FGL to HPP = 300 mm


Bottom of Foundation = 1500 mm
No. of Pedestal / Foundation = 4 Nos

Loads
Member spaced = 1 m
DL (Chequered Plate) = 0.6 kN/m²
Mid Span = 0.60 kN/m
End Span = 0.30 kN/m

RCC Qty
Foundation Qty = 7 m³
Pedestal Qty = 1.69 m³
Bliding Concrete = 1.716 m³
Reinforcement = 1.0428 MT

Steel Qty
Grating Qty = 36 m²
Structural Steel = 3.2 MT

Support Reaction
Node L/C Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm
Max Fx 3 101 DL + L 10.523 48.165 0 0 0 -13.295
Min Fx 4 105 DL + L -13.073 49.089 0 0 0 18.323
Max Fy 4 105 DL + L -13.073 49.089 0 0 0 18.323
Min Fy 1 102 DL + W -1.859 2.241 0 0 0 4.155
Max Fz 1 101 DL + L 10.523 48.165 0 0 0 -13.295
Min Fz 1 103 DL + W 0.691 3.165 -3.45 -11.4 0.043 -0.873
Max Mx 1 101 DL + L 10.523 48.165 0 0 0 -13.295
Min Mx 1 103 DL + W 0.691 3.165 -3.45 -11.4 0.043 -0.873
Max My 1 103 DL + W 0.691 3.165 -3.45 -11.4 0.043 -0.873
Min My 2 103 DL + W -0.691 3.165 -3.45 -11.4 -0.043 0.873
Max Mz 4 105 DL + L -13.073 49.089 0 0 0 18.323
Min Mz 3 101 DL + L 10.523 48.165 0 0 0 -13.295
Type - 3
General
Length = 6 m
Width = 6 m
Area = 36 m²

Pedestal size a = 500 mm


b = 700 mm

Foundation SIze A = 2000 mm


B = 2000 mm
Thickness of Foundation C = 500 mm

FGL to HPP = 300 mm


Bottom of Foundation = 1500 mm
No. of Pedestal / Foundation = 4 Nos

Loads
Member spaced = 2 m
Wt of Deck sheet = 0.076 kN/m²
Wt of Deck slab (125mm thick) = 3.125 kN/m²
Mid Span = 6.40 kN/m
End Span = 3.20 kN/m

RCC Qty
Foundation Qty = 8 m³
Pedestal Qty = 1.82 m³
Bliding Concrete = 1.936 m³
Reinforcement = 1.7184 MT
Slab Qty = 4.5 m³
Deck sheet = 36 m²

Steel Qty

Structural Steel = 2.45 MT

Support Reaction
Node L/C Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm
Max Fx 3 101 DL + L 10.523 48.165 0 0 0 -13.295
Min Fx 4 105 DL + L -13.073 49.089 0 0 0 18.323
Max Fy 4 105 DL + L -13.073 49.089 0 0 0 18.323
Min Fy 1 102 DL + W -1.859 2.241 0 0 0 4.155
Max Fz 1 101 DL + L 10.523 48.165 0 0 0 -13.295
Min Fz 1 103 DL + W 0.691 3.165 -3.45 -11.4 0.043 -0.873
Max Mx 1 101 DL + L 10.523 48.165 0 0 0 -13.295
Min Mx 1 103 DL + W 0.691 3.165 -3.45 -11.4 0.043 -0.873
Max My 1 103 DL + W 0.691 3.165 -3.45 -11.4 0.043 -0.873
Min My 2 103 DL + W -0.691 3.165 -3.45 -11.4 -0.043 0.873
Max Mz 4 105 DL + L -13.073 49.089 0 0 0 18.323
Min Mz 3 101 DL + L 10.523 48.165 0 0 0 -13.295
Type - 1 T

S.No Description Qty Unit Rate Amount S.No

Civil

1 Earth work excavation 36.66 m³ 140 5132.4 1

2 Blidng Concrete 1.716 m³ 3200 5491.2 2

3 RCC - Footing 7 m³ 5700 39900 3

4 RCC - Pedestal 1.56 m³ 5700 8892 4

5 Reinorement 1.0272 MT 68000 69849.6 5

Total (Civil) = 129265

Strucutral Work Struc

6 Grating 36 m² 110 3960 6

7 Structural Steel 2.8 MT 72000 201600 7

Total (Structural) = 205560

Total Amount = 334825

Area of the Building (m²) = 36

Rate per Sq.m = 9301

% of Civil Work 38.61


% of Structural Work 61.39
100.00
Type - 2 Type - 3

Description Qty Unit Rate Amount S.No Description

Civil Civil

Earth work excavation 36.66 m³ 140 5132.4 1 Earth work excavation

Blidng Concrete 1.716 m³ 3200 5491.2 2 Blidng Concrete

RCC - Footing 7 m³ 5700 39900 3 RCC - Footing

RCC - Pedestal 1.69 m³ 5700 9633 4 RCC - Pedestal

Reinorement 1.0428 MT 68000 70910.4 5 Reinorement

Total (Civil) = 131067 6 Deck Slab (125 thk)

Strucutral Work 7 Deck sheet

Chequered Plate 36 m² 150 5400

Structural Steel 3.2 MT 72000 230400 Strucutral Work

Total (Structural) = 235800 8 Structural Steel

Total Amount (round off) = 366867

Area of the Building (m²) = 36 Total Amount (rou

Rate per Sq.m = 10191 Area of the Buildi

% of Civil Work 35.73


% of Structural Work 64.27 % of Structu
100.00
Type - 3

Qty Unit Rate Amount

Civil

40.56 m³ 140 5678.4

1.936 m³ 3200 6195.2

8 m³ 5700 45600

1.82 m³ 5700 10374

1.178 MT 68000 80131.2

4.5 m³ 6200 27900

36 m² 750 27000

Total (Civil) = 202879

Strucutral Work

2.45 MT 72000 176400

Total (Structural) = 176400

Total Amount (round off) = 379279

Area of the Building (m²) = 36


Rate per Sq.m = 10536

% of Civil Work 53.49


% of Structural Work 46.51
100.00